Ship: |
Knorr |
Schedule Status: |
Final |
Schedule ID: |
11215 |
Schedule Year: |
2011 |
Schedule Name: |
Final 2011 |
Notes: |
8/18: Changed arrival into Reykjavik Iceland to Aug 18 (from 8/19) // 3 Mob days for Pickart. No change in # of op days. 8/10: Removed 1 demob day Dec 12 from Jenkins cruise. Was counted twice. New Op day total 286. 7/20: 1 demob day from R. Curry for transit to WHOI. R.Curry cruise arrival date into Bermuda changed to June 12. S. Miller cruise arrival date into WHOI changed to June17. 6/1: B.Johns cruise Arrived P.Evglds May 3 (old date May 4). 5/10/11: Added one day onto PICKART. Shifted LEE, Transit, and Jenkins one day to the right. 4/1/11: Added Bermuda port call for Jenkins 3/30/11: NEW SCHEDULE /// Geotraces back to Knorr. No Jason ops for 2011. (301 to 287 op days) 2/28: Reduced # of op days to 301 from 304 (deleted charged port days for Schopfel for a total of 14) 2//5/11: Changed Schopfel cruise ports and dates (whoi to whoi) // new transit to Iceland. 1/31/11: added transit from Greece to Key West // Added Chris German cruise Key West to Key West. 1/11/11: Added Schopfel July - August dates // Added 3 days to Edgcomb cruise 1/4/11: Deleted Schopfel cruise. Added transit from WHOI to HLFX Feb 21. 11/12/10 - Hebert's ports changed to Halifax NS. PLEASE NOTE -Schopfel cruise may go in/out of Key West several times during the cruise. -Johns cruise will need to make Bahamas port stop for clearance check in |
|
Operator Cruise ID: |
|
Chief Scientist: |
None |
Activity Type: |
At Sea for Science |
Created By: |
Eric Benway |
|
|
Dates To Be Determined
|
Load Non-charge Days: |
0 |
Load Charge Days: |
0 |
|
Load Date: |
11/19/2011 |
Activity Days: |
23 |
Adjustment Days |
Start Date: |
11/19/2011 |
Transit Days: |
0 |
0 |
End Date: |
12/11/2011 |
Unload Charge Days: |
0 |
|
Unload Date: |
12/11/2011 |
Unload Non-charge Days: |
0 |
|
Mob Days: |
3 |
|
Science Days: |
52 |
Optimum Start Date: |
9/15/2010 |
Transit Estimate: |
0 |
Earliest Start Date: |
9/6/2010 |
Demob Days: |
2 |
Latest Start Date: |
10/15/2010 |
Repeating Cruise: |
No |
Dates To Avoid: |
|
Number of Repeating Cruises: |
0 |
Repeating Interval: |
|
Repeating Cruise Comments: |
|
Justification/Comments: |
|
|
PI |
|
Project/Purpose |
|
Agency |
|
Funding Status |
|
Op Days |
William J. Jenkins, WHOI |
|
GEOTRACES Atlantic |
|
NSF/OCE/CO |
|
Funded |
|
23 |
|
|
Requested Start Port: |
Woods Hole, MA, USA |
Intermediate Port(s): |
Lisboa, Portugal |
Requested End Port: |
None |
Port Comments: |
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
|
|
|
Ending
|
|
|
|
|
|
Op Area Description: |
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
41° 31.2' N
/
70° 40.2' W
map
|
|
|
Ending
|
38° 42.6' N
/
9° 8.4' W
map
|
|
|
|
Show Degrees Minutes |
|
|
|
|
Op Area Description: |
Subtrop N.Atl |
|
Coastal States Requiring Clearance:
|
|
|
Foreign Clearance Required: |
Yes |
|
Foreign Clearance Comments: |
|
|
|
Instrumentation Requested: |
PI-Provided Vans - briefly describe
|
Instrumentation Comments: |
|
Ancil Facilities Requested: |
|
Ancil Facility Comments: |
|
|
External Cruise Webpage: |
|
Cruise Notes: |
|
|