View Schedule

or schedule as:
the schedule as:
  2021 - Oceanus  
OCEANUS 2021
Secure - ID #14408    Version #6 - 5/28/2021

Scheduling Contact(s)
Kaya Johnson kaya^%^%^johnson*%*%*oregonstate^%^%^edu (971) 563-0790
Christine Golden goldenc*%*%*oregonstate^%^%^edu (541) 867-0200
Roberta Mesa roberta^%^%^mesa*%*%*oregonstate^%^%^edu (541) 867-0295

  Notes:  
  View Summary     Set Default Associated Cruises
Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Jan 2021
Dep:01 Jan 2021
Arr:28 Mar 2021
Unload:28 Mar 2021
 
Newport, OR, USA
Newport, OR, USA
 
home port/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Kaya Johnson
Available for Service
  87/87

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:29 Mar 2021
Dep:30 Mar 2021
Arr:07 Apr 2021
Unload:08 Apr 2021
 
Newport, OR, USA
Newport, OR, USA
 
OR WA Coast/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  James W. Moffett
  9/11

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Iron Shuttle James W. Moffett/USC 2023708 18/NSF-OCE-CO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:09 Apr 2021
Dep:09 Apr 2021
Arr:18 Apr 2021
Unload:18 Apr 2021
 
Newport, OR, USA
Newport, OR, USA
 
home port/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Kaya Johnson
General Upkeep and Outfitting
  10/10

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:19 Apr 2021
Dep:20 Apr 2021
Arr:23 Apr 2021
Unload:24 Apr 2021
 
Newport, OR, USA
Newport, OR, USA
 
Oregon Coast/
NP09
NP09
 
 
 
45N/124W
45N/124W
 
  Jack A. Barth
  4/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Oregon Ship Time Jack A. Barth/OSU-CEOAS Not Specified 5/STATE/F
 
Notes: rollover from 2020

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:25 Apr 2021
Dep:25 Apr 2021
Arr:26 Apr 2021
Unload:26 Apr 2021
 
Newport, OR, USA
Newport, OR, USA
 
home port/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Kaya Johnson
General Upkeep and Outfitting
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:27 Apr 2021
Dep:27 Apr 2021
Arr:13 May 2021
Unload:13 May 2021
 
Newport, OR, USA
Newport, OR, USA
 
home port/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Kaya Johnson
Available for Service
  17/17

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:14 May 2021
Dep:14 May 2021
Arr:18 May 2021
Unload:18 May 2021
 
Newport, OR, USA
Newport, OR, USA
 
home port/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Kaya Johnson
General Upkeep and Outfitting
  5/5

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:19 May 2021
Dep:23 May 2021
Arr:19 Jun 2021
Unload:21 Jun 2021
 
Newport, OR, USA
Newport, OR, USA
 
West Coast/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Nathaniel Miller
  28/34

Clearances: NONE(T)

Ancil Facs: Ocean Bottom Seismograph Instrument Center (OBSIC)
 
Project PI/Institution Project # Days/Agency/Status
Cascadia forearc Juan Pablo Canales/WHOI 1929545 34/NSF-OCE-MGG/F
 
Notes: rollover from 2020; highest priority

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:22 Jun 2021
Dep:23 Jun 2021
Arr:14 Jul 2021
Unload:15 Jul 2021
 
Newport, OR, USA
Port Angeles, WA, USA
 
West Coast/
NP09
NP09
 
 
 
44N/124W
48N/123W
 
  Nathaniel Miller
  22/24

Clearances: NONE(T)

Ancil Facs: Ocean Bottom Seismograph Instrument Center (OBSIC)
 
Project PI/Institution Project # Days/Agency/Status
Cascadia forearc Juan Pablo Canales/WHOI 1929545 24/NSF-OCE-MGG/F
 
Notes: rollover from 2020; highest priority

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:16 Jul 2021
Dep:16 Jul 2021
Arr:17 Jul 2021
Unload:17 Jul 2021
 
Port Angeles, WA, USA
Newport, OR, USA
 
NA/
NP09
NP09
 
 
 
48N/123W
44N/124W
 
  Kaya Johnson
Transit Cruise
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:18 Jul 2021
Dep:18 Jul 2021
Arr:19 Jul 2021
Unload:19 Jul 2021
 
Newport, OR, USA
Newport, OR, USA
 
home port/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Kaya Johnson
General Upkeep and Outfitting
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:20 Jul 2021
Dep:21 Jul 2021
Arr:12 Aug 2021
Unload:13 Aug 2021
 
Newport, OR, USA
Newport, OR, USA
 
OR Coast/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  James W. Moffett
  23/25

