Ship: Knorr Schedule Status: Final Schedule ID: 11215
Schedule Year: 2011 Schedule Name: Final 2011
Notes: 8/18: Changed arrival into Reykjavik Iceland to Aug 18 (from 8/19) // 3 Mob days for Pickart. No change in # of op days.
8/10: Removed 1 demob day Dec 12 from Jenkins cruise. Was counted twice. New Op day total 286.
7/20: 1 demob day from R. Curry for transit to WHOI.
R.Curry cruise arrival date into Bermuda changed to June 12.
S. Miller cruise arrival date into WHOI changed to June17.
6/1: B.Johns cruise Arrived P.Evglds May 3 (old date May 4).
5/10/11: Added one day onto PICKART. Shifted LEE, Transit, and Jenkins one day to the right.
4/1/11: Added Bermuda port call for Jenkins
3/30/11: NEW SCHEDULE /// Geotraces back to Knorr.
No Jason ops for 2011. (301 to 287 op days)
2/28: Reduced # of op days to 301 from 304 (deleted charged port days for Schopfel for a total of 14)
2//5/11: Changed Schopfel cruise ports and dates (whoi to whoi) // new transit to Iceland.
1/31/11: added transit from Greece to Key West // Added Chris German cruise Key West to Key West.
1/11/11: Added Schopfel July - August dates // Added 3 days to Edgcomb cruise
1/4/11: Deleted Schopfel cruise. Added transit from WHOI to HLFX Feb 21.
11/12/10 - Hebert's ports changed to Halifax NS.
PLEASE NOTE
-Schopfel cruise may go in/out of Key West several times during the cruise.
-Johns cruise will need to make Bahamas port stop for clearance check in
  Cruise Information  
Ship Request Information
Operator Cruise ID:
Chief Scientist: None
Activity Type: At Sea for Science
Created By: Eric Benway
Compare Request:
Project Short Title: GEOTRACES Mngmnt
Requested Year: 2010
Requested Ship: Knorr  
Request Type: Primary  
Created By: William J. Jenkins  
Load Non-charge Days: 0
Load Charge Days: 4   Load Date: 11/2/2011
Activity Days: 13 Adjustment Days Start Date: 11/6/2011
Transit Days: 0 0 End Date: 11/18/2011
Unload Charge Days: 0   Unload Date: 11/18/2011
Unload Non-charge Days: 0
Mob Days: 3  
Science Days: 52 Optimum Start Date: 9/15/2010
Transit Estimate: 0 Earliest Start Date: 9/6/2010
Demob Days: 2 Latest Start Date: 10/15/2010
Repeating Cruise: No Dates To Avoid:
Number of Repeating Cruises: 0 Repeating Interval:
Repeating Cruise Comments:
Justification/Comments:
PI   Project/Purpose   Agency   Funding Status   Op Days
William J. Jenkins, WHOI   GEOTRACES Mngmnt   NSF/OCE/CO   Funded   13
  Start Port: Woods Hole, MA, USA
  End Port: St. George's, Bermuda
Requested Start Port: Woods Hole, MA, USA
Intermediate Port(s): None
Requested End Port: Lisboa, Portugal
Port Comments:
  Lat/Long Marsden Grid Navy Op Area
Beginning
Ending
 
Op Area Description:
  Lat/Long Marsden Grid Navy Op Area
Beginning
41.52° N / 70.67° W map
152 map
NA06 map
Ending
38.71° N / 9.14° W map
109 map
NA07 map
  Show Degrees Minutes    
 
Op Area Description: Subtrop N.Atl
Coastal States Requiring Clearance:
Foreign Clearance Required: Yes
Foreign Clearance Comments:
Ancil Facilities:
Instrumentation Requested: PI-Provided Vans - briefly describe
Instrumentation Comments:
Ancil Facilities Requested: Other Facility
Other Towed Underwater Vehicle
Ancil Facility Comments: Hydrography, CTD and nutrient measurements will be supported by the Ocean Data Facility (J. Swift) at Scripps Institution of Oceanography and funded through NSF Facilities. They will be providing an additional CTD rosette system along with nephelometer and LADCP. A trace metal clean Go-Flo Rosette and winch will be provided by the group at Old Dominion University (G. Cutter) along with a towed underway pumping system.
External Cruise Webpage:
Cruise Notes: Rescheduled from Atlantis - make up from 2010.
Will need port stop (1 night) in Bermuda.