  Schedule Information  
Ship: Knorr Schedule Status: Final Schedule ID: 10300
Schedule Year: 2008 Schedule Name: Set 1
Notes: Changes:
10/27: End Pickart on 31
9/24: added a port day and shifted D'Hondt a day later
9/23: add a day for WHOI testing of equipment
9/15: stop in Sisimiut for replacement releases for Lee
4/28: Added 6 days to Bower transit to Nuuk for Straneo moorings in Hudson Strait.
4/16: Moved Bermuda port stop to arrive June 27 and depart 29th.
4/9: Added 2 days to Reykjavik port stop (April 24 to May 1) for repair of bow thruster. Lee/Perry and Cutter cruises shifted 2 days later.
3/5: Departure from Charleston/shipyard changed to March 11th arrive into WHOI March 14. Depart for Bates March 19.
1/14: Added Daly/Wakeham and D'Hondt cruises to the end of the year
1/9: Johns mooring recovery has been removed from the schedule. Knorr will transit directly to the shipyard in Charleston.
  Cruise Information  
Ship Request Information
Operator Cruise ID:
Chief Scientist: Robert S. Pickart, WHOI
Activity Type: At Sea for Science
Created By: Elizabeth Caporelli
Compare Request:
Project Short Title: Shelf-basin exchange
Requested Year: 2008
Requested Ship: Knorr  
Request Type: Primary  
Created By: Robert S. Pickart  
Load Non-charge Days: 0
Load Charge Days: 2   Load Date: 10/1/2008
Activity Days: 29 Adjustment Days Start Date: 10/3/2008
Transit Days: 0 0 End Date: 10/31/2008
Unload Charge Days: 1   Unload Date: 11/1/2008
Unload Non-charge Days: 0
Mob Days: 0  
Science Days: 28 Optimum Start Date: 9/1/2008
Transit Estimate: 0 Earliest Start Date: 9/1/2008
Demob Days: 0 Latest Start Date: 9/1/2008
Repeating Cruise: No Dates To Avoid:
Number of Repeating Cruises: 0 Repeating Interval:
Repeating Cruise Comments:
Justification/Comments: Optimum date: 9/1/08 - 9/28/08 / Alternate date: 8/1/08 - 8/28/08
PI   Project/Purpose   Agency   Funding Status   Op Days
Robert S. Pickart, WHOI   Shelf-basin exchange   NSF/OCE/PO   Funded   32
  Start Port: Reykjavik, Iceland
  End Port: Reykjavik, Iceland
Requested Start Port: Reykjavik, Iceland
Intermediate Port(s): None
Requested End Port: Reykjavik, Iceland
Port Comments: Requested Ports: Start - Reykjavik/Intermediate - /End - Reykjavik
  Lat/Long Marsden Grid Navy Op Area
Beginning
63° N / 40° W map
221 map
AR11 map
Ending
68° N / 24° W map
219 map
NA01 map
  Show Degrees Minutes    
 
Op Area Description:
  Lat/Long Marsden Grid Navy Op Area
Beginning
63° N / 40° W map
220 map
NA04 map
Ending
68° N / 24° W map
219 map
NA01 map
  Show Degrees Minutes    
 
Op Area Description:
Coastal States Requiring Clearance: Denmark(T), Iceland(T)
Foreign Clearance Required: Yes
Denmark, Iceland
Foreign Clearance Comments:
Ancil Facilities:
Instrumentation Requested: Dynamic Positioning
PI-Provided Vans - briefly describe
Instrumentation Comments:
Ancil Facilities Requested:
Ancil Facility Comments:
External Cruise Webpage:
Cruise Notes: PI requests to start & end the cruise in Isafjordur Iceland. Nuuk to Isafjordur 1116nm, 4.3 days. Nuuk to Reykjavik 4.1 days. Isafjordur to WHOI 2399nm, 9.1 days, Reykjavik to WHOI 2341nm, 8.9 days.