  Schedule Information  
Ship: Neil Armstrong Schedule Status: Final Schedule ID: 13727
Schedule Year: 2018 Schedule Name: Version 16
Notes: 11/28: Arrives 1 day early for Savidge d/t bad wx (was 11/29)
11/17: Departs 1 day later for Savidge d/t bad wx (was 11/16)
10/27-28: Pioneer Pit stop to pick up critical spare parts for science mission
10/24: Vessel returned from 1st Pioneer leg 1 day later d/t wx
10/19: Deadhead allocation correction from Iceland to WHOI (from Global to Ocean class policy)
10/15: Arrive WHOI 1 day late d/t wx. Removed 1 of the 3 demobe days to compensate for delayed arrival. 1 day added to OOI account on the transit. 1 day added to the overall schedule (248 to 249).
10/2: Armstrong's Pickart cruise returns a day earlier.
9/4: Hodgkiss returns 2 days earlier (day count stays the same)
8/1: Vsl arrives Reykjavik 1 day earlier d/t wx
7/25: Fall Pioneer legs updated
5/15: 1 day late in Reykjavik d/t wx
4/6: Main crane failure, emergency port stop 4/ 6th-8th.
2/12: 1 day shift to the left starting on Spring Pioneer to add 1 day into deadhead transit up to Reykjavik/ Removed 1 day from the 4 day demobe at WHOI after the deadhead transit from Reykjavik (scheduling oversight).
Remove March WHOI Inst Days place holder.
Changed 57 days alongside to "Laydays" not "Available"
Add 3 days before PEACH for WHOI Inst Days.
1/6: Non-paid day at sea for maintenance and testing on Jan 24th.
Jan 23rd USCG COI
12/15: MacKinnon (Harper) will use 2 days at WHOI to mobe before transit
11/25: Spring Pioneer in 2 legs
11/22: Shift deadhead from WHOI 1 day to the left...Give Hodgkiss 1 more mobe day & adjust spring OOI into 2 legs (not 3).
11/13: INSURV scheduled for week of 12/17/18
10/4: ONR granted 4 additional days of funding to accommodate Hodgkiss swap
9/15: Shifted everything fm MacKinnon 2 days to the right to give the ship 5 days prep at WHOI
9/7: Thanksgiving 2018 is Nov. 22nd
8/30: Peters not funded
6/28: Evans & Garwakawicz "W"
6/27: Martens & Duda "W"
6/16: Send not funded
6/13: Mak Saito on Atlantic Explorer? (Clio already in Bermuda)
6/13: Lyle changed his STR to a 1 month later start date (Endeavor or AE?)
6/13: Bucklin "W"
D'Hont, Miksis-Olds & Toole on Endeavor
6/2: Johns & Bower updated STR's
4/3: Toole deferring his spring mission to 2019 (not ready)
3/27: Updated OOI Pioneer & Irminger science days
3/2: Toole may have to go on Atlantic Explorer/ Endeavor. He may delay 1st of 2 voyages TBD.
2/20: Hutchin's OUT (on Atlantis)/ Saito & Hodgekiss IN
2/1: Hutchins in, half of Herbert in (remainder on Endeavor), Savidge out (2 voyages), Miksis out (1 of 2 voyages), D'Hont Out...SAVIDGE #1 back in
  Cruise Information  
Ship Request Information
Operator Cruise ID: AR30-04
Chief Scientist: William E. Johns, RSMAS
Activity Type: At Sea for Science
Created By: Kerry Strom
Compare Request:
Project Short Title: OSNAP East 2018
Requested Year: 2018
Requested Ship: Neil Armstrong  
Request Type: Primary  
Created By: William E. Johns  
Load Non-charge Days: 0
Load Charge Days: 4   Load Date: 6/27/2018
Activity Days: 24 Adjustment Days Start Date: 7/1/2018
Transit Days: 5 0 End Date: 7/29/2018
Unload Charge Days: 2   Unload Date: 7/31/2018
Unload Non-charge Days: 0
Mob Days: 2  
Science Days: 22 Optimum Start Date: 7/1/2018
Transit Estimate: 4 Earliest Start Date: 7/1/2018
Demob Days: 1 Latest Start Date: 8/1/2018
Repeating Cruise: No Dates To Avoid: This cruise is one of a series of internationally-coordinated, annual project cruises that are targeted for the July-Aug time frame, to provide regular ~1 yr intervals between mooring servicing operations, and timed to occur during good working (weather) conditions.
Number of Repeating Cruises: 0 Repeating Interval:
Repeating Cruise Comments: N/A
Justification/Comments: The cruise requires a large ship (Ocean class/Knorr equivalent), to hold all the required mooring gear. This cruise is one of a series of internationally-coordinated, annual project cruises that are targeted for the July-Aug time frame, to provide regular ~1 yr intervals between mooring servicing operations, and timed to occur during good working (weather) conditions.
PI   Project/Purpose   Agency   Funding Status   Op Days
William E. Johns, RSMAS   OSNAP East 2018   NSF/OCE/PO   Funded   30
  3 Dutch Days   NSF/OCE/PO   Funded   3
  2 days mobelization   NAVY/ONR   Funded   2
  Start Port: Reykjavik, Iceland
  End Port: Reykjavik, Iceland
Requested Start Port: Reykjavik, Iceland
Intermediate Port(s): None
Requested End Port: Reykjavik, Iceland
Port Comments: Alternate port for beginning or end of cruise could be in Ireland or western Scotland, (Ii.e. Belfast, Dublin, Glasgow).
  Lat/Long Marsden Grid Navy Op Area
Beginning
64° N / 20° W map
219 map
NA01 map
Ending
64° N / 20° W map
219 map
NA01 map
  Show Degrees Minutes    
 
Op Area Description: North Atlantic
  Lat/Long Marsden Grid Navy Op Area
Beginning
57° N / 9° W map
181 map
NA05 map
Ending
59° N / 31° W map
184 map
NA04 map
  Show Degrees Minutes    
 
Op Area Description: North Atlantic
Coastal States Requiring Clearance: United Kingdom(A)
Foreign Clearance Required: Yes
United Kingdom
Foreign Clearance Comments: N/A
Ancil Facilities:
Instrumentation Requested: ADCP
Multibeam
Other Operator Provided Inst. - Describe
PI-Provided Vans - briefly describe
Instrumentation Comments: Mooring Winch
Ancil Facilities Requested: Mooring Spooler
Ancil Facility Comments: A double-capstain (Lebus) winch is needed, if available.
External Cruise Webpage:
Cruise Notes: 10/4: 2 additional days granted from ONR to delay Pickart cruise by 4 days and accommodate the cruise swaps for Hodgkiss.

Rey to job start 650nm/ 11/ 24 = 2.4 days
Job finish to Rey 450nm/ 11/ 24 = 1.7 days