View Schedule

or schedule as:
the schedule as:
  2009 - Oceanus  
Published
Final - ID #10808    Version #7 - 1/5/2010

Scheduling Contact(s)
Kaya Johnson kaya^%^%^johnson*%*%*oregonstate^%^%^edu (971) 563-0790
Christine Golden goldenc*%*%*oregonstate^%^%^edu (541) 867-0200
Roberta Mesa roberta^%^%^mesa*%*%*oregonstate^%^%^edu (541) 867-0295

  Notes:   Please note shipyard port may change.
1/15: Added 4 days for Toole Mooring work
2/2: added 10 days for Anderson in Oct
2/26: changed shipyard departure date from Jax to 3/6
3/20: Oceanus arrived into WHOI on 3/09
4/22: Added NSF inspection and Bernhard cruise in Sept
4/22: added one day onto the Anderson cruise in Oct.
5/22: added one day onto the front end of the Toole cruise for NAVAIR
8/18: shifted return to WHOI to 8/25 and moved follow on cruises, Bernhard and both Graber.
10/01: Departed for Graber a day later. Sci party needed more inport time
11/09: Dec Graber cruise canceled
  View Summary     Set Default Associated Cruises
Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Jan 2009
Dep:01 Jan 2009
Arr:28 Jan 2009
Unload:28 Jan 2009
 
Woods Hole, MA, USA
 
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Out of Service
  28/28
 
Project PI/Institution Project # Days/Agency/Status
28 Days Non Op Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:29 Jan 2009
Dep:29 Jan 2009
Arr:01 Feb 2009
Unload:01 Feb 2009
 
Woods Hole, MA, USA
Jacksonville, FL, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Transit
  4/4
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 0/OTHER/P

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:02 Feb 2009
Dep:02 Feb 2009
Arr:05 Mar 2009
Unload:05 Mar 2009
 
Jacksonville, FL, USA
 
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Maintenance
  32/32
 
Project PI/Institution Project # Days/Agency/Status
32 SHIP YARD JAX Not Specified 0/OTHER/P

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:06 Mar 2009
Dep:06 Mar 2009
Arr:09 Mar 2009
Unload:09 Mar 2009
 
Jacksonville, FL, USA
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Transit
  4/4
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 0/OTHER/P

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:10 Mar 2009
Dep:10 Mar 2009
Arr:28 May 2009
Unload:28 May 2009
 
Woods Hole, MA, USA
 
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Out of Service
  80/80
 
Project PI/Institution Project # Days/Agency/Status
80 non op Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Jun 2009
Dep:01 Jun 2009
Arr:05 Jun 2009
Unload:05 Jun 2009
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  5/5
 
Project PI/Institution Project # Days/Agency/Status
Culturing deep-sea b Daniel C. McCorkle/WHOI 0647899 5/NSF-OCE-MGG/F
 
Notes: load Friday the 29th or over the weekend

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:07 Jun 2009
Dep:09 Jun 2009
Arr:13 Jun 2009
Unload:15 Jun 2009
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  5/9
 
Project PI/Institution Project # Days/Agency/Status
Line W: A sustained John M. Toole/WHOI 0726720 4/NSF-OCE-PO/F
NAVAIR Not Specified 1/NAVY/F
 
Notes: Moorings. One day for NAVAIR ops on the 10th

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:18 Jun 2009
Dep:18 Jun 2009
Arr:01 Jul 2009
Unload:01 Jul 2009
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  14/14
 
Project PI/Institution Project # Days/Agency/Status
Mag Forecasts William J. Teague/NRL_SSC Not Specified 14/NAVY-NRL/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:06 Jul 2009
Dep:06 Jul 2009
Arr:25 Jul 2009
Unload:25 Jul 2009
 
Woods Hole, MA, USA
Piraievs, Greece
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Transit
  20/20
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 20/NSF-OCE-EDU/F
 
Notes: 4,530 nm from Whoi to Paraeus 17.1, 18 total at 11kts 18.9 days at 10 kts

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:26 Jul 2009
Dep:28 Jul 2009
Arr:05 Aug 2009
Unload:07 Aug 2009
 
Piraievs, Greece
Piraievs, Greece
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  9/13
 
Project PI/Institution Project # Days/Agency/Status
Pickled Protists Virginia P. Edgcomb/WHOI 0849578 13/NSF-OCE-BIO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:08 Aug 2009
Dep:08 Aug 2009
Arr:27 Aug 2009
Unload:27 Aug 2009
 
Piraievs, Greece
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Transit
  20/20
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 20/NSF-OCE-EDU/F
 
Notes: 5,326 nm Paraeus to Port Everglades. 20 days 5 hrs at 11kts, 22.1 at 10kts

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:28 Aug 2009
Dep:28 Aug 2009
Arr:08 Sep 2009
Unload:08 Sep 2009
 
Woods Hole, MA, USA
 
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Out of Service
  12/12
 
Project PI/Institution Project # Days/Agency/Status
12 non-op Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:09 Sep 2009
Dep:09 Sep 2009
Arr:13 Sep 2009
Unload:13 Sep 2009
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  5/5
 
Project PI/Institution Project # Days/Agency/Status
Foram Dispersal Joan M. Bernhard/WHOI ARRA 0850494 5/NSF-OCE-BIO/F
 
Notes: 2 days transit, 2.5 days on station

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:17 Sep 2009
Dep:17 Sep 2009
Arr:18 Sep 2009
Unload:18 Sep 2009
 
Woods Hole, MA, USA
 
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  2/2
 
Project PI/Institution Project # Days/Agency/Status
NSF Inspection Not Specified 0/NSF-OCE-EDU/P
 
Notes: 18th at sea

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:23 Sep 2009
Dep:23 Sep 2009
Arr:27 Sep 2009
Unload:27 Sep 2009
 
Woods Hole, MA, USA
Jacksonville, FL, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Transit
  5/5
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 3/NAVY-ONR/F
Not Specified 2/NSF-OCE-EDU/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:28 Sep 2009
Dep:01 Oct 2009
Arr:05 Oct 2009
Unload:06 Oct 2009
 
Jacksonville, FL, USA
Jacksonville, FL, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  5/9
 
Project PI/Institution Project # Days/Agency/Status
ASI of Typhoons HANS C. GRABER/RSMAS Not Specified 9/NAVY-ONR-OAS/F
 
Notes: Let's look at Deployment Cruise 3 August to transit to study site 4 August to 7 August Science Ops 8 August transit to Port Everglades, FL. Then Recovery Cruise 15 October to transit to study site 16 October to 19 October Science Ops 20 October transit to Port Everglades, FL.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:07 Oct 2009
Dep:07 Oct 2009
Arr:11 Oct 2009
Unload:11 Oct 2009
 
Jacksonville, FL, USA
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Transit
  5/5
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 5/NAVY/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:13 Oct 2009
Dep:15 Oct 2009
Arr:25 Oct 2009
Unload:26 Oct 2009
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  11/14

Clearances: Canada(T)
 
Project PI/Institution Project # Days/Agency/Status
Gulf of Maine cysts Donald Anderson/WHOI NA06NOS4780245 11/NOAA/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:26 Oct 2009
Dep:26 Oct 2009
Arr:31 Dec 2009
Unload:31 Dec 2009
 
Woods Hole, MA, USA
 
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Out of Service
  67/67
 
Project PI/Institution Project # Days/Agency/Status
67 days Not Specified 0/OTHER/NonOp
Agency   Funded   Pending   Total
NAVY   32   0   32
NOAA   11   0   11
NSF   69   0   69
OTHER   0   0   0
Total  112 0 112
<
<