View Cruise

  Schedule Information  
Ship: Knorr Schedule Status: Final Schedule ID: 10300
Schedule Year: 2008 Schedule Name: Set 1
Notes: Changes:
10/27: End Pickart on 31
9/24: added a port day and shifted D'Hondt a day later
9/23: add a day for WHOI testing of equipment
9/15: stop in Sisimiut for replacement releases for Lee
4/28: Added 6 days to Bower transit to Nuuk for Straneo moorings in Hudson Strait.
4/16: Moved Bermuda port stop to arrive June 27 and depart 29th.
4/9: Added 2 days to Reykjavik port stop (April 24 to May 1) for repair of bow thruster. Lee/Perry and Cutter cruises shifted 2 days later.
3/5: Departure from Charleston/shipyard changed to March 11th arrive into WHOI March 14. Depart for Bates March 19.
1/14: Added Daly/Wakeham and D'Hondt cruises to the end of the year
1/9: Johns mooring recovery has been removed from the schedule. Knorr will transit directly to the shipyard in Charleston.
  Cruise Information  
Ship Request Information
Operator Cruise ID:
Chief Scientist: Mary Jane Perry, Maine
Activity Type: At Sea for Science
Created By: Elizabeth Caporelli
Compare Request:
Project Short Title: Autonomous measur
Requested Year: 2008
Requested Ship: Global  
Request Type: Primary  
Created By: Craig M. Lee  
Load Non-charge Days: 0
Load Charge Days: 2   Load Date: 4/29/2008
Activity Days: 22 Adjustment Days Start Date: 5/1/2008
Transit Days: 0 0 End Date: 5/22/2008
Unload Charge Days: 1   Unload Date: 5/23/2008
Unload Non-charge Days: 0
Mob Days: 0  
Science Days: 22 Optimum Start Date: 5/1/2008
Transit Estimate: 0 Earliest Start Date: 4/25/2008
Demob Days: 0 Latest Start Date: 5/1/2008
Repeating Cruise: No Dates To Avoid:
Number of Repeating Cruises: 0 Repeating Interval:
Repeating Cruise Comments:
Justification/Comments: Optimum date: start 05/01/08 / Alternate date: start 04/25/08
PI   Project/Purpose   Agency   Funding Status   Op Days
Craig M. Lee, UW_APL   Autonomous measur   NSF/BE   Funded   25
  Start Port: Reykjavik, Iceland
  End Port: Reykjavik, Iceland
Requested Start Port: Reykjavik, Iceland
Intermediate Port(s): None
Requested End Port: Reykjavik, Iceland
Port Comments: Requested Ports: Start - Reykjavik/Intermediate - none/End - Reykjavik
  Lat/Long Marsden Grid Navy Op Area
Beginning
NA05 map
Ending
NA05 map
 
Op Area Description:
  Lat/Long Marsden Grid Navy Op Area
Beginning
NA05 map
Ending
NA05 map
 
Op Area Description:
Coastal States Requiring Clearance: Iceland(T)
Foreign Clearance Required: No
Iceland
Foreign Clearance Comments:
Ancil Facilities:
Instrumentation Requested:
Instrumentation Comments:
Ancil Facilities Requested:
Ancil Facility Comments:
External Cruise Webpage:
Cruise Notes: Mary Jane Perry is Chief Sci, Eric D'Asaro is PI.