Ship: |
Atlantis |
Schedule Status: |
Final |
Schedule ID: |
10873 |
Schedule Year: |
2010 |
Schedule Name: |
Atlantis 2010 Schedule/Final Version |
Notes: |
*** PLEASE NOTE: The ports for the Gulf of Mexico cruises are subject to change.
Alvin Eng dives need to be scheduled 12/10: Nooner cruise will depart on 12/15 and arrive on 01/03, will use Alvin 01/21: Cut 4 days from Calnex/Bates cruise 01/02: Capone/Moffett departed one day late on 01/29 02/08: Removed 1 day for Eglinton from Toole cruise and added Alvin Eng dive day in SD 5/4: Arrival into San Diego changed from 4/25 to 4/24 6/1: Cowen will depart on 6/14 and use Jason 6/16: Cowen cruise departed on 6/15 7/16: Added Gulf Rapid Response Cruise for C. Fisher w/Alvin in Dec. 8/24: Changed departure from SD to 8/18 9/10: Arrival into WHOI changed to the 6th 9/10: additional dives added to the Joye and Fisher cruise 9/17: added Alvin Eng dive to Joye cruise in place of maint day. 11/9: added Sentry to Fisher/German cruise 11/24: added shipyard port Jacksonville, FL. 12/15: additional day / dive added onto Chuck Fisher cruise (12/14) / New ETA into Gulfport 12/15 // New Departure date from Gulfport 12/15 // NEW ETA Jacksonville Fl. 12/19. 12/28: Publish final version 2010 schedule |
|
Operator Cruise ID: |
|
Chief Scientist: |
John Sinton, UH_SOEST |
Activity Type: |
At Sea for Science |
Created By: |
Elizabeth Caporelli |
|
|
Dates To Be Determined
|
Load Non-charge Days: |
0 |
Load Charge Days: |
2 |
|
Load Date: |
3/13/2010 |
Activity Days: |
29 |
Adjustment Days |
Start Date: |
3/15/2010 |
Transit Days: |
2 |
0 |
End Date: |
4/14/2010 |
Unload Charge Days: |
1 |
|
Unload Date: |
4/15/2010 |
Unload Non-charge Days: |
0 |
|
Mob Days: |
0 |
|
Science Days: |
30 |
Optimum Start Date: |
9/1/2010 |
Transit Estimate: |
8 |
Earliest Start Date: |
9/1/2010 |
Demob Days: |
0 |
Latest Start Date: |
1/31/2011 |
Repeating Cruise: |
No |
Dates To Avoid: |
deferred to 2010 [jmp] |
Number of Repeating Cruises: |
0 |
Repeating Interval: |
|
Repeating Cruise Comments: |
|
Justification/Comments: |
|
|
PI |
|
Project/Purpose |
|
Agency |
|
Funding Status |
|
Op Days |
John Sinton, UH_SOEST |
|
Volcanic Eruptions o |
|
NSF/OCE/MGG |
|
Funded |
|
34 |
|
|
ALVIN SENTRY |
|
OTHER |
|
Pending |
|
0 |
|
|
Requested Start Port: |
Puntarenas, Costa Rica |
Intermediate Port(s): |
None |
Requested End Port: |
Puntarenas, Costa Rica |
Port Comments: |
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
|
|
|
Ending
|
|
|
|
|
Show Degrees Minutes |
|
|
|
|
Op Area Description: |
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
|
|
|
Ending
|
|
|
|
|
Show Degrees Minutes |
|
|
|
|
Op Area Description: |
|
|
Coastal States Requiring Clearance:
|
Ecuador(T)
|
|
Foreign Clearance Required: |
Yes |
Ecuador
|
Foreign Clearance Comments: |
|
|
Ancil Facilities: |
Sentry Alvin
|
|
Instrumentation Requested: |
Dynamic Positioning Multibeam Dredging/Coring/Large Dia. Trawl Wire
|
Instrumentation Comments: |
mother ship for Alvin submersible, multibeam, dredging, wax coring |
Ancil Facilities Requested: |
Sentry Alvin
|
Ancil Facility Comments: |
|
|
External Cruise Webpage: |
|
Cruise Notes: |
Galap to Balboa 833nm 3/4days 2 days transit to area 1 1 day deployment and surveying 13 days diving and surveying (transit to area 2 at night) 1 day deployment and surveying (no Alvin dives) 13 days diving and surveying (pick up transponders end of last dive) 1 day transit to Puerto Ayora |
|