View Cruise

  Schedule Information  
Ship: Knorr Schedule Status: Final Schedule ID: 12058
Schedule Year: 2013 Schedule Name: Verstion 8 _ Oct 10, 2013
Notes: 1/6/14: Final Sch.
10/10: Reduced WELLER / OOI November cruise 3 days. New dates Nov 20 - 26.
7/11: (1) Shifted Transit to Nuuk + Lee + Huebert cruises 1 day earlier. (2) OOI cruise reduced to 10 sea days and changed departure date to Nov 20. New op days 256.
6/21: Reduced Lee mobilization in Nuuk to 2 days. Moved departure day from WHOI to Sept 5 for the adjustment.
4/23: Added 3 days for the new Jason / Media winch test. WHOI to WHOI July 26 - 28.
3/6: Defined Maintenance periods while in port WHOI. 6/22 - 7/7 & 7/23 - 9/3. Still available for service.
2/26: Added 2 days transit onto Eleuterio, one on each leg. Cruise dates stay the same. Total op days to 258.
1/3/13: Transit from Norfolk VA to WHOI changed to July 20 - 21. Operating days stay the same.
12/11/12: Removed R. Hey cruise. New transit Sept 4 - 11 to Nuuk. New C. Lee dates Sept 15 - Oct 4 and B Huebert dates Oct 10 - Nov 15. New op day total 256
11/9/12: Shifted Trident Warrior cruise to the right, July 13- 18. fixed end port for Kujawinski = Barbados.
11/8/12: Published Knorr 2013 schedule Version 1
  Cruise Information  
Ship Request Information
Operator Cruise ID:
Chief Scientist: Luc Lenain, SIO
Activity Type: At Sea for Science
Created By: Eric Benway
Compare Request:
Project Short Title:
Requested Year:
Requested Ship:  
Request Type:  
Created By:  
Load Non-charge Days: 0
Load Charge Days: 2   Load Date: 7/11/2013
Activity Days: 4 Adjustment Days Start Date: 7/13/2013
Transit Days: 2 0 End Date: 7/18/2013
Unload Charge Days: 1   Unload Date: 7/19/2013
Unload Non-charge Days: 0
Mob Days:  
Science Days: Optimum Start Date:
Transit Estimate: Earliest Start Date:
Demob Days: Latest Start Date:
Repeating Cruise: Dates To Avoid:
Number of Repeating Cruises: Repeating Interval:
Repeating Cruise Comments:
Justification/Comments:
PI   Project/Purpose   Agency   Funding Status   Op Days
Daniel Eleuterio, ONR   Trident Warrior   NAVY/ONR   Funded   9
  Start Port: Norfolk, VA, USA
  End Port: Norfolk, VA, USA
Requested Start Port:
Intermediate Port(s):
Requested End Port:
Port Comments:
  Lat/Long Marsden Grid Navy Op Area
Beginning
Ending
 
Op Area Description:
  Lat/Long Marsden Grid Navy Op Area
Beginning
Ending
 
Op Area Description:
Coastal States Requiring Clearance:
Foreign Clearance Required:
Foreign Clearance Comments:
Ancil Facilities:
Instrumentation Requested:
Instrumentation Comments:
Ancil Facilities Requested:
Ancil Facility Comments:
External Cruise Webpage:
Cruise Notes: this is a 4 day U.S. Navy unmanned surface vessel operation.
Estimate 1 day transit out to op area and 1 day back in.

PI / Ch Sci to be named.