  2017 - Sikuliaq  
SKQ 2017 Final (updated) 01Mar2018
Final - ID #13486    Version #2 - 3/1/2018

Scheduling Contact(s)
Doug Baird ddbaird2*%*%*alaska^%^%^edu (907) 224-5261

  Notes:   Accounting for 365 days, with final edits, and updated instructions from 08 Feb 2018 meeting
  View Summary     Set Default Associated Cruises
Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Jan 2017
Dep:01 Jan 2017
Arr:14 Jan 2017
Unload:16 Jan 2017
 
San Diego, CA, USA
Manzanillo, Mexico
 
NP 13/
NP09
NP13
 
 
 
32N/117W
19N/104W
 
  Gabrielle Rocap
  14/16

Clearances: Mexico(A)
 
Project PI/Institution Project # Days/Agency/Status
ODZ dimensions Gabrielle Rocap/UW 1542240 (Diversity) 16/NSF-OCE-BIO/F
 
Notes: This cruise started in mid-December 2016, Sikuliaq was at-sea on January 1st, 2017

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:17 Jan 2017
Dep:19 Jan 2017
Arr:15 Feb 2017
Unload:17 Feb 2017
 
Manzanillo, Mexico
San Diego, CA, USA
 
NP 03/
NP12
NP12
 
 
 
28N/130W
22N/130W
 
  Brad A. Seibel
  28/32

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Metabolic Index Brad A. Seibel/USF_Tampa 1459243 32/NSF-OCE-BIO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:18 Feb 2017
Dep:18 Feb 2017
Arr:28 Feb 2017
Unload:28 Feb 2017
 
San Diego, CA, USA
Honolulu, HI, USA
 
NP9 - NP12/
NP09
NP12
 
 
 
33N/117W
21N/158W
 
  James B. Girton
Transit Cruise
  11/11

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
SMILE James B. Girton/UW_APL 1536314 11/NSF-OCE-PO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Mar 2017
Dep:03 Mar 2017
Arr:04 Apr 2017
Unload:05 Apr 2017
 
Honolulu, HI, USA
Newport, OR, USA
 
NP12-NP9/
NP08
NP12
 
 
 
33N/159W
25N/147W
 
  James B. Girton
  33/36

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
SMILE James B. Girton/UW_APL 1536314 36/NSF-OCE-PO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:06 Apr 2017
Dep:09 Apr 2017
Arr:23 Apr 2017
Unload:24 Apr 2017
 
Newport, OR, USA
Newport, OR, USA
 
NP9/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Edward P. Dever
  15/19

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Endurance Array OM Edward P. Dever/OSU-CEOAS Not Specified 19/NSF-OOI-OOI/F
 
Notes: Due to Newport bar conditions, Sikuliaq departed 1-days late. Originally scheduled to depart on April 8, Vessel was not able to sail until April 9th.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:25 Apr 2017
Dep:26 Apr 2017
Arr:30 Apr 2017
Unload:30 Apr 2017
 
Newport, OR, USA
Seattle, WA, USA
 
NP9/
NP09
NP09
 
 
 
44N/125W
44N/126W
 
  William S. Wilcock
  5/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Oregon Profile ASCPR William S. Wilcock/UW 1558477 5/NSF-OCE-MGG/F
Cascadia CPIES Meng Wei/URI_GSO 1728060 1/NSF-OCE-MGG/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 May 2017
Dep:01 May 2017
Arr:08 May 2017
Unload:08 May 2017
 
Seattle, WA, USA
Seattle, WA, USA
 
NP9/
NP09
NP09
 
 
 
38N/122W
38N/122W
 
  Murray Stein
Maintenance
  8/8

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:09 May 2017
Dep:09 May 2017
Arr:12 May 2017
Unload:12 May 2017
 
Seattle, WA, USA
Seattle, WA, USA
 
Seattle/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Murray Stein
Inspection
  4/4

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: USCG COI annual and UWILD

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:13 May 2017
Dep:13 May 2017
Arr:17 May 2017
Unload:17 May 2017
 
