View Cruise

  Schedule Information  
Ship: Neil Armstrong Schedule Status: Final Schedule ID: 13492
Schedule Year: 2017 Schedule Name: FOY
Notes: 12/14: Arrived one day earlier d/t WX. ONR funds the lost day so day count stays the same.
11/17: Miksis-Olds cruise will depart 1 day later d/t wx, ONR kindly funding the lost day.
11/2: OOI Pioneer (Fall) Leg A, arrived a day early d/t wx, & departed a day early (Same day count)
10/3: Captain updates WHOI arrival to Oct 12th for Behn transit
9/28: Keigwin arriving a day early
9/25: Reduce the last cruise of the year, ADEON by 2 days as per the PI.
9/18: Corrected drydock departure from Feb 16th to 15th (was double billed [47-46 days])
9/18: Also corrected Keigwin arrival departure dates as UNOLS will not accept the 2nd of Oct to be an arrival & departure day.
8/24: 6 day earlier arrival d/t good wx & operations. OOI will pay for 3 of the 6 lost days. 1 crew member/ medical evacuation.
7/25: Shift WHOI days 1 day to left
7/1: Added 1 funded day to Geyer as per email 6/28.
5/23: Add 3/25 as an operational day.
5/22: Keigwin will arrive/ depart on the same day. Transit will be 10 funded days.
5/19: 1 day added to Azores transit for magnatometer tow work.
5/17: Extra port day in 3rd leg of OOI, ONR "In Port Days" for NYC Event.
4/24: Added 3 legs to Fall OOI Pioneer, Corrected Keigwin's days from 25 to 22.
4/21: Added 2 WHOI Inst. Days before Keigwin & removed 1 day in Azores
4/5: Added 4 mobe days to Keigwin and 1 demobe in Azores for replenishment.
...Put WHOI Inst. Days to "Non-Op"
...Vessel arrived 1730/4 d/t wx, keeping operational days the same to maintain annual funded day count in schedule.
4/3: Corrected March 3 (wx day) to count, so departed 3/2 to get proper 9 days.
3/22: Depart 1 day earlier for NYC PR (5/23)
3/22: Demobe only 1 day so Geyer can depart earlier (6/23)
3/20: Becker unplanned returned to WHOI to pick up winch (3/16-17)-added a voyage/ port call (no Voyage number).
3/3: Becker departure was delayed 1 day d/t wx
2/17: Departed ship yard 2 days later than planned (was 2/15)
2/7: 2nd leg of Becker changed from March 16th to the 17th.
2/2: Split out OOI legs as per email 2/2
1/27: Added a 4th leg to Becker
1/23: OOI Pioneer (Fall) keep Oct.22-Nov.11.
1/23: Add Newport, RI pitstop to Becker (3/16)
1/18: Remove SVC coring from Keigwin until further notice.
1/9: Geyer asks to deduct 1 science day d/t vessel traffic holiday weekend. Left 4th of July open at WHOI.
1/5: Agreed to shorten the PR event by 2 days
11/7: SVC7 for coring will be done at the front of the Keigwin voyage.
11/3: Savidge and Geyer need to go back to original schedule due to personnel/ vsl traffic respectively.
10/25: PR Event after Becker, VanMooy & Savidge...
10/24: Coring arm install, SVC, WHOI Days, PR
9/01: SVC7 2016 pushed into 2017 (Coring), maybe during WHOI institutional days in Block Isl. Sound w/ Donnelly & Kegwin...TBD
8/30: Savidge transit removed
2017 schedule adjusted for 10 knots as per Port Ops.
Becker is a 3 ship operation. Armstrong + Endeavor + Sharp. March 31st was the agreed start date in March 2016 scheduling meeting.

Adjusted Navy dates 6/23 (Jon's email 6/23)

7/25: A. Bower & Saito deleted d/t denied funding
  Cruise Information  
Ship Request Information
Operator Cruise ID:
Chief Scientist: Albert Suchy, WHOI
Activity Type: At Sea for Science
Created By: Kerry Strom
Compare Request:
Project Short Title:
Requested Year:
Requested Ship:  
Request Type:  
Created By:  
Load Non-charge Days: 0
Load Charge Days: 0   Load Date: 2/16/2017
Activity Days: 0 Adjustment Days Start Date: 2/16/2017
Transit Days: 5 0 End Date: 2/20/2017
Unload Charge Days: 0   Unload Date: 2/20/2017
Unload Non-charge Days: 0
Mob Days:  
Science Days: Optimum Start Date:
Transit Estimate: Earliest Start Date:
Demob Days: Latest Start Date:
Repeating Cruise: Dates To Avoid:
Number of Repeating Cruises: Repeating Interval:
Repeating Cruise Comments:
Justification/Comments:
PI   Project/Purpose   Agency   Funding Status   Op Days
  Testing   NAVY/ONR   Funded   2
  2 days NON OP   OTHER   Funded   0
  Start Port: Charleston, SC, USA
  End Port: Woods Hole, MA, USA
Requested Start Port:
Intermediate Port(s):
Requested End Port:
Port Comments:
  Lat/Long Marsden Grid Navy Op Area
Beginning
0° N / 0° E map
335 map
SA02 map
Ending
0° N / 0° E map
335 map
SA02 map
  Show Degrees Minutes    
 
Op Area Description: Transit
  Lat/Long Marsden Grid Navy Op Area
Beginning
Ending
 
Op Area Description:
Coastal States Requiring Clearance: NONE(T)
Foreign Clearance Required:
Foreign Clearance Comments:
Ancil Facilities:
Instrumentation Requested:
Instrumentation Comments:
Ancil Facilities Requested:
Ancil Facility Comments:
External Cruise Webpage:
Cruise Notes: 2 days of transit are funded by ONR for testing.
4 days of transit are non-op, but can't show both in 1 transit, so have day count as "0"