  2020 - Rachel Carson  
2020 - February update
Secure - ID #14052    Version #3 - 2/20/2020

Scheduling Contact(s)
Robert Kamphaus kamphaus*%*%*uw^%^%^edu (206) 685-5672

  Notes:   3/12/2019 - First draft for scheduling call
7/1/2019 - added dates for FISH312 (Wood)
8/16/2019 - Adjusted dates for OA in April.
8/28/2019 - removed Student Thesis (443); on TGT. Updated funding status. Linked Puget Plumes to funding request.
8/29/2019 - updated academic days pending/funded.
10/10/2019 - deleted declined project.
10/11/2019 - Puget Bubbles first cruise moved to 2019
10/29/2019 - updated funding for OSU; schedule published
12/1/2019 - added Keister Sea Grant jellyfish cruise for south sound
12/14/2019 - reduced OCN 201 to 2 days u/w; de-conflicted. Added cruise numbers for first few cruises. Updated funding status of UW days.
12/28/2019 - Ocean 517 is alternate years; removed from 2020 schedule.
1/6/2020 - Fram postponed due to glider availability and weather.
1/13/2020 - Fram delayed again due to weather; updated OA dates.
1/23/2020 - Fram delayed again due to weather and crew availability.
1/29/2020 - Fram further delayed due to weather.
2/3/2020 - Updated OCN 220 PI to Morris and moved to to 16-21 April 2020.
2/4/2020 - Fram further delayed due to weather and Ocean Sciences
2/20/2020 - Added Roland Mapping Cruise and Cheryl Greengrove (UW-T), moved Fram. Johnson dates TBD in Spring 2020.
  View Summary     Set Default Associated Cruises
Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Jan 2020
Dep:01 Jan 2020
Arr:05 Jan 2020
Unload:05 Jan 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
General Upkeep and Outfitting
  5/5

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:06 Jan 2020
Dep:06 Jan 2020
Arr:25 Feb 2020
Unload:25 Feb 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
Available for Service
  51/51

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:26 Feb 2020
Dep:27 Feb 2020
Arr:29 Feb 2020
Unload:01 Mar 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Puget Sound/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Emily Roland
  3/5

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
UW Surveying Class Richard G. Keil/UW Not Specified 3/INST-UW/F
 
Notes: Moved to Winter Quarter 2020

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:02 Mar 2020
Dep:02 Mar 2020
Arr:02 Mar 2020
Unload:02 Mar 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
General Upkeep and Outfitting
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:03 Mar 2020
Dep:03 Mar 2020
Arr:06 Mar 2020
Unload:06 Mar 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
WA Coast/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Jonathan P. Fram
  4/4

Clearances: US EEZ(A)
 
Project PI/Institution Project # Days/Agency/Status
OSU PO - profiler Jonathan P. Fram/OSU-CEOAS Not Specified 4/OTHER/F
 
Notes: RC-0039. Glider and profiler work off Gray's Harbor.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:07 Mar 2020
Dep:07 Mar 2020
Arr:30 Mar 2020
Unload:30 Mar 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
Available for Service
  24/24

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:31 Mar 2020
Dep:01 Apr 2020
Arr:05 Apr 2020
Unload:05 Apr 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Puget Sound/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Jan Newton
  5/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Ocean Acidification Jan Newton/UW_APL Not Specified 5/OTHER/P
 
Notes: Dates requested in e-mail from Jan and Beth on 8/16/19; dates updated per 1/8/20 e-mail.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:06 Apr 2020
Dep:06 Apr 2020
Arr:14 Apr 2020
Unload:14 Apr 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
Available for Service
  9/9

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:15 Apr 2020
Dep:16 Apr 2020
Arr:19 Apr 2020
Unload:20 Apr 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Puget Sound/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Morris
  4/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Ocean 220 Cruise Richard G. Keil/UW Not Specified 4/INST-UW/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:21 Apr 2020
Dep:21 Apr 2020
Arr:23 Apr 2020
Unload:23 Apr 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
General Upkeep and Outfitting
  3/3

