View Schedule

or schedule as:
the schedule as:
  2013 - Sentry  
UPDATED Oct 25, 2013
Final - ID #12071    Version #3 - 2/25/2014

Scheduling Contact(s)
Kerry Strom kstrom*%*%*whoi^%^%^edu (508) 289-3938

  Notes:   10/25: Changed re load date onto Atlantis to Nov 22. Wheat cruise reduced by 7 days. Wheat new cruise dates Dec 7 - Dec 23.

7/16: Added 1 sea day to Camilli cruise and shifted dates later to July 27 - Aug 12.
6/21: Shifted load date for Sentry on Atlantis to Nov 17 in San Diego. Shifted Transit to Costa Rica to Nov 18 ETD. Shifted G. Wheat cruise to Dec 1 - Dec 24. FULL OFF LOAD of Sentry after Wheat cruise.
5/23: Added R. Camilli cruise on EV Nautilus, 20 days in GOM.
5/8: (1) Differ Tivey/Farr cruise to 2014. (2) Schedule shift; Valentine 25 Sept - 16 Oct. / Wheat 22 Nov - 15 Dec. (2) Added 3 days onto Wheat.
1/31/13: New Mob date at UW March 3. Revised Moyer cruise sch Honlulu as start and end port March 16 - April 1.
12/11/12: Changed Mob and Demob times for Moyer cruise March. 2 days mob and 1 day demob.
11/8/12: Published 2013 Sentry Version 1.
10/16/12: Mob Sentry on Thompson March 5 at UW. Updated Schouten end port with added transit time. 2 Engineering dives scheduled. 10 day transit on Atlantis Oct 25 - Nov 3.
  View Summary     Set Default Associated Cruises
Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:02 Mar 2013
Dep:03 Mar 2013
Arr:03 Mar 2013
Unload:03 Mar 2013
 
Seattle, WA, USA
Seattle, WA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  0/1
 
Project PI/Institution Project # Days/Agency/Status
Seamount FeOBs Craig L. Moyer/WWU - Biology 1155756 1/NSF-OCE-BIO/F
RV THOMPSON Not Specified 0/OTHER/F
 
Notes: Mob Sentry at UW on Thompson before transit to Hilo. RV Thompson departs March 6 for Hilo.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:14 Mar 2013
Dep:16 Mar 2013
Arr:01 Apr 2013
Unload:02 Apr 2013
 
Honolulu, HI, USA
Honolulu, HI, USA
 
NW Eifuku/
NP10
NP10
 
 
 
22N/144E
13N/144E
 
  Craig L. Moyer
  17/20
 
Project PI/Institution Project # Days/Agency/Status
Seamount FeOBs Craig L. Moyer/WWU - Biology 1155756 20/NSF-OCE-BIO/F
RV THOMPSON Not Specified 0/OTHER/F
 
Notes: Hilo will be mob port, Honolulu demob port. Heavy mob is done in Seattle.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:12 May 2013
Dep:14 May 2013
Arr:19 Jun 2013
Unload:21 Jun 2013
 
Bridgetown, Barbados
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  37/41
 
Project PI/Institution Project # Days/Agency/Status
Faults at the MAR Hans Schouten/WHOI 1131636 40/NSF-OCE-MGG/F
SENTRY ENG DIVE Carl Kaiser/WHOI Not Specified 1/NOAA/F
RV KNORR Not Specified 0/OTHER/F
Faults at the MAR Hans Schouten/WHOI Not Specified 0/NSF-OCE-EDU/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:24 Jul 2013
Dep:27 Jul 2013
Arr:12 Aug 2013
Unload:13 Aug 2013
 
Galveston, TX, USA
Galveston, TX, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  17/21

Ancil Facs: Sentry
 
Project PI/Institution Project # Days/Agency/Status
Methane Seep GoM Richard Camilli/WHOI Not Specified 21/OTHER/F
E/V NAUTILUS Not Specified 0/OTHER/F
 
Notes: This project is funded as of May 27, 2013.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:22 Sep 2013
Dep:26 Sep 2013
Arr:17 Oct 2013
Unload:19 Oct 2013
 
San Francisco, CA, USA
San Diego, CA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  22/28
 
Project PI/Institution Project # Days/Agency/Status
SEEPS 13 David L. Valentine/UCSB 1046144 13/NSF-OCE-BIO/F
Fate of Natural Gas David L. Valentine/UCSB 1155855 13/NSF-OCE-CO/F
Sentry Eng Dive Not Specified 2/NOAA/F
RV ATLANTIS+ JASON Not Specified 0/OTHER/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:21 Nov 2013
Dep:22 Nov 2013
Arr:22 Nov 2013
Unload:22 Nov 2013
 
San Diego, CA, USA
San Diego, CA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  0/1
 
Project PI/Institution Project # Days/Agency/Status
Doroda Outcrop Charles G. Wheat/UAF_CFOS 1130146 1/NSF-OCE-MGG/F
Mob onto RV ATLANTIS Not Specified 0/OTHER/F
 
Notes: Re loading for Wheat cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:24 Nov 2013
Dep:24 Nov 2013
Arr:03 Dec 2013
Unload:03 Dec 2013
 
San Diego, CA, USA
Puntarenas, Costa Rica
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  10/10
 
Project PI/Institution Project # Days/Agency/Status
Transit Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:04 Dec 2013
Dep:07 Dec 2013
Arr:23 Dec 2013
Unload:25 Dec 2013
 
Puntarenas, Costa Rica
Puntarenas, Costa Rica
 
Costa Rica/
NP13
NP13
 
 
 
9N/87W
9N/84W
 
  Charles G. Wheat
  17/22
 
Project PI/Institution Project # Days/Agency/Status
Doroda Outcrop Charles G. Wheat/UAF_CFOS 1130146 21/NSF-OCE-MGG/F
Sentry Eng Dive Not Specified 1/NOAA/F
RV ATLANTIS & JASON Not Specified 0/OTHER/F
 
Notes: Off load Sentry Dec 23 in Puerto Caldera.
Agency   Funded   Pending   Total
NOAA   4   0   4
NSF   109   0   109
OTHER   21   0   21
Total  134 0 134