  2021 - Atlantic Explorer  
2021 Schedule (REV 28 12/09/21-FINAL)
Final - ID #14374    Version #11 - 1/11/2022

Scheduling Contact(s)
Quentin M. Lewis marine^%^%^superintendent*%*%*bios^%^%^edu (646) 547-1788x208

  Notes:   2021 US Academic Research Fleet vessel schedules are subject to change as the COVID-19 pandemic evolves. Scheduled cruise Chief Scientists are urged to keep in close contact with the vessel operators to remain aware of any updates/changes.
12/07/21 - ADJUSTED FALL SCHEDULE FOR COVID AND WEATHER
10/15/21 - Added in 2 days of out-of-service time, to remove damaged 0.322" cable from CTD winch on December 2, replace with borrowed spool from East Coast winch/wire pool on December 3, between scheduled cruises.
9/22/21 - Ship stand-down due to Covid-19 spike in Bermuda, for 9/23 - 9/29. All cruises beyond September 29 to end of year delayed and shifted again, but all accommodated within schedule. Ship remained healthy and no Covid-19 cases on board.
9/9/21 - Added Todd 3-day Recovery cruise for WHOI (September 19 - 21)
9/7/21 - September 7 - 9: stand by in port for Hurricane LARRY, all cruises from September 9 - December 18 shifted to accommodate delay
8/17/21 - Stand by in port for Hurricane HENRI
07/20/21 - Completed mobilization for Beaupre in 3 days instead of 4, added 1 day to science portion
07/30/21 - Shifted 1 BATS day from August BATS cruise to December BATS cruise. Separated August, November, and December Hydro days to separate 1-day cruises
04/01/21 - Added 1 BATS day to April BATS Bloom cruise, removed 1 day from September BATS cruise
03/01/21 - 1 day of Neuer moved to 2022
02/01/21 - Gentile USAF cruise unable to allocate funds in time for missile launch
12/07/20 - January BATS cruise shifted 2 days later, to accommodate new travel restrictions and quarantine requirements in Bermuda. Neuer actually has 3 funded science days, not just 1
11/26/20 - Subhas declined, March Bloom cruise moved back to original requested date
11/26/20 - Tully Declined. Beaupre added, funded. Gentile USAF 11-day cruise added, pending. BATS days redistributed to add in 2 spring Bloom cruises. HYDRO days redistributed to add one day to each Bloom cruise, and to provide 3 separate 1-day cruises
10/22/20 - Angela Knapp cruises declined. Will add 16 days for Steven Beaupre cruise, July 2021, which shows as funded.
Currently have 6 days pending for Benjamin Tully and 3 days for Adam Subhas
10/1/20 - Added two cruises for Angela Knapp. Not yet scheduled, as cruises pending
  View Summary     Set Default Associated Cruises
Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Jan 2021
Dep:01 Jan 2021
Arr:21 Jan 2021
Unload:21 Jan 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA6/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  21/21

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:22 Jan 2021
Dep:23 Jan 2021
Arr:26 Jan 2021
Unload:27 Jan 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  4/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 5/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 1/NSF-OCE-PO/F
 
Notes: AE 2101 - BATS/HYDRO Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:28 Jan 2021
Dep:28 Jan 2021
Arr:31 Jan 2021
Unload:31 Jan 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  4/4

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting - BATS/HYDRO cruise AE 2101 cut short 2 days due to Gale conditions. 1 Grundle day and 1 BATS day re-scheduled for cruises later in 2021.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Feb 2021
Dep:01 Feb 2021
Arr:05 Feb 2021
Unload:05 Feb 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
Out of Service
  5/5

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: Out of Service - ABS Annual Surveys - Dockside in Bermuda

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:06 Feb 2021
Dep:06 Feb 2021
Arr:09 Feb 2021
Unload:09 Feb 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  4/4

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:10 Feb 2021
Dep:11 Feb 2021
Arr:17 Feb 2021
Unload:18 Feb 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  7/9

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 7/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 2/NSF-OCE-PO/F
 
Notes: AE 2102 - BATS/HYDRO Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:19 Feb 2021
Dep:19 Feb 2021
Arr:12 Mar 2021
Unload:12 Mar 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA6/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
Available for Service
  22/22

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: AVAILABLE FOR SERVICE

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:13 Mar 2021
Dep:14 Mar 2021
Arr:20 Mar 2021
Unload:21 Mar 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  7/9

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 7/NSF-OCE-CO/F
NCP-Glider Damian Grundle/BIOS 1851224 1/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 1/NSF-OCE-PO/F
 
