View Cruise

  Schedule Information  
Ship: Neil Armstrong Schedule Status: Final Schedule ID: 13492
Schedule Year: 2017 Schedule Name: FOY
Notes: 12/14: Arrived one day earlier d/t WX. ONR funds the lost day so day count stays the same.
11/17: Miksis-Olds cruise will depart 1 day later d/t wx, ONR kindly funding the lost day.
11/2: OOI Pioneer (Fall) Leg A, arrived a day early d/t wx, & departed a day early (Same day count)
10/3: Captain updates WHOI arrival to Oct 12th for Behn transit
9/28: Keigwin arriving a day early
9/25: Reduce the last cruise of the year, ADEON by 2 days as per the PI.
9/18: Corrected drydock departure from Feb 16th to 15th (was double billed [47-46 days])
9/18: Also corrected Keigwin arrival departure dates as UNOLS will not accept the 2nd of Oct to be an arrival & departure day.
8/24: 6 day earlier arrival d/t good wx & operations. OOI will pay for 3 of the 6 lost days. 1 crew member/ medical evacuation.
7/25: Shift WHOI days 1 day to left
7/1: Added 1 funded day to Geyer as per email 6/28.
5/23: Add 3/25 as an operational day.
5/22: Keigwin will arrive/ depart on the same day. Transit will be 10 funded days.
5/19: 1 day added to Azores transit for magnatometer tow work.
5/17: Extra port day in 3rd leg of OOI, ONR "In Port Days" for NYC Event.
4/24: Added 3 legs to Fall OOI Pioneer, Corrected Keigwin's days from 25 to 22.
4/21: Added 2 WHOI Inst. Days before Keigwin & removed 1 day in Azores
4/5: Added 4 mobe days to Keigwin and 1 demobe in Azores for replenishment.
...Put WHOI Inst. Days to "Non-Op"
...Vessel arrived 1730/4 d/t wx, keeping operational days the same to maintain annual funded day count in schedule.
4/3: Corrected March 3 (wx day) to count, so departed 3/2 to get proper 9 days.
3/22: Depart 1 day earlier for NYC PR (5/23)
3/22: Demobe only 1 day so Geyer can depart earlier (6/23)
3/20: Becker unplanned returned to WHOI to pick up winch (3/16-17)-added a voyage/ port call (no Voyage number).
3/3: Becker departure was delayed 1 day d/t wx
2/17: Departed ship yard 2 days later than planned (was 2/15)
2/7: 2nd leg of Becker changed from March 16th to the 17th.
2/2: Split out OOI legs as per email 2/2
1/27: Added a 4th leg to Becker
1/23: OOI Pioneer (Fall) keep Oct.22-Nov.11.
1/23: Add Newport, RI pitstop to Becker (3/16)
1/18: Remove SVC coring from Keigwin until further notice.
1/9: Geyer asks to deduct 1 science day d/t vessel traffic holiday weekend. Left 4th of July open at WHOI.
1/5: Agreed to shorten the PR event by 2 days
11/7: SVC7 for coring will be done at the front of the Keigwin voyage.
11/3: Savidge and Geyer need to go back to original schedule due to personnel/ vsl traffic respectively.
10/25: PR Event after Becker, VanMooy & Savidge...
10/24: Coring arm install, SVC, WHOI Days, PR
9/01: SVC7 2016 pushed into 2017 (Coring), maybe during WHOI institutional days in Block Isl. Sound w/ Donnelly & Kegwin...TBD
8/30: Savidge transit removed
2017 schedule adjusted for 10 knots as per Port Ops.
Becker is a 3 ship operation. Armstrong + Endeavor + Sharp. March 31st was the agreed start date in March 2016 scheduling meeting.

Adjusted Navy dates 6/23 (Jon's email 6/23)

7/25: A. Bower & Saito deleted d/t denied funding
  Cruise Information  
Ship Request Information
Operator Cruise ID:
Chief Scientist: Al Plueddemann, WHOI
Activity Type: At Sea for Science
Created By: Kerry Strom
Compare Request:
Project Short Title: OOI Pioneer
Requested Year: 2017
Requested Ship: Neil Armstrong  
Request Type: Primary  
Created By: Paul Matthias  
Load Non-charge Days: 2
Load Charge Days: 0   Load Date: 10/20/2017
Activity Days: 4 Adjustment Days Start Date: 10/22/2017
Transit Days: 0 0 End Date: 10/25/2017
Unload Charge Days: 0   Unload Date: 10/26/2017
Unload Non-charge Days: 1
Mob Days: 2  
Science Days: 21 Optimum Start Date: 9/15/2017
Transit Estimate: 0 Earliest Start Date: 9/1/2017
Demob Days: 2 Latest Start Date: 9/15/2017
Repeating Cruise: Yes Dates To Avoid: Mooring servicing in spring and fall, timed for weather and biofouling cycle
Number of Repeating Cruises: 16 Repeating Interval: every 6 months
Repeating Cruise Comments: Due to deck space, cruise will require two legs, 9 days and 12, with one port day between. Recover, redeploy, refresh power systems and sensors every 6 months.
Justification/Comments: Spring and fall cruises to meet requirement to refresh power and sensors every 6 months, deal with biofouling.
Deck payload when deploying and servicing moorings requires large UNOLS vessel, such as Knorr.
PI   Project/Purpose   Agency   Funding Status   Op Days
Al Plueddemann, WHOI   OOI Pioneer   NSF-OOI/OOI   Funded   4
  Start Port: Woods Hole, MA, USA
  End Port: Woods Hole, MA, USA
Requested Start Port: Woods Hole, MA, USA
Intermediate Port(s): None
Requested End Port: Woods Hole, MA, USA
Port Comments:
  Lat/Long Marsden Grid Navy Op Area
Beginning
41° N / 70° W map
152 map
NA06 map
Ending
41° N / 70° W map
152 map
NA06 map
  Show Degrees Minutes    
 
Op Area Description: NE shelf
  Lat/Long Marsden Grid Navy Op Area
Beginning
39° N / 69° W map
115 map
NA06 map
Ending
41° N / 71° W map
152 map
NA06 map
  Show Degrees Minutes    
 
Op Area Description: NE shelf
Coastal States Requiring Clearance: NONE(T)
Foreign Clearance Required: No
Foreign Clearance Comments:
Ancil Facilities:
Instrumentation Requested: Dynamic Positioning
Multibeam
Dredging/Coring/Large Dia. Trawl Wire
Instrumentation Comments: Trawl in case of ned to drag for moorings.
Ancil Facilities Requested:
Ancil Facility Comments: Intermediate vessel with dynamic positioning, crane rated to 7000 lbs, A-frame to 10 tons. 1200 sq ft working deck area; 60,000 lb ship deck load; 9,000 m 9/16 th trawl wire, 12 days endurance, experience with mooring operations.
External Cruise Webpage:
Cruise Notes: Arrived a day early d/t wx, & departed a day early.
4/5: Eric said to keep the 10/22 departure date for needed OOI preparation. He will add 2 legs in shortly...