23 September 2009
|
Final -
ID #10543
Version #8 -
9/1/2016
|
|
|
Notes: |
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 25 Dec 2009 |
Dep: | 30 Dec 2009 |
Arr: | 07 Feb 2010 |
Unload: | 10 Feb 2010 |
|
|
|
|
|
|
|
|
Hugh Ducklow
|
|
40/48
|
|
Project
|
PI/Institution
|
Project #
|
Days/Agency/Status
|
|
|
Not Specified
|
40/NSF-OPP-ARC/F
|
|
|
External Cruise Webpage: http://pal.lternet.edu/ |
Notes: Other PIs include: Douglas Martinson, Deborah Steinberg, Oscar Schoefiled, William Fraser, Michael Bender. |
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 10 Feb 2010 |
Dep: | 13 Feb 2010 |
Arr: | 26 Mar 2010 |
Unload: | 27 Mar 2010 |
|
|
|
|
|
|
|
|
|
|
42/46
|
|
Project
|
PI/Institution
|
Project #
|
Days/Agency/Status
|
|
|
Not Specified
|
42/NSF-OPP-ARC/F
|
|
|
Notes: Palmer Station Logistics |
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 27 Mar 2010 |
Dep: | 27 Mar 2010 |
Arr: | 09 Apr 2010 |
Unload: | 09 Apr 2010 |
|
|
|
|
|
|
|
|
Maintenance
|
|
14/14
|
|
Project
|
PI/Institution
|
Project #
|
Days/Agency/Status
|
|
|
Notes: Vessel maintenance in Punta Arenas, Chile |
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 10 Apr 2010 |
Dep: | 10 Apr 2010 |
Arr: | 29 Apr 2010 |
Unload: | 02 May 2010 |
|
|
|
|
|
|
|
|
William Detrich
|
|
20/23
|
|
Project
|
PI/Institution
|
Project #
|
Days/Agency/Status
|
|
|
Not Specified
|
20/NSF-OPP-ARC/F
|
|
|
Notes: Detrich cruise #1, Palmer Station turnover. |
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 02 May 2010 |
Dep: | 04 May 2010 |
Arr: | 08 Jun 2010 |
Unload: | 11 Jun 2010 |
|
|
|
|
|
|
|
|
William Detrich
|
|
36/41
|
|
|
|
Notes: Detrich cruise #2, Palmer Station turnover |
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 11 Jun 2010 |
Dep: | 14 Jun 2010 |
Arr: | 13 Sep 2010 |
Unload: | 16 Sep 2010 |
|
|
|
|
|
|
|
|
Available for Service
|
|
92/98
|
|
Project
|
PI/Institution
|
Project #
|
Days/Agency/Status
|
|
|
Not Specified
|
0/NSF-OPP-ARC/NonOp
|
|
|
Notes: Open Period |
|
|
|
|
|
Agency
| |
Funded
| |
Pending
| |
Total
|
NSF
| |
138
| |
0
| |
138
|
Total
| | 138 | | 0 | | 138 |
|
<
|
<
|