  Schedule Information  
Ship: Knorr Schedule Status: Final Schedule ID: 11215
Schedule Year: 2011 Schedule Name: Final 2011
Notes: 8/18: Changed arrival into Reykjavik Iceland to Aug 18 (from 8/19) // 3 Mob days for Pickart. No change in # of op days.
8/10: Removed 1 demob day Dec 12 from Jenkins cruise. Was counted twice. New Op day total 286.
7/20: 1 demob day from R. Curry for transit to WHOI.
R.Curry cruise arrival date into Bermuda changed to June 12.
S. Miller cruise arrival date into WHOI changed to June17.
6/1: B.Johns cruise Arrived P.Evglds May 3 (old date May 4).
5/10/11: Added one day onto PICKART. Shifted LEE, Transit, and Jenkins one day to the right.
4/1/11: Added Bermuda port call for Jenkins
3/30/11: NEW SCHEDULE /// Geotraces back to Knorr.
No Jason ops for 2011. (301 to 287 op days)
2/28: Reduced # of op days to 301 from 304 (deleted charged port days for Schopfel for a total of 14)
2//5/11: Changed Schopfel cruise ports and dates (whoi to whoi) // new transit to Iceland.
1/31/11: added transit from Greece to Key West // Added Chris German cruise Key West to Key West.
1/11/11: Added Schopfel July - August dates // Added 3 days to Edgcomb cruise
1/4/11: Deleted Schopfel cruise. Added transit from WHOI to HLFX Feb 21.
11/12/10 - Hebert's ports changed to Halifax NS.
PLEASE NOTE
-Schopfel cruise may go in/out of Key West several times during the cruise.
-Johns cruise will need to make Bahamas port stop for clearance check in
  Cruise Information  
Ship Request Information
Operator Cruise ID:
Chief Scientist: None
Activity Type: Transit Cruise
Created By: Eric Benway
Compare Request:
Project Short Title:
Requested Year:
Requested Ship:  
Request Type:  
Created By:  
Load Non-charge Days: 0
Load Charge Days: 0   Load Date: 12/12/2011
Activity Days: 0 Adjustment Days Start Date: 12/12/2011
Transit Days: 12 0 End Date: 12/23/2011
Unload Charge Days: 2   Unload Date: 12/25/2011
Unload Non-charge Days: 0
Mob Days:  
Science Days: Optimum Start Date:
Transit Estimate: Earliest Start Date:
Demob Days: Latest Start Date:
Repeating Cruise: Dates To Avoid:
Number of Repeating Cruises: Repeating Interval:
Repeating Cruise Comments:
Justification/Comments:
PI   Project/Purpose   Agency   Funding Status   Op Days
  Transit   NSF/OCE/EDU   Funded   12
  Start Port: Praia, Sao Tiago, Cape Verde Islands
  End Port: Woods Hole, MA, USA
Requested Start Port:
Intermediate Port(s):
Requested End Port:
Port Comments:
  Lat/Long Marsden Grid Navy Op Area
Beginning
Ending
 
Op Area Description:
  Lat/Long Marsden Grid Navy Op Area
Beginning
Ending
 
Op Area Description:
Coastal States Requiring Clearance:
Foreign Clearance Required:
Foreign Clearance Comments:
Ancil Facilities:
Instrumentation Requested:
Instrumentation Comments:
Ancil Facilities Requested:
Ancil Facility Comments:
External Cruise Webpage:
Cruise Notes: Deadhead transit = 2958=11day + 1 = 12 day transit.