| Ship: |
Knorr |
Schedule Status: |
Final |
Schedule ID: |
11215 |
| Schedule Year: |
2011 |
Schedule Name: |
Final 2011 |
| Notes: |
8/18: Changed arrival into Reykjavik Iceland to Aug 18 (from 8/19) // 3 Mob days for Pickart. No change in # of op days. 8/10: Removed 1 demob day Dec 12 from Jenkins cruise. Was counted twice. New Op day total 286. 7/20: 1 demob day from R. Curry for transit to WHOI. R.Curry cruise arrival date into Bermuda changed to June 12. S. Miller cruise arrival date into WHOI changed to June17. 6/1: B.Johns cruise Arrived P.Evglds May 3 (old date May 4). 5/10/11: Added one day onto PICKART. Shifted LEE, Transit, and Jenkins one day to the right. 4/1/11: Added Bermuda port call for Jenkins 3/30/11: NEW SCHEDULE /// Geotraces back to Knorr. No Jason ops for 2011. (301 to 287 op days) 2/28: Reduced # of op days to 301 from 304 (deleted charged port days for Schopfel for a total of 14) 2//5/11: Changed Schopfel cruise ports and dates (whoi to whoi) // new transit to Iceland. 1/31/11: added transit from Greece to Key West // Added Chris German cruise Key West to Key West. 1/11/11: Added Schopfel July - August dates // Added 3 days to Edgcomb cruise 1/4/11: Deleted Schopfel cruise. Added transit from WHOI to HLFX Feb 21. 11/12/10 - Hebert's ports changed to Halifax NS. PLEASE NOTE -Schopfel cruise may go in/out of Key West several times during the cruise. -Johns cruise will need to make Bahamas port stop for clearance check in |
|
| Operator Cruise ID: |
|
| Chief Scientist: |
Robert S. Pickart, WHOI |
| Activity Type: |
At Sea for Science |
| Created By: |
Eric Benway |
|
|
Dates To Be Determined
|
| Load Non-charge Days: |
0 |
| Load Charge Days: |
3 |
|
Load Date: |
8/19/2011 |
| Activity Days: |
31 |
Adjustment Days |
Start Date: |
8/22/2011 |
| Transit Days: |
1 |
0 |
End Date: |
9/22/2011 |
| Unload Charge Days: |
2 |
|
Unload Date: |
9/24/2011 |
| Unload Non-charge Days: |
0 |
|
| Mob Days: |
2 |
|
| Science Days: |
30 |
Optimum Start Date: |
8/1/2011 |
| Transit Estimate: |
1 |
Earliest Start Date: |
7/1/2011 |
| Demob Days: |
1 |
Latest Start Date: |
10/1/2011 |
| Repeating Cruise: |
No |
Dates To Avoid: |
We shouldn't go earlier than July because of the pack-ice, or later than October because of the storm season. |
| Number of Repeating Cruises: |
0 |
Repeating Interval: |
|
| Repeating Cruise Comments: |
|
| Justification/Comments: |
|
|
| PI |
|
Project/Purpose |
|
Agency |
|
Funding Status |
|
Op Days |
| Robert S. Pickart, WHOI |
|
DSOW |
|
NSF/OCE/PO |
|
Funded |
|
37 |
|
|
|
| Requested Start Port: |
Reykjavik, Iceland |
| Intermediate Port(s): |
None |
| Requested End Port: |
Reykjavik, Iceland |
| Port Comments: |
|
|
| |
Lat/Long |
Marsden Grid |
Navy Op Area |
|
Beginning
|
|
|
|
|
Ending
|
|
|
|
| |
Show Degrees Minutes |
|
|
|
| |
| Op Area Description: |
Iceland |
|
| |
Lat/Long |
Marsden Grid |
Navy Op Area |
|
Beginning
|
|
|
|
|
Ending
|
|
|
|
| |
Show Degrees Minutes |
|
|
|
| |
| Op Area Description: |
Iceland |
|
|
Coastal States Requiring Clearance:
|
|
|
| Foreign Clearance Required: |
Yes |
|
|
| Foreign Clearance Comments: |
|
|
|
|
| Instrumentation Requested: |
Dynamic Positioning Multibeam
|
| Instrumentation Comments: |
A hull-mounted ADCP is required. |
| Ancil Facilities Requested: |
|
| Ancil Facility Comments: |
|
|
| External Cruise Webpage: |
|
| Cruise Notes: |
Bob P. on the Healy schedule NASA cruise which is scheduled, right now, for July 9 to Aug 12 and for Oct 7- Oct 20 END PORT ISAFJOROUR Added one day mob and shifted schedule one day to right. |
|