Seattle, WA, USA
Seattle, WA, USA
 
Seattle/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Murray Stein
Maintenance
  5/5

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:18 May 2017
Dep:18 May 2017
Arr:25 May 2017
Unload:25 May 2017
 
Seattle, WA, USA
Dutch Harbor, AK, USA
 
NP9-NP5/
NP09
NP05
 
 
 
48N/122W
54N/166W
 
  Hongsheng Bi
Transit Cruise
  8/8

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 8/NSF-OCE-IPS/F
Bering Sea Jellyfish Hongsheng Bi/UMD_CES 1602488 0/NSF-OPP-ARC/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:26 May 2017
Dep:27 May 2017
Arr:02 Jun 2017
Unload:03 Jun 2017
 
Dutch Harbor, AK, USA
Dutch Harbor, AK, USA
 
NP5/
NP05
NP05
 
 
 
57N/160W
57N/167W
 
  Hongsheng Bi
  7/9

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Bering Sea Jellyfish Hongsheng Bi/UMD_CES 1602488 9/NSF-OPP-ARC/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:04 Jun 2017
Dep:04 Jun 2017
Arr:07 Jun 2017
Unload:07 Jun 2017
 
Dutch Harbor, AK, USA
Nome, AK, USA
 
NP5/
NP05
NP02
 
 
 
54N/166W
64N/165W
 
  Seth Danielson
Transit Cruise
  4/4

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
ASGARD Seth Danielson/UAF_CFOS Not Specified 4/OTHER/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:08 Jun 2017
Dep:09 Jun 2017
Arr:28 Jun 2017
Unload:29 Jun 2017
 
Nome, AK, USA
Nome, AK, USA
 
NP2/
NP02
NP02
 
 
 
64N/165W
64N/165W
 
  Seth Danielson
  20/22

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
ASGARD Seth Danielson/UAF_CFOS Not Specified 11/OTHER/F
Not Specified 9/INST-UAF/F
Bering Sea Diatoms Jeffrey W. Krause/MESC 1603605 2/NSF-OPP-ARC/F
 
Notes: Reduced science days to 20 to cover transit costs

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:30 Jun 2017
Dep:30 Jun 2017
Arr:05 Jul 2017
Unload:05 Jul 2017
 
Nome, AK, USA
Seward, AK, USA
 
NP5/
NP02
NP05
 
 
 
64N/165W
54N/166W
 
  Murray Stein
Transit Cruise
  6/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 6/NSF-OCE-IPS/F
 
Notes: Transit to homeport

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:06 Jul 2017
Dep:06 Jul 2017
Arr:29 Jul 2017
Unload:29 Jul 2017
 
Seward, AK, USA
Seward, AK, USA
 
NP2/
NP05
NP05
 
 
 
54N/166W
54N/166W
 
  Doug Baird
Standby Days
  24/24

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: Ship was available for service - but previously assigned project was worked on another vessel; used the time for general upkeep, crew rest and crew training (Polar Code required Polar Operations, both basic and advanced)

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:30 Jul 2017
Dep:30 Jul 2017
Arr:05 Aug 2017
Unload:05 Aug 2017
 
Seward, AK, USA
Nome, AK, USA
 
NP5/
NP05
NP02
 
 
 
54N/166W
64N/166W
 
  Laurie Juranek
Transit Cruise
  7/7

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Shelf Break Ecology Carin J. Ashjian/WHOI 1603941 4/NSF-OPP-ARC/F
Arctic Productivity Laurie Juranek/OS 1504394 3/NSF-OPP-ARC/F
 
Notes: Transit to Nome for cruises; Transit Policy: Juranek 40% (2.8 days), Ashjian 60% (4.2 days)

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:06 Aug 2017
Dep:06 Aug 2017
Arr:22 Aug 2017
Unload:23 Aug 2017
 
Nome, AK, USA
Nome, AK, USA
 
NP2 - AR7/
NP02
AR07
 
 
 
