  2020 - Endeavor  
Sosik/Allen/Makris Rev G - 10.9.19
Secure - ID #13812    Version #5 - 2/28/2020

Scheduling Contact(s)
Thomas Glennon thomas_glennon*%*%*uri^%^%^edu (401) 465-3606

  Notes:   Disregard previous version (Rev F), all cruises were duplicated.
10.24.19 Moved Young cruise to early October due to SENTRY schedule change.
1.16.20 Removed 7 day Wang (Project ID:106345), moved to 2021 schedule as Pending.
1.16.20 Removed 12 day Menden-Deuer Chief Sci training Cruise, moved to 2021 schedule as Pending
1.24.20 Added 8 day Edelmann Cruise 6.18 - 6.25
2.6.20 Moved Omand cruise from Sept to Nov
2.28.20 Shifted Lohmann, Johns, and STEMSEAs 3 days each due to delay.
  View Summary     Set Default Associated Cruises
Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Jan 2020
Dep:01 Jan 2020
Arr:29 Jan 2020
Unload:29 Jan 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
Overhaul or Repair
  29/29

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:30 Jan 2020
Dep:01 Feb 2020
Arr:06 Feb 2020
Unload:07 Feb 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
WH-Pioneer/
NA06
NA06
 
 
 
42N/71W
42N/71W
 
  Heidi M. Sosik
  6/9

Clearances: NONE(T)

Ancil Facs: Radioisotope Lab Van
 
Project PI/Institution Project # Days/Agency/Status
NES-LTER Heidi M. Sosik/WHOI 1655686 9/NSF-OCE/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:08 Feb 2020
Dep:08 Feb 2020
Arr:10 Feb 2020
Unload:10 Feb 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
General Upkeep and Outfitting
  3/3

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:11 Feb 2020
Dep:12 Feb 2020
Arr:21 Feb 2020
Unload:22 Feb 2020
 
Narragansett, RI, USA
Bridgetown, Barbados
 
E. Atlantic/
NA06
NA09
 
 
 
41N/71W
17N/68W
 
  Rainer Lohmann
Transit Cruise
  10/12

Clearances: Senegal(T)
 
Project PI/Institution Project # Days/Agency/Status
Tropical Atlantic BC Rainer Lohmann/URI_GSO 1924191 12/NSF-OCE-CO/F
 
Notes: All transit days, URI to Barbados and Cape Verde to Port Everglades, split proportionally between Lohmann/Johns.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:23 Feb 2020
Dep:24 Feb 2020
Arr:17 Mar 2020
Unload:18 Mar 2020
 
Bridgetown, Barbados
Praia, Sao Tiago, Cape Verde Islands
 
E. Atlantic/
NA09
NA10
 
 
 
17N/68W
15N/22W
 
  Rainer Lohmann
  23/25

Clearances: Senegal(T)
 
Project PI/Institution Project # Days/Agency/Status
Tropical Atlantic BC Rainer Lohmann/URI_GSO 1924191 25/NSF-OCE-CO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:16 Mar 2020
Dep:17 Mar 2020
Arr:25 Mar 2020
Unload:25 Mar 2020
 
Praia, Sao Tiago, Cape Verde Islands
Port Everglades, FL, USA
 
E. Atlantic/
NA10
NA09
 
 
 
15N/22W
17N/68W
 
  Rainer Lohmann
Transit Cruise
  9/10

Clearances: Senegal(T)
 
Project PI/Institution Project # Days/Agency/Status
Tropical Atlantic BC Rainer Lohmann/URI_GSO 1924191 10/NSF-OCE-CO/F
 
Notes: All transit days, URI to Barbados and Cape Verde to Port Everglades, split proportionally between Lohmann/Johns.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:26 Mar 2020
Dep:26 Mar 2020
Arr:30 Mar 2020
Unload:31 Mar 2020
 
Praia, Sao Tiago, Cape Verde Islands
Port Everglades, FL, USA
 
E. Atlantic/
NA10
NA09
 
 
 
15N/22W
17N/68W
 
  William E. Johns
Transit Cruise
  5/6

Clearances: Senegal(T)
 
Project PI/Institution Project # Days/Agency/Status
RAPID-MOCHA 2019 William E. Johns/RSMAS 1926008 6/NSF-OCE-PO/F
 