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:24 Apr 2020
Dep:24 Apr 2020
Arr:25 Apr 2020
Unload:26 Apr 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Lake Washington/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Chelsea Wood
  2/3

Clearances: US EEZ(T)
 
Project PI/Institution Project # Days/Agency/Status
FISH 312 Richard G. Keil/UW Not Specified 2/INST-UW/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:27 Apr 2020
Dep:27 Apr 2020
Arr:06 May 2020
Unload:06 May 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
Available for Service
  10/10

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:07 May 2020
Dep:08 May 2020
Arr:09 May 2020
Unload:10 May 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Puget Sound/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Cheryl Greengrove
  2/4

Clearances: US EEZ(A)
 
Project PI/Institution Project # Days/Agency/Status
UWT TGEOS 445 Richard G. Keil/UW Not Specified 2/INST-UW/F
 
Notes: UWT TGEOS 445 Estuarine Field Studies

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:11 May 2020
Dep:11 May 2020
Arr:11 May 2020
Unload:11 May 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
General Upkeep and Outfitting
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:12 May 2020
Dep:13 May 2020
Arr:14 May 2020
Unload:14 May 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Puget Sound/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Jodi Young
  2/3

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Ocean 201 Cruises Richard G. Keil/UW Not Specified 2/INST-UW/F
 
Notes: Dates based on similar dates for Ocean 201 in prior years.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:15 May 2020
Dep:15 May 2020
Arr:16 May 2020
Unload:17 May 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Puget Sound/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Chelsea Wood
  2/3

Clearances: US EEZ(T)
 
Project PI/Institution Project # Days/Agency/Status
FISH 312 Richard G. Keil/UW Not Specified 2/INST-UW/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:18 May 2020
Dep:18 May 2020
Arr:06 Jul 2020
Unload:06 Jul 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Seattle/
NP09
NP09
 
 
 
43N/122W
43N/122W
 
  Robert Kamphaus
Available for Service
  50/50

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:07 Jul 2020
Dep:08 Jul 2020
Arr:12 Jul 2020
Unload:12 Jul 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Puget Sound/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Jan Newton
  5/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Ocean Acidification Richard G. Keil/UW Not Specified 5/INST-UW/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:13 Jul 2020
Dep:13 Jul 2020
Arr:14 Jul 2020
Unload:14 Jul 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
General Upkeep and Outfitting
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:15 Jul 2020
Dep:15 Jul 2020
Arr:27 Jul 2020
Unload:27 Jul 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
Available for Service
  13/13

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:28 Jul 2020
Dep:28 Jul 2020
Arr:29 Jul 2020
Unload:29 Jul 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
Inspection
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
NSF Inspection Robert Kamphaus/UW Not Specified 0/INST-UW/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:30 Jul 2020
Dep:30 Jul 2020
Arr:23 Aug 2020
Unload:23 Aug 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
Available for Service
  25/25

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:24 Aug 2020
Dep:25 Aug 2020
Arr:28 Aug 2020
Unload:28 Aug 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Puget Sound/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Julie E. Keister
  4/5

Clearances: US EEZ(T)
 
Project PI/Institution Project # Days/Agency/Status
Jellyfish-WSG Match Richard G. Keil/UW Not Specified 4/INST-UW/F
 
Notes: Estimated dates based on e-mail from Keister. Preference late Aug or early Sept when jellyfish abundance is highest. South Sound.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:29 Aug 2020
Dep:29 Aug 2020
Arr:30 Aug 2020
Unload:30 Aug 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
General Upkeep and Outfitting
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:31 Aug 2020
Dep:01 Sep 2020
Arr:05 Sep 2020
Unload:05 Sep 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Puget Sound/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Monica Orellana
  5/6

Clearances: US EEZ(T)
 
Project PI/Institution Project # Days/Agency/Status
Diatoms and OA Monica Orellana/ISB 1947620 5/NSF-OCE-BIO/P

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:06 Sep 2020
Dep:06 Sep 2020
Arr:12 Sep 2020
Unload:12 Sep 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
Available for Service
  7/7