Notes: AE 2103 - BATS/HYDRO/GRUNDLE Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:22 Mar 2021
Dep:22 Mar 2021
Arr:23 Mar 2021
Unload:23 Mar 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA6/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:24 Mar 2021
Dep:24 Mar 2021
Arr:26 Mar 2021
Unload:27 Mar 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  3/4

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 2/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 2/NSF-OCE-PO/F
 
Notes: AE 2104 - BATS Bloom/HYDRO Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:28 Mar 2021
Dep:28 Mar 2021
Arr:03 Apr 2021
Unload:03 Apr 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA6/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  7/7

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:04 Apr 2021
Dep:05 Apr 2021
Arr:10 Apr 2021
Unload:11 Apr 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  6/8

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 5/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 2/NSF-OCE-PO/F
NCP-Glider Damian Grundle/BIOS 1851224 1/NSF-OCE-CO/F
 
Notes: AE 2105 - BATS/HYDRO/GRUNDLE Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:12 Apr 2021
Dep:14 Apr 2021
Arr:21 Apr 2021
Unload:22 Apr 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Maureen H. Conte
  8/11

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Oceanic Flux Program Maureen H. Conte/BIOS 1829885 11/NSF-OCE-CO/F
 
Notes: AE 2106 - CONTE OFP Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:23 Apr 2021
Dep:23 Apr 2021
Arr:26 Apr 2021
Unload:26 Apr 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  4/4

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:27 Apr 2021
Dep:28 Apr 2021
Arr:01 May 2021
Unload:01 May 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  4/5

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 3/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 2/NSF-OCE-PO/F
 
Notes: AE 2107 - BATS Bloom/HYDRO Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:02 May 2021
Dep:02 May 2021
Arr:05 May 2021
Unload:05 May 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  4/4

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:06 May 2021
Dep:06 May 2021
Arr:07 May 2021
Unload:07 May 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
Transit Cruise
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: AE 2108 - Transit cruise to test CTD winch level-wind repairs

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:08 May 2021
Dep:08 May 2021
Arr:09 May 2021
Unload:09 May 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:10 May 2021
Dep:11 May 2021
Arr:18 May 2021
Unload:19 May 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  8/10

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 5/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 4/NSF-OCE-PO/F
NCP-Glider Damian Grundle/BIOS 1851224 1/NSF-OCE-CO/F
 
Notes: AE 2109- BATS/HYDRO/GRUNDLE Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:20 May 2021
Dep:20 May 2021
Arr:12 Jun 2021
Unload:12 Jun 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA6/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
Available for Service
  24/24

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: AVAILABLE FOR SERVICE

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:13 Jun 2021
Dep:14 Jun 2021
Arr:21 Jun 2021
Unload:22 Jun 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  8/10

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 8/NSF-OCE-CO/F
NCP-Glider Damian Grundle/BIOS 1851224 1/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 1/NSF-OCE-PO/F
 
Notes: AE 2110- BATS/HYDRO/GRUNDLE Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:23 Jun 2021
Dep:23 Jun 2021
Arr:23 Jun 2021
Unload:23 Jun 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:24 Jun 2021
Dep:24 Jun 2021
Arr:24 Jun 2021
Unload:24 Jun 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Hydrostation S Nicholas R. Bates/BIOS 1633125 1/NSF-OCE-PO/F
 
Notes: AE 2111 - HYDRO Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:25 Jun 2021
Dep:25 Jun 2021
Arr:06 Jul 2021
Unload:06 Jul 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA6/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
Available for Service
  12/12

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: AVAILABLE FOR SERVICE

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:07 Jul 2021
Dep:08 Jul 2021
Arr:16 Jul 2021
Unload:17 Jul 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  9/11

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 7/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 2/NSF-OCE-PO/F
Zoopl Mediation Susanne Neuer/ASU 2023621 1/NSF-OCE-BIO/F
NCP-Glider Damian Grundle/BIOS 1851224 1/NSF-OCE-CO/F
 
Notes: AE 2112- BATS/HYDRO/GRUNDLE/NEUER Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:18 Jul 2021
Dep:18 Jul 2021
Arr:18 Jul 2021
Unload:18 Jul 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:19 Jul 2021
Dep:22 Jul 2021
Arr:01 Aug 2021
Unload:03 Aug 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA6/
NA06
NA06
 
 
 