Notes: All transit days, URI to Barbados and Cape Verde to Port Everglades, split proportionally between Lohmann/Johns.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Apr 2020
Dep:02 Apr 2020
Arr:19 Apr 2020
Unload:21 Apr 2020
 
Port Everglades, FL, USA
Port Everglades, FL, USA
 
S. Atlantic/
NA09
NA09
 
 
 
26N/80W
26N/80W
 
  William E. Johns
  18/21

Clearances: Bahamas(T)
 
Project PI/Institution Project # Days/Agency/Status
RAPID-MOCHA 2019 William E. Johns/RSMAS 1926008 21/NSF-OCE-PO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:22 Apr 2020
Dep:22 Apr 2020
Arr:28 Apr 2020
Unload:28 Apr 2020
 
Port Everglades, FL, USA
Narragansett, RI, USA
 
S. Atlantic/
NA09
NA06
 
 
 
26N/80W
41N/71W
 
  William E. Johns
Transit Cruise
  7/7

Clearances: Bahamas(T)
 
Project PI/Institution Project # Days/Agency/Status
RAPID-MOCHA 2019 William E. Johns/RSMAS 1926008 7/NSF-OCE-PO/F
 
Notes: All transit days, URI to Barbados and Cape Verde to Port Everglades, split proportionally between Lohmann/Johns. Additional transit day added to accommodate STEMSEAS science ops.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:29 Apr 2020
Dep:29 Apr 2020
Arr:18 May 2020
Unload:18 May 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
General Upkeep and Outfitting
  20/20

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:19 May 2020
Dep:20 May 2020
Arr:23 May 2020
Unload:24 May 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  John M. Toole
  4/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
LAMP John M. Toole/WHOI 7668649 6/NSF-OCE-OTIC/F
 
Notes: This purpose of this science mission is to retrieve the mooring that was deployed off Endeavor in Oct 2019.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:25 May 2020
Dep:25 May 2020
Arr:26 May 2020
Unload:26 May 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
General Upkeep and Outfitting
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:27 May 2020
Dep:28 May 2020
Arr:04 Jun 2020
Unload:05 Jun 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
New England/
NA06
NA06
 
 
 
40N/70W
40N/70W
 
  Glen Gawarkiewicz
  8/10

Clearances: NONE(T)

Ancil Facs: Other AUV, AUV Lab Van #1
 
Project PI/Institution Project # Days/Agency/Status
Salinity Intrusions Glen Gawarkiewicz/WHOI 1851261 10/NSF-OCE-PO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:06 Jun 2020
Dep:06 Jun 2020
Arr:06 Jun 2020
Unload:06 Jun 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
Outreach
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:07 Jun 2020
Dep:07 Jun 2020
Arr:17 Jun 2020
Unload:17 Jun 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
General Upkeep and Outfitting
  11/11

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:18 Jun 2020
Dep:19 Jun 2020
Arr:24 Jun 2020
Unload:25 Jun 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Geoffrey F. Edelmann
  6/8

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Reliable ACOMMS Geoffrey F. Edelmann/NRL-DC Not Specified 8/NAVY-NRL/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:26 Jun 2020
Dep:26 Jun 2020
Arr:30 Jun 2020
Unload:30 Jun 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
General Upkeep and Outfitting
  5/5

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Jul 2020
Dep:02 Jul 2020
Arr:17 Jul 2020
Unload:18 Jul 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
Gulf of Maine/
NA06
NA06
 
 
 
42N/68W
42N/68W
 
  Purnima R. Makris
  16/18

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
NEU Array Purnima R. Makris/Nthest U 1736749 18/NSF-OCE-OTIC/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:19 Jul 2020
Dep:19 Jul 2020
Arr:21 Jul 2020
Unload:21 Jul 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
General Upkeep and Outfitting
  3/3

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:22 Jul 2020
Dep:24 Jul 2020
Arr:29 Jul 2020
Unload:30 Jul 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
WH-Pioneer/
NA06
NA06
 
 
 
42N/71W
42N/71W
 
  Heidi M. Sosik
  6/9

Clearances: NONE(T)

