View Cruise

  Schedule Information  
Ship: Neil Armstrong Schedule Status: Final Schedule ID: 13054
Schedule Year: 2016 Schedule Name: Version 14
Notes: 11/4: Charleston nominated for drydock. Amended transit time.
10/20: 9 Oct was a charged weather day and 17 Oct a special charged demobe day due to extended gap between legs 1 & 2 per agreement with OOI 18 Oct 2016.
10/3: SVC VII Cancelled
8/16: Shifted OOI Pioneer 4 days earlier to start 9/27.
8/3/16: G. Tupper OOI Irminger early arrival Reykjavik July 26.
6/1: OOI Pioneer arrival one day early. No change in charge days.
5/31: Added 1 SVC days for SVC VI - Lawson and 2 SVC days for SVC VIII (tbd).
4/13: Updated departure for SVC III to April 2 - April 6. and changed Ch Sci to Y.T. Lin
3/2/16: 1) Reconfigured OOI Pioneer spring cruise legs. (2) Swapped number of sea days for SVC V and SVC VI. (3) SVC VII Nov 4 - Nov 14. Added Ch Scientists to SVC V & VI.
2/12/16: 1) Changed SVC V to June 10 - 16. (2) Changed SVC VI to June 20 - 24. (3) Shifted OOI Irminger back to June 30 - July 28. (4) Shifted Pickart / OSNAP back to Aug 3 to Sept 8.
2/9/16: Moved DC port call to November. Added Norfolk Va port call ending SVC II. SVC IV moved after UNOLS inspection. Added 1 sci day to SVC IV.
Added non op transit to warranty shipyard / period into 2017. We have 12 shakedown days not used or rescheduled yet 2/9/16).
1/27: 1) Feb 9 - 17 is now NAVY/WHOI acceptance trials - Non Op.
2)Removed "Shakedown 3". Shakedown 2 is now for AUTEC.
3) Added Washingont D.C. (Alexandria VA) port call March 29 - 31
4) Shifted SVC III to April 4/2 - 4/7.
5) SVC IV moved after UNOLS inspection w/ ROV component testing
6) OOI "Pioneer 6" moved to May 13 - June 7 (3 legs).
7) OOI Irminger Sea moved to July 8 - Aug 5
8) ONSAP/Pickart moved to Aug 11 -Sept 16.
9) OOI "Pioneer 7" moved earlier to Oct 10 - Oct 23 (3 legs).
10) Added SVC VIII from old shakedown 2 that was taken up by acceptance trials.
1/5/16:
1) Added AUTEC range into Shakedown 2
2) Scheduled March 27-31 Washington DC port call.
3) Swapped Maintenance period ahead of NSF/NAVSEA/UNOLS inspection
4) SVC IV after inspection w/ ROV test prior to funded OOI cruise
12/22: Corrected SVC III to 10 charge days (not 9). Corrected OOI May 7 - 16 charge days to 10 (not 8).
12/9/15: Removed 2015 portion.
10/8: San Fransisco departure moved ahead 1 day to Nov 10, 2015. 2016 Operating days 204.
9/23/15: Published schedule
- Charleston SC used as a placeholder only. Location for Phase III yard TBD.
  Cruise Information  
Ship Request Information
Operator Cruise ID:
Chief Scientist: None /transit, NoneTBD
Activity Type: At Sea for Science
Created By: Kerry Strom
Compare Request:
Project Short Title:
Requested Year:
Requested Ship:  
Request Type:  
Created By:  
Load Non-charge Days: 0
Load Charge Days: 5   Load Date: 2/19/2016
Activity Days: 2 Adjustment Days Start Date: 2/24/2016
Transit Days: 5 0 End Date: 3/1/2016
Unload Charge Days: 1   Unload Date: 3/2/2016
Unload Non-charge Days: 0
Mob Days:  
Science Days: Optimum Start Date:
Transit Estimate: Earliest Start Date:
Demob Days: Latest Start Date:
Repeating Cruise: Dates To Avoid:
Number of Repeating Cruises: Repeating Interval:
Repeating Cruise Comments:
Justification/Comments:
PI   Project/Purpose   Agency   Funding Status   Op Days
  Shakedown 2   NAVY/ONR   Funded   13
  AUTEC RANGE   OTHER   Pending   0
  Start Port: Charleston, SC, USA
  End Port: Charleston, SC, USA
Requested Start Port:
Intermediate Port(s):
Requested End Port:
Port Comments:
  Lat/Long Marsden Grid Navy Op Area
Beginning
32° N / 77° W map
116 map
NA06 map
Ending
32° N / 77° W map
116 map
NA06 map
  Show Degrees Minutes    
 
Op Area Description: Bahamas
  Lat/Long Marsden Grid Navy Op Area
Beginning
Ending
 
Op Area Description:
Coastal States Requiring Clearance: NONE(A)
Foreign Clearance Required:
Foreign Clearance Comments:
Ancil Facilities:
Instrumentation Requested:
Instrumentation Comments:
Ancil Facilities Requested:
Ancil Facility Comments:
External Cruise Webpage:
Cruise Notes: 2/2/16: Navy scheduled Feb 27 for Armstrong.

This would be a sonar acoustic test. 2 days on site.
490nm Char to Autec range = 3 days transit (6 RT) + 2 sci = 8 days at sea

During transits the following may be tested and checked, but not limited to:
Multibeam
ADCP
Lab van and Rad van set up.
Lab set ups and flow through systems
Computer systems