32N/80W
32N/80W
 
  Steven R. Beaupre
  11/16

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
PMA2020 - Revised Steven R. Beaupre/SUNYSB 2023115 16/NSF-OCE-CO/F
 
Notes: AE 2113 - BEAUPRE Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:04 Aug 2021
Dep:05 Aug 2021
Arr:08 Aug 2021
Unload:09 Aug 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA6/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Craig A. Carlson
  4/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
SCOPE Craig A. Carlson/UCSB Not Specified 6/INST-BIOS/F
 
Notes: AE 2114 BIOS-SCOPE Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:10 Aug 2021
Dep:10 Aug 2021
Arr:10 Aug 2021
Unload:10 Aug 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:11 Aug 2021
Dep:11 Aug 2021
Arr:11 Aug 2021
Unload:11 Aug 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Hydrostation S Nicholas R. Bates/BIOS 1633125 1/NSF-OCE-PO/F
 
Notes: AE 2115 - HYDRO Cruise (1-DAY)

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:12 Aug 2021
Dep:12 Aug 2021
Arr:13 Aug 2021
Unload:13 Aug 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:14 Aug 2021
Dep:15 Aug 2021
Arr:16 Aug 2021
Unload:16 Aug 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  2/3

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 2/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 1/NSF-OCE-PO/F
 
Notes: AE 2116- BATS/HYDRO/GRUNDLE Cruise - LEG 1, Returned to port due to Hurricane Henri passing close to Bermuda

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:17 Aug 2021
Dep:17 Aug 2021
Arr:17 Aug 2021
Unload:17 Aug 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
Standby Days
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: Standby day for Hurricane Henri to pass

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:18 Aug 2021
Dep:18 Aug 2021
Arr:21 Aug 2021
Unload:22 Aug 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  4/5

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 3/NSF-OCE-CO/F
NCP-Glider Damian Grundle/BIOS 1851224 1/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 1/NSF-OCE-PO/F
 
Notes: AE 2116- BATS/HYDRO/GRUNDLE Cruise LEG 2, Return to sea after Hurricane Henri

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:23 Aug 2021
Dep:23 Aug 2021
Arr:06 Sep 2021
Unload:06 Sep 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA6/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
Available for Service
  15/15

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: AVAILABLE FOR SERVICE

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:07 Sep 2021
Dep:07 Sep 2021
Arr:09 Sep 2021
Unload:09 Sep 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
Standby Days
  3/3

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: Standby days in port in Bermuda for Hurricane Larry to pass

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:10 Sep 2021
Dep:11 Sep 2021
Arr:16 Sep 2021
Unload:17 Sep 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  6/8

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 4/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 3/NSF-OCE-PO/F
NCP-Glider Damian Grundle/BIOS 1851224 1/NSF-OCE-CO/F
 
Notes: AE 2117 - BATS/HYDRO/GRUNDLE Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:18 Sep 2021
Dep:18 Sep 2021
Arr:18 Sep 2021
Unload:18 Sep 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:19 Sep 2021
Dep:19 Sep 2021
Arr:21 Sep 2021
Unload:21 Sep 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA6/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Robert E. Todd
  3/3

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Todd Glider Recovery Robert E. Todd/WHOI Not Specified 3/INST-WHOI/F
 
Notes: AE 2118 WHOI/Todd Glider Recovery Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:22 Sep 2021
Dep:22 Sep 2021
Arr:22 Sep 2021
Unload:22 Sep 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:23 Sep 2021
Dep:23 Sep 2021
Arr:28 Sep 2021
Unload:28 Sep 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
Standby Days
  6/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: Stand-by days - RVAE in port during Covid-19 spike in Bermuda cases

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:29 Sep 2021
Dep:29 Sep 2021
Arr:29 Sep 2021
Unload:29 Sep 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Hydrostation S Nicholas R. Bates/BIOS 1633125 1/NSF-OCE-PO/F
 
Notes: AE 2119 - HYDRO CRUISE (1-DAY)

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:30 Sep 2021
Dep:30 Sep 2021
Arr:02 Oct 2021
Unload:02 Oct 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
Standby Days
  3/3

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: Stand-by days - RVAE in port due to passing gale

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:03 Oct 2021
Dep:04 Oct 2021
Arr:09 Oct 2021
Unload:09 Oct 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  6/7

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 5/NSF-OCE-CO/F
NCP-Glider Damian Grundle/BIOS 1851224 1/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 1/NSF-OCE-PO/F
 
Notes: AE 2120- BATS/HYDRO/GRUNDLE Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:10 Oct 2021
Dep:11 Oct 2021
Arr:25 Oct 2021
Unload:25 Oct 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  15/16