Ancil Facs: Radioisotope Lab Van
 
Project PI/Institution Project # Days/Agency/Status
NES-LTER Heidi M. Sosik/WHOI 1655686 9/NSF-OCE/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:31 Jul 2020
Dep:31 Jul 2020
Arr:05 Aug 2020
Unload:05 Aug 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
General Upkeep and Outfitting
  6/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:06 Aug 2020
Dep:07 Aug 2020
Arr:09 Aug 2020
Unload:10 Aug 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  David C. Smith
  3/5

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
David C. Smith/URI_GSO Not Specified 5/INST-URI-GSO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:11 Aug 2020
Dep:11 Aug 2020
Arr:16 Aug 2020
Unload:16 Aug 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
General Upkeep and Outfitting
  6/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:17 Aug 2020
Dep:18 Aug 2020
Arr:27 Aug 2020
Unload:28 Aug 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
Gulf of Maine/
NA06
NA06
 
 
 
42N/71W
42N/71W
 
  Katherine A. Allen
  10/12

Clearances: NONE(T)

Ancil Facs: Large Gravity Core
 
Project PI/Institution Project # Days/Agency/Status
Gulf of Maine Katherine A. Allen/Maine 1847742 12/NSF-OCE-MGG/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:29 Aug 2020
Dep:29 Aug 2020
Arr:20 Sep 2020
Unload:20 Sep 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
General Upkeep and Outfitting
  23/23

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:21 Sep 2020
Dep:21 Sep 2020
Arr:28 Sep 2020
Unload:28 Sep 2020
 
Narragansett, RI, USA
Gulfport, MS, USA
 
GOM/
NA06
NA09
 
 
 
41N/71W
29N/88W
 
  Craig M. Young
Transit Cruise
  8/8

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
seep larval dispersa Craig M. Young/OIMB 1851383 8/NSF-OCE-BIO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:29 Sep 2020
Dep:01 Oct 2020
Arr:18 Oct 2020
Unload:20 Oct 2020
 
Gulfport, MS, USA
Morehead City, NC, USA
 
GOM/
NA09
NA06
 
 
 
29N/88W
34N/76W
 
  Craig M. Young
  18/22

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
seep larval dispersa Craig M. Young/OIMB 1851383 22/NSF-OCE-BIO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:21 Oct 2020
Dep:21 Oct 2020
Arr:24 Oct 2020
Unload:24 Oct 2020
 
Morehead City, NC, USA
Narragansett, RI, USA
 
GOM/
NA06
NA06
 
 
 
34N/76W
41N/71W
 
  Craig M. Young
Transit Cruise
  4/4

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
seep larval dispersa Craig M. Young/OIMB 1851383 4/NSF-OCE-BIO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:25 Oct 2020
Dep:25 Oct 2020
Arr:02 Nov 2020
Unload:02 Nov 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
General Upkeep and Outfitting
  9/9

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:03 Nov 2020
Dep:04 Nov 2020
Arr:09 Nov 2020
Unload:10 Nov 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Melissa M. Omand
  6/8

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Melissa M. Omand/URI_GSO Not Specified 8/INST-URI-GSO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:11 Nov 2020
Dep:11 Nov 2020
Arr:24 Nov 2020
Unload:24 Nov 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
Available for Service
  14/14

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:25 Nov 2020
Dep:25 Nov 2020
Arr:30 Nov 2020
Unload:30 Nov 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
Overhaul or Repair
  6/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Dec 2020
Dep:01 Dec 2020
Arr:02 Dec 2020
Unload:02 Dec 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
Inspection
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: NSF 2 day biennial vessel survey/inspection - 1 dockside, 1 at sea.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:03 Dec 2020
Dep:03 Dec 2020
Arr:31 Dec 2020
Unload:31 Dec 2020
 
Narragansett, RI, USA
Narragansett, RI, USA
 
N Atlantic/
NA06
NA06
 
 
 
41N/71W
41N/71W
 
  Thomas Glennon
Overhaul or Repair
  29/29

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Agency   Funded   Pending   Total
INST   13   0   13
NAVY   8   0   8
NSF   179   0   179
Total  200 0 200
<
Day Type   Total
Available for Service   14
Transit Cruise   43
General Upkeep and Outfitting   88
Inspection   2
Overhaul or Repair   64
At Sea for Science   124
Outreach   1
Total  336
<
Load/Unload Days   Total
ChargeLoad   17
ChargeUnload   16
Total  33