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Iron Shuttle James W. Moffett/USC 2023708 18/NSF-OCE-CO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:14 Aug 2021
Dep:14 Aug 2021
Arr:20 Aug 2021
Unload:20 Aug 2021
 
Newport, OR, USA
Newport, OR, USA
 
home port/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Kaya Johnson
Available for Service
  7/7

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:21 Aug 2021
Dep:22 Aug 2021
Arr:25 Aug 2021
Unload:26 Aug 2021
 
Newport, OR, USA
Newport, OR, USA
 
NP09/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Jack A. Barth
  4/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 6/STATE/P
 
Notes: PI = Valerie Sahakian

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:27 Aug 2021
Dep:28 Aug 2021
Arr:30 Aug 2021
Unload:31 Aug 2021
 
Newport, OR, USA
Newport, OR, USA
 
NP09/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Jack A. Barth
  3/5

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 5/STATE/P
 
Notes: PI = Craig Young

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Sep 2021
Dep:01 Sep 2021
Arr:01 Sep 2021
Unload:01 Sep 2021
 
Newport, OR, USA
Newport, OR, USA
 
N/A/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Kaya Johnson
General Upkeep and Outfitting
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:02 Sep 2021
Dep:03 Sep 2021
Arr:07 Sep 2021
Unload:08 Sep 2021
 
Newport, OR, USA
Newport, OR, USA
 
NP09/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Jennifer Fehrenbacher
  5/7

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
PNW Foram Ecology Jennifer Fehrenbacher/OSU_Oregon State 2049143 0/NSF-OCE-MGG/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:09 Sep 2021
Dep:09 Sep 2021
Arr:09 Sep 2021
Unload:09 Sep 2021
 
Newport, OR, USA
Newport, OR, USA
 
home port/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Kaya Johnson
General Upkeep and Outfitting
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:10 Sep 2021
Dep:11 Sep 2021
Arr:26 Sep 2021
Unload:26 Sep 2021
 
Newport, OR, USA
Newport, OR, USA
 
offSanFrancisco/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Eric Jolliffe
  16/17

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:27 Sep 2021
Dep:27 Sep 2021
Arr:30 Sep 2021
Unload:30 Sep 2021
 
Newport, OR, USA
Newport, OR, USA
 
inport/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Kaya Johnson
Available for Service
  4/4

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Oct 2021
Dep:02 Oct 2021
Arr:06 Oct 2021
Unload:07 Oct 2021
 
Newport, OR, USA
Newport, OR, USA
 
NP09/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Jenna Hill
  5/7

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:08 Oct 2021
Dep:08 Oct 2021
Arr:16 Oct 2021
Unload:16 Oct 2021
 
Newport, OR, USA
Newport, OR, USA
 
inport/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Kaya Johnson
Available for Service
  9/9

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:17 Oct 2021
Dep:19 Oct 2021
Arr:08 Nov 2021
Unload:09 Nov 2021
 
Newport, OR, USA
Newport, OR, USA
 
San Francisco/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  John T. Farrar
  21/24

Clearances: US EEZ(T)
 
Project PI/Institution Project # Days/Agency/Status
S-MODE John T. Farrar/WHOI Not Specified 18/NASA/F
IRISS Andrew T. Jessup/UW_APL 2022750 6/NSF-OCE-OTIC/F
 
Notes: 4/2/21: Added Jessup and adjusted days per emails.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:10 Nov 2021
Dep:10 Nov 2021
Arr:13 Nov 2021
Unload:13 Nov 2021
 
Newport, OR, USA
Newport, OR, USA
 
N/A/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Kaya Johnson
General Upkeep and Outfitting
  4/4

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:14 Nov 2021
Dep:15 Nov 2021
Arr:17 Nov 2021
Unload:18 Nov 2021
 
Newport, OR, USA
Newport, OR, USA
 
NP09/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Jack A. Barth
  3/5

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 5/STATE/P
 
Notes: PI = Clare Reimers

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:19 Nov 2021
Dep:19 Nov 2021
Arr:31 Dec 2021
Unload:31 Dec 2021
 
Newport, OR, USA
Newport, OR, USA
 
poss shipyard/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Kaya Johnson
Available for Service
  43/43

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Agency   Funded   Pending   Total
NASA   18   0   18
NSF   100   0   100
STATE   5   16   21
Total  123 16 139
<
Day Type   Total
Available for Service   167
Transit Cruise   2
General Upkeep and Outfitting   25
At Sea for Science   143
Total  337
<
Load/Unload Days   Total
ChargeLoad   16
ChargeUnload   12
Total  28