Notes: |
1/6/14: Final Sch. 10/10: Reduced WELLER / OOI November cruise 3 days. New dates Nov 20 - 26. 7/11: (1) Shifted Transit to Nuuk + Lee + Huebert cruises 1 day earlier. (2) OOI cruise reduced to 10 sea days and changed departure date to Nov 20. New op days 256. 6/21: Reduced Lee mobilization in Nuuk to 2 days. Moved departure day from WHOI to Sept 5 for the adjustment. 4/23: Added 3 days for the new Jason / Media winch test. WHOI to WHOI July 26 - 28. 3/6: Defined Maintenance periods while in port WHOI. 6/22 - 7/7 & 7/23 - 9/3. Still available for service. 2/26: Added 2 days transit onto Eleuterio, one on each leg. Cruise dates stay the same. Total op days to 258. 1/3/13: Transit from Norfolk VA to WHOI changed to July 20 - 21. Operating days stay the same. 12/11/12: Removed R. Hey cruise. New transit Sept 4 - 11 to Nuuk. New C. Lee dates Sept 15 - Oct 4 and B Huebert dates Oct 10 - Nov 15. New op day total 256 11/9/12: Shifted Trident Warrior cruise to the right, July 13- 18. fixed end port for Kujawinski = Barbados. 11/8/12: Published Knorr 2013 schedule Version 1 |
|
Operator Cruise ID: |
|
Chief Scientist: |
Al Plueddemann, WHOI |
Activity Type: |
At Sea for Science |
Created By: |
Eric Benway |
|
|
Dates To Be Determined
|
Load Non-charge Days: |
0 |
Load Charge Days: |
2 |
|
Load Date: |
11/18/2013 |
Activity Days: |
5 |
Adjustment Days |
Start Date: |
11/20/2013 |
Transit Days: |
2 |
0 |
End Date: |
11/26/2013 |
Unload Charge Days: |
1 |
|
Unload Date: |
11/27/2013 |
Unload Non-charge Days: |
0 |
|
Mob Days: |
2 |
|
Science Days: |
12 |
Optimum Start Date: |
10/15/2013 |
Transit Estimate: |
2 |
Earliest Start Date: |
10/1/2013 |
Demob Days: |
1 |
Latest Start Date: |
11/1/2013 |
Repeating Cruise: |
Yes |
Dates To Avoid: |
Mooring servicing in spring and fall, timed for weather and biofouling cycle |
Number of Repeating Cruises: |
16 |
Repeating Interval: |
every 6 months |
Repeating Cruise Comments: |
Recover, redeploy, refresh power systems and sensors every 6 months. |
Justification/Comments: |
Spring and fall cruises to meet requirement to refresh power and sensors every 6 months, deal with biofouling. Deck payload when deploying and servicing moorings requires Global UNOLS vessel, such as Knorr. |
|
PI |
|
Project/Purpose |
|
Agency |
|
Funding Status |
|
Op Days |
Al Plueddemann, WHOI |
|
OOI Pioneer |
|
NSF-OOI/OOI |
|
Funded |
|
7 |
|
|
Requested Start Port: |
Woods Hole, MA, USA |
Intermediate Port(s): |
None |
Requested End Port: |
Woods Hole, MA, USA |
Port Comments: |
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
|
|
|
Ending
|
|
|
|
|
|
Op Area Description: |
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
|
|
|
Ending
|
|
|
|
|
Show Degrees Minutes |
|
|
|
|
Op Area Description: |
NE shelf |
|
Coastal States Requiring Clearance:
|
|
|
Foreign Clearance Required: |
No |
|
Foreign Clearance Comments: |
|
|
|
Instrumentation Requested: |
Dynamic Positioning Multibeam Dredging/Coring/Large Dia. Trawl Wire
|
Instrumentation Comments: |
Trawl in case of ned to drag for moorings. |
Ancil Facilities Requested: |
|
Ancil Facility Comments: |
Global vessel with dynamic positioning, crane rated to 7000 lbs, A-frame to 10 tons. 1200 sq ft working deck area; 60,000 lb ship deck load; 9,000 m 9/16 th trawl wire, 12 days endurance, experience with mooring operations. |
|
External Cruise Webpage: |
|
Cruise Notes: |
Reduced op days to 7 total Oct 10, 2013. Al Plueddemann assigned CH Sci Mar 1 2013. |
|