View Cruise

  Schedule Information  
Ship: Atlantis Schedule Status: Final Schedule ID: 13491
Schedule Year: 2017 Schedule Name: FOY
Notes: 1/4: Split the transit from Barbados to Argentina btw ONR, OOI & IPS (10,10 & 9).
12/30: Atlantis departs 12/30 (2 days ahead of schedule)
12/17: Atlantis arrives Mar del Plata on 17th, not 18th (Added 1 more day in port).
12/14: Additional delay w/ Sub Search
11/30: Koppers deferred OOI AB back on after CURV ops
9/18: UNOLS Upgrade Adjustments
7/7: OOI AB looses 3 funded days
6/29: Arrives WHOI 1 day earlier (298 funded days to 297)
4/18: Arrive 1 day ahead of schedule in Manzanillo/ Luther (was the 19th)
3/22: Shift 1 day to the right starting w/ Wheat...Revelle added 1 Jason day to Nooner
3/11: McGuire back 1 day early & depart for Alvin test dive 1 day early (was the 9th & 12th)
1/27: Split transit funding btw NSF & NASA
1/11: Arrived Easter Island 1 day early (Jan 10th). Departing as scheduled the 15th.
9/21: 1 day added for Sentry test dive
9/8: Port office needs 1 day in Manzanillo Dec 31st 2016 for ABS/ USCG
8/29: Remove Bermuda dead-head transit and do Wheat from WHOI instead (Customs problems as per UNOLS meeting & better timing for Jason shipping)
8/23: Re scheduled the Alvin test dive (5 days total)
6/29 Al Suchy: USCG and ABS Special Survey has to be done in the early 2017 .
6/23 email from Jon: Johns "MOCHA" will go on Endeavor.
***Switch McGuire & Cheadle to Arica d/t swell in Iquiqe & previous damage to vessel, lines and Jason Equipment.
***Deb Smith can go in March- Changed from Galapagos d/t vessel inspections in Equador ($$$ & Time)
-Susan Lang Jason is in direct conflict with Deb Kelly OOI on Thompson
INSURV REQUIRED by end of OCTOBER 2017:
3 Alvin Audits:
January...May...September
Alvin NAVSEA & Internal Audits, 5 days each, M-F
NAVSEA inspection, 5 days, M-F
TWO, 5 day audits for Alvin
*Alvin & NAVSEA audits added at WHOI
  Cruise Information  
Ship Request Information
Operator Cruise ID:
Chief Scientist: Peter Lemmond, WHOI
Activity Type: At Sea for Science
Created By: Kerry Strom
Compare Request:
Project Short Title:
Requested Year:
Requested Ship:  
Request Type:  
Created By:  
Load Non-charge Days: 0
Load Charge Days: 0   Load Date: 12/21/2017
Activity Days: 4 Adjustment Days Start Date: 12/21/2017
Transit Days: 4 0 End Date: 12/28/2017
Unload Charge Days: 1   Unload Date: 12/29/2017
Unload Non-charge Days: 0
Mob Days:  
Science Days: Optimum Start Date:
Transit Estimate: Earliest Start Date:
Demob Days: Latest Start Date:
Repeating Cruise: Dates To Avoid:
Number of Repeating Cruises: Repeating Interval:
Repeating Cruise Comments:
Justification/Comments:
PI   Project/Purpose   Agency   Funding Status   Op Days
  CURV OPS   NAVY/ONR   Funded   9
  Start Port: Mar Del Plata, Argentina
  End Port: Comodoro Rivadavia, Argentina
Requested Start Port:
Intermediate Port(s):
Requested End Port:
Port Comments:
  Lat/Long Marsden Grid Navy Op Area
Beginning
0° N / 0° E map
335 map
SA02 map
Ending
0° N / 0° E map
335 map
SA02 map
  Show Degrees Minutes    
 
Op Area Description: CURV OPS
  Lat/Long Marsden Grid Navy Op Area
Beginning
Ending
 
Op Area Description:
Coastal States Requiring Clearance: NONE(T)
Foreign Clearance Required:
Foreign Clearance Comments:
Ancil Facilities:
Instrumentation Requested:
Instrumentation Comments:
Ancil Facilities Requested:
Ancil Facility Comments:
External Cruise Webpage:
Cruise Notes: Vessel was able to demobe in 1 day instead of 3 as planned.
Effort being made to get USCG inspection before OOI departure.