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 12/NSF-OCE-CO/F
oxygen project Adam Martiny/UCI 1948842 3/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 1/NSF-OCE-PO/F
 
Notes: AE 2121 - BATS VALIDATION/MARTINY CRUISE (SOUTH) (NOTE: Port call in San Juan October 20, with PCR tests administered to all crew and science party for return to BDA. Cruise was a 2-leg cruise, BDA to BDA, Ship quarantined for 1 day in BDA on return, October 26, pending results of arrival PCR tests - all negative. Vessel de-mobilized on October 27.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:26 Oct 2021
Dep:26 Oct 2021
Arr:26 Oct 2021
Unload:26 Oct 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
Out of Service
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: QUARANTINE DAY - Following BATS VALIDATION Cruise (SOUTH)

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:27 Oct 2021
Dep:27 Oct 2021
Arr:27 Oct 2021
Unload:27 Oct 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  0/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 1/NSF-OCE-CO/F
 
Notes: AE 2121 - BATS VALIDATION CRUISE (SOUTH) BATS charged De-mob day following 1-day quarantine period in Bermuda

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:28 Oct 2021
Dep:30 Oct 2021
Arr:06 Nov 2021
Unload:07 Nov 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Maureen H. Conte
  8/11

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Oceanic Flux Program Maureen H. Conte/BIOS 1829885 11/NSF-OCE-CO/F
 
Notes: AE 2122 - CONTE OFP Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:08 Nov 2021
Dep:08 Nov 2021
Arr:08 Nov 2021
Unload:08 Nov 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
Standby Days
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: Standby day - weather

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:09 Nov 2021
Dep:10 Nov 2021
Arr:13 Nov 2021
Unload:14 Nov 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA6/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Craig A. Carlson
  4/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
SCOPE Craig A. Carlson/UCSB Not Specified 6/INST-BIOS/F
 
Notes: AE 2123 BIOS-SCOPE Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:15 Nov 2021
Dep:16 Nov 2021
Arr:23 Nov 2021
Unload:24 Nov 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  8/10

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 5/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 3/NSF-OCE-PO/F
Zoopl Mediation Susanne Neuer/ASU 2023621 1/NSF-OCE-BIO/F
NCP-Glider Damian Grundle/BIOS 1851224 1/NSF-OCE-CO/F
 
Notes: AE 2124- BATS/HYDRO/GRUNDLE/NEUER Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:25 Nov 2021
Dep:25 Nov 2021
Arr:01 Dec 2021
Unload:01 Dec 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA6/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  7/7

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:02 Dec 2021
Dep:02 Dec 2021
Arr:03 Dec 2021
Unload:03 Dec 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
Out of Service
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: OUT OF SERVICE - Swap out CTD wire

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:04 Dec 2021
Dep:04 Dec 2021
Arr:05 Dec 2021
Unload:05 Dec 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Hydrostation S Nicholas R. Bates/BIOS 1633125 2/NSF-OCE-PO/F
 
Notes: AE 2125 - HYDRO Cruise (2-DAYS)

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:06 Dec 2021
Dep:06 Dec 2021
Arr:06 Dec 2021
Unload:06 Dec 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA6/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:07 Dec 2021
Dep:08 Dec 2021
Arr:16 Dec 2021
Unload:17 Dec 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
NA06/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Rod Johnson
  9/11

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
BATS Nicholas R. Bates/BIOS 1756105 10/NSF-OCE-CO/F
Hydrostation S Nicholas R. Bates/BIOS 1633125 1/NSF-OCE-PO/F
 
Notes: AE 2126 - BATS/HYDRO Cruise

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:18 Dec 2021
Dep:18 Dec 2021
Arr:31 Dec 2021
Unload:31 Dec 2021
 
St. George's, Bermuda
St. George's, Bermuda
 
Bermuda/
NA06
NA06
 
 
 
32N/64W
32N/64W
 
  Quentin M. Lewis
General Upkeep and Outfitting
  14/14

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
 
Notes: General Upkeep and Outfitting - END OF YEAR
Agency   Funded   Pending   Total
INST   15   0   15
NSF   176   0   176
Total  191 0 191
<
Day Type   Total
Available for Service   73
Transit Cruise   2
General Upkeep and Outfitting   77
Standby Days   14
At Sea for Science   149
Out of Service   8
Total  323
<
Load/Unload Days   Total
ChargeLoad   23
ChargeUnload   19
Total  42