Ship: |
Knorr |
Schedule Status: |
Final |
Schedule ID: |
10300 |
Schedule Year: |
2008 |
Schedule Name: |
Set 1 |
Notes: |
Changes: 10/27: End Pickart on 31 9/24: added a port day and shifted D'Hondt a day later 9/23: add a day for WHOI testing of equipment 9/15: stop in Sisimiut for replacement releases for Lee 4/28: Added 6 days to Bower transit to Nuuk for Straneo moorings in Hudson Strait. 4/16: Moved Bermuda port stop to arrive June 27 and depart 29th. 4/9: Added 2 days to Reykjavik port stop (April 24 to May 1) for repair of bow thruster. Lee/Perry and Cutter cruises shifted 2 days later. 3/5: Departure from Charleston/shipyard changed to March 11th arrive into WHOI March 14. Depart for Bates March 19. 1/14: Added Daly/Wakeham and D'Hondt cruises to the end of the year 1/9: Johns mooring recovery has been removed from the schedule. Knorr will transit directly to the shipyard in Charleston. |
|
Operator Cruise ID: |
|
Chief Scientist: |
Gregory A. Cutter, ODU_OEAS |
Activity Type: |
At Sea for Science |
Created By: |
Elizabeth Caporelli |
|
|
Dates To Be Determined
|
Load Non-charge Days: |
0 |
Load Charge Days: |
0 |
|
Load Date: |
6/29/2008 |
Activity Days: |
12 |
Adjustment Days |
Start Date: |
6/29/2008 |
Transit Days: |
2 |
0 |
End Date: |
7/12/2008 |
Unload Charge Days: |
2 |
|
Unload Date: |
7/14/2008 |
Unload Non-charge Days: |
0 |
|
Mob Days: |
0 |
|
Science Days: |
30 |
Optimum Start Date: |
5/1/2008 |
Transit Estimate: |
0 |
Earliest Start Date: |
5/1/2008 |
Demob Days: |
0 |
Latest Start Date: |
6/1/2008 |
Repeating Cruise: |
No |
Dates To Avoid: |
|
Number of Repeating Cruises: |
0 |
Repeating Interval: |
|
Repeating Cruise Comments: |
|
Justification/Comments: |
|
|
PI |
|
Project/Purpose |
|
Agency |
|
Funding Status |
|
Op Days |
Gregory A. Cutter, ODU_OEAS |
|
US GEOTRACES sam |
|
NSF/OCE/CO |
|
Funded |
|
16 |
Ken O. Buesseler, WHOI |
|
GEOTRACES- Intercali |
|
NSF/OCE/CO |
|
Funded |
|
0 |
|
|
Requested Start Port: |
Norfolk, VA, USA |
Intermediate Port(s): |
St. George's, Bermuda |
Requested End Port: |
None |
Port Comments: |
Requested Ports: Start - 2008, Norfolk; 2009, San Diego/Intermediate - 2008, St Georges, Bermuda/End - 2008, Norfolk; 2009, San Diego |
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
|
|
|
Ending
|
|
|
|
|
|
Op Area Description: |
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
|
|
|
Ending
|
|
|
|
|
|
Op Area Description: |
|
|
Coastal States Requiring Clearance:
|
|
|
Foreign Clearance Required: |
Yes |
Bermuda
|
Foreign Clearance Comments: |
|
|
|
Instrumentation Requested: |
PI-Provided Vans - briefly describe
|
Instrumentation Comments: |
|
Ancil Facilities Requested: |
|
Ancil Facility Comments: |
|
|
External Cruise Webpage: |
|
Cruise Notes: |
|
|