Ship: Neil Armstrong Schedule Status: Final Schedule ID: 12670
Schedule Year: 2015 Schedule Name: Final 2015 Schedule (ver 2)
Notes: 1/14/16: Published final 2015 schedule.
10/6: Changed departure date San Francisco one day earlier to Nov 10. Schedule shifts one day to the left.
- Charleston SC used as a placeholder only. Location for Phase III yard TBD.
- USCG underway day ~9/15.
- Delivery Scheduled for Sept 23, 2015.
  Cruise Information  
Ship Request Information
Operator Cruise ID:
Chief Scientist: Amy Simoneau, WHOI
Activity Type: Transit Cruise
Created By: Eric Benway
Compare Request:
Project Short Title:
Requested Year:
Requested Ship:  
Request Type:  
Created By:  
Load Non-charge Days: 0
Load Charge Days: 0   Load Date: 10/31/2015
Activity Days: 4 Adjustment Days Start Date: 10/31/2015
Transit Days: 4 0 End Date: 11/7/2015
Unload Charge Days: 1   Unload Date: 11/8/2015
Unload Non-charge Days: 0
Mob Days:  
Science Days: Optimum Start Date:
Transit Estimate: Earliest Start Date:
Demob Days: Latest Start Date:
Repeating Cruise: Dates To Avoid:
Number of Repeating Cruises: Repeating Interval:
Repeating Cruise Comments:
Justification/Comments:
PI   Project/Purpose   Agency   Funding Status   Op Days
  Shakedown Leg 1   NAVY   Funded   9
  Markey/Allied tests   OTHER   Funded   0
  Start Port: Anacortes, WA, USA
  End Port: San Francisco, CA, USA
Requested Start Port:
Intermediate Port(s):
Requested End Port:
Port Comments:
  Lat/Long Marsden Grid Navy Op Area
Beginning
48.5° N / 122.5° W map
157 map
NP09 map
Ending
37.8° N / 122.4° W map
121 map
NP09 map
  Show Degrees Minutes    
 
Op Area Description: East Pacific
  Lat/Long Marsden Grid Navy Op Area
Beginning
Ending
 
Op Area Description:
Coastal States Requiring Clearance: NONE(T)
Foreign Clearance Required:
Foreign Clearance Comments:
Ancil Facilities:
Instrumentation Requested:
Instrumentation Comments:
Ancil Facilities Requested:
Ancil Facility Comments:
External Cruise Webpage:
Cruise Notes: Anacortes to San Fran = 814nm = 4 days + Winch testing 4 days = 8 days
WHOI has a development event in San Fran Nov 8, 19 & 10.