60N/170W
72N/158W
 
  Laurie Juranek
  17/18

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Arctic Productivity Laurie Juranek/OS 1504394 18/NSF-OPP-ARC/F
Arctic N fixation Rachel E. Sipler/VIMS 1504307 0/NSF-OPP-ARC/F
 
Notes: To finish 2016 inshore stations.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:24 Aug 2017
Dep:25 Aug 2017
Arr:18 Sep 2017
Unload:19 Sep 2017
 
Nome, AK, USA
Nome, AK, USA
 
AR7/
AR07
AR07
 
 
 
71N/152W
72N/147W
 
  Carin J. Ashjian
  25/27

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Shelf Break Ecology Carin J. Ashjian/WHOI 1603941 27/NSF-OPP-ARC/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:20 Sep 2017
Dep:20 Sep 2017
Arr:29 Sep 2017
Unload:29 Sep 2017
 
Nome, AK, USA
Newport, OR, USA
 
NP6/
NP05
NP03
 
 
 
54N/166W
60N/149W
 
  Edward P. Dever
Transit Cruise
  10/10

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Transit Edward P. Dever/OSU-CEOAS Not Specified 10/NSF-OOI-OOI/F
Endurance Array OM Edward P. Dever/OSU-CEOAS Not Specified 0/NSF-OOI-OOI/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:30 Sep 2017
Dep:02 Oct 2017
Arr:17 Oct 2017
Unload:18 Oct 2017
 
Newport, OR, USA
Newport, OR, USA
 
NP9/
NP09
NP09
 
 
 
44N/124W
44N/124W
 
  Edward P. Dever
  16/19

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Endurance Array OM Edward P. Dever/OSU-CEOAS Not Specified 19/NSF-OOI-OOI/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:19 Oct 2017
Dep:19 Oct 2017
Arr:23 Oct 2017
Unload:23 Oct 2017
 
Newport, OR, USA
San Diego, CA, USA
 
NP9/
NP09
NP09
 
 
 
45N/124W
33N/117W
 
  Jesse I. Angle
Transit Cruise
  5/5

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
ALMOND-U Jesse I. Angle/NSWC_PCD DWAM51678 5/NAVY-ONR/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:24 Oct 2017
Dep:25 Oct 2017
Arr:07 Nov 2017
Unload:08 Nov 2017
 
San Diego, CA, USA
San Diego, CA, USA
 
Southern CA UXO/
NP09
NP09
 
 
 
33N/117W
33N/117W
 
  Jesse I. Angle
  14/16

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
ALMOND-U Jesse I. Angle/NSWC_PCD DWAM51678 16/NAVY-ONR/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:09 Nov 2017
Dep:09 Nov 2017
Arr:28 Nov 2017
Unload:28 Nov 2017
 
San Diego, CA, USA
San Diego, CA, USA
 
NP9/
NP09
NP09
 
 
 
33N/117W
33N/117W
 
  Doug Baird
Standby Days
  20/20

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: Ship was available for service, but no projects assigned - so, general upkeep and crew rest while prepping for scheduled maintenance in December.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:29 Nov 2017
Dep:29 Nov 2017
Arr:31 Dec 2017
Unload:31 Dec 2017
 
San Diego, CA, USA
San Diego, CA, USA
 
San Diego, CA/
NP09
NP09
 
 
 
33N/117W
33N/117W
 
  Doug Baird
Maintenance
  33/33

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: Maintenance performed while alongside TAMT at Port of San Diego
Agency   Funded   Pending   Total
INST   9   0   9
NAVY   21   0   21
NSF   178   0   178
NSF-OOI   48   0   48
OTHER   15   0   15
Total  271 0 271
<
Day Type   Total
Transit Cruise   51
Inspection   4
Standby Days   44
Maintenance   46
At Sea for Science   194
Total  339
<
Load/Unload Days   Total
ChargeLoad   14
ChargeUnload   12
Total  26