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:13 Sep 2020
Dep:14 Sep 2020
Arr:18 Sep 2020
Unload:18 Sep 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Puget Sound/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Jan Newton
  5/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Ocean Acidification Richard G. Keil/UW Not Specified 5/OTHER/P
 
Notes: Estimated dates based on previous similar cruises.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:19 Sep 2020
Dep:19 Sep 2020
Arr:08 Oct 2020
Unload:08 Oct 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
Available for Service
  20/20

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:09 Oct 2020
Dep:10 Oct 2020
Arr:12 Oct 2020
Unload:13 Oct 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Elwha River/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Andrea S. Ogston
  3/5

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Elwha River Richard G. Keil/UW Not Specified 3/INST-UW/F
 
Notes: Estimated dates based on similar previous cruises - every other year in even years.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:14 Oct 2020
Dep:14 Oct 2020
Arr:14 Oct 2020
Unload:14 Oct 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
General Upkeep and Outfitting
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:15 Oct 2020
Dep:16 Oct 2020
Arr:16 Oct 2020
Unload:16 Oct 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Lake Washington/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  John Horne
  1/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Fish Acoustics Class John Horne/UW Not Specified 1/INST-UW/F
 
Notes: Estimated date based on similar previous cruises.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:17 Oct 2020
Dep:17 Oct 2020
Arr:20 Oct 2020
Unload:20 Oct 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
General Upkeep and Outfitting
  4/4

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:21 Oct 2020
Dep:22 Oct 2020
Arr:22 Oct 2020
Unload:22 Oct 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
Puget Sound/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Charles Nittrouer
  1/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
OCN 230 Class Richard G. Keil/UW Not Specified 1/INST-UW/F
 
Notes: Estimated dates based on similar previous cruises

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:23 Oct 2020
Dep:23 Oct 2020
Arr:28 Oct 2020
Unload:28 Oct 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
General Upkeep and Outfitting
  6/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:16 Nov 2020
Dep:16 Nov 2020
Arr:31 Dec 2020
Unload:31 Dec 2020
 
Seattle, WA, USA
Seattle, WA, USA
 
UW/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Robert Kamphaus
Available for Service
  46/46

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:TBD
Dep:TBD
Arr:TBD
Unload:TBD
 
Seattle, WA, USA
Seattle, WA, USA
 
Puget Sound/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Richard G. Keil
  13/13

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
UW Academic Not Specified 11/INST-UW/P
 
Notes: ~40 Days available from conversion of UW funded Thompson days to Carson days per concurrence from ONR. Days to be applied towards 2020 UW research and academic cruises

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:TBD
Dep:TBD
Arr:TBD
Unload:TBD
 
Seattle, WA, USA
Seattle, WA, USA
 
Puget Sound/
NP09
NP09
 
 
 
48N/122W
48N/122W
 
  Harlan P. Johnson
  2/4

Clearances: US EEZ(T)

Ancil Facs: Other ROV
 
Project PI/Institution Project # Days/Agency/Status
Puget Bubbles Harlan P. Johnson/UW 1945975 2/NSF-OCE-MGG/F
Puget Bubbles Harlan P. Johnson/UW Not Specified 0/NSF-OCE-EAGER/F
 
Notes: RC-0040. To allow for sampling of gas emission sites, we are requesting two 2-day cruises, with the first in January 2020 [first scheduled in December], and the second 2-day cruise in March 2020. 2/20/2020 - dates moved to 'TBD' for Spring 2020, postponed the 16-18 March 2020 cruise.
Agency   Funded   Pending   Total
INST   29   11   40
NSF   2   5   7
OTHER   4   10   14
Total  35 26 61
<
Day Type   Total
Available for Service   255
General Upkeep and Outfitting   25
Inspection   2
At Sea for Science   63
Total  345
<
Load/Unload Days   Total
ChargeLoad   1
ChargeUnload   1
NonChargeLoad   12
NonChargeUnload   6
Total  20