View Cruise

  Schedule Information  
Ship: Atlantis Schedule Status: Final Schedule ID: 14061
Schedule Year: 2019 Schedule Name: Version 12
Notes: 12/15: Vessel arrives Manz.,MX 2 days early Dec 12th (was the 14th)
12/5: Changed 10 OOI days to OCE days as per 12/4 email. There is not a Kelley STR for OCE funding. Added this account manually.
12/4: Removed Marum STR to reflect billing to UW, not "Other" which is what the STR comes up as.
11/15/2019: Scheduler error, Put 4N instead of 4S...3 days additional transit, -1 day from 2019 GoFar ops, transferring it to 2020 ops on Revelle, -2 days from Manzanillo mobe, keeping the next cruise on schedule
9/30/2019: Atlantis pitstop (9/25-26) on Pythias Oasis cruise into Newport d/t wx & family emergency
7/17: Added 2 days to 9n for Fornari
7/8: Add 1 day to Boettcher cruise & 1 more demobe day d/t MX
6/10: Kelley's 1st leg, delayed arrival by 1 day (6/10), d/t wx. Delayed departure as well (now the 13th)
5/2: Sylvan arrives 1 day early. Was 4/24th now 23rd (recent hull cleaning)
3/22: OOI Legs added
3/6: Drazen after Sylvan d/t Atlantis maintenance issue
ONR eng dive added to Sylvan from Drazen
Shift Ohman cruise onto Sikuliaq to keep Drazen/ Alvin cruise
2/16: -1 day/ ONR from Alvin Eng Dive on Hansel
2/11: Changed DD dock from SFO to Vallejo
1/19/2019: Added 19d Valentine (2020) work in SD, B4 transiting Panama
1/9/2019: Removed Hueber's 7 days from Lang (not funded)
12/12: Add 2 Alvin Eng Dives onto Sylvan
& add 1 day to Ohman's 1st cruise for NOAA
10/12: Add 7 days to Lang (Huber & Rogers)
10/1: Add Drazen Alvin Cruise...Remove Resing (Sally Ride)...Add 2 days on Kelley's Pythias for Rob Harris.
9/28: Ref Email from UW: Take 10 charge days from Kelley's OOI & bill it to IPS
AND Corrected transit to Orcutt cruise from MGG to OOI d/t schedule changes
9/7: Ohman: 2 days of NOAA funding may be added to Spring cruise. TBC?
8/30: squeeze Hansel inbetween newport>SD transit.
8/21: change Jason eng dive from Kelley to Abers/ Sikuliaq and take 1 mobe day off Kelley OOI
8/3: Hansel can NOT go before Sept d/t an August cruise elsewhere & her instruments will not be ready until Sept. They are flexible in location and can go from Sept-Dec, no prob.
8/2: Lang in 2020, Hansel before Resing then Boettcher (using Manta, Equador)
7/17: This schedule delays the vessel from DD to start USWC Jason work later to give Jason a week to get from Charleston to Newport (provided Adams/ Brown goes in April)
6/27: "W" -3 days Rappe off Orcutt
6/25: Confirmed Resing can not work at EPR in OCT d/t wx
6/12: Add SSSG STR for Multibeam calibrations 2 days on a seamount/ deepwater
5/18: Orcutt:"The CORKs that are the primary target for my Jason cruise are at 2.6km water depth. We could do either Jason deployment mode - single body or double body. If my cruise is bracketed by OOI work, I imagine that single body might be the mode of choice to limit configuration changes? If single body, we would want to have the science tool sled instead of the heavy lift sled, since we will not have any heavy lift needs on my cruise."
5/14: Ohman needs mid June/ July for filament "spin up" and windfields (too still in Aug) Also needs berthing for 36 (no DSOG?)
3/30: Reimers on the Cabled array (not Endurance)
3/28: Sikuliaq will cover Ohman
3/26: Added 2nd Abers & Reimer
3/6: Orcutt "There is a good chance that I will be invited to participate in a IODP drilling expedition off Costa Rica within the same optimal time window for the JdF cruise (July-September 2019)."
2/8: Cohen "W" (-19 days)
1/31: Hansel can do late summer/ early fall near Caymans (flexible).
Out of DRY DOCK...? March/ April? (Al-TBD)
Funded STR's for Kelley (CA), Orcutt (OR) & Abers (AK) need to be covered
Remove 2 SWIFT cruises in the Indian Ocean (too far & no Alvin work)
Add Armstrong's: Chave, McGillicuddy & Fall Pioneer?
1/22: Young W (-22 days w/ Alvin Sentry) as per scientist
1/18/18: Karson W (-33 days w/ Sentry & Jason)
12/15/17: Resenbach W (-7days w/ Alvin)
  Cruise Information  
Ship Request Information
Operator Cruise ID: AT42-18
Chief Scientist: Colleen Hansel, WHOI
Activity Type: At Sea for Science
Created By: Kerry Strom
Compare Request:
Project Short Title: SOLARIS
Requested Year: 2019
Requested Ship: Atlantis  
Request Type: Collaborative  
Created By: Colleen Hansel  
Load Non-charge Days: 0
Load Charge Days: 2   Load Date: 10/6/2019
Activity Days: 11 Adjustment Days Start Date: 10/8/2019
Transit Days: 5 0 End Date: 10/23/2019
Unload Charge Days: 1   Unload Date: 10/24/2019
Unload Non-charge Days: 0
Mob Days: 1  
Science Days: 6 Optimum Start Date: 6/1/2019
Transit Estimate: 0 Earliest Start Date: 3/1/2019
Demob Days: 1 Latest Start Date: 8/1/2019
Repeating Cruise: No Dates To Avoid: Cruise scheduling prior to March 2019 may be sooner than can be accommodated for completion of the instrumentation development.
Number of Repeating Cruises: 0 Repeating Interval:
Repeating Cruise Comments: NA
Justification/Comments: NA
PI   Project/Purpose   Agency   Funding Status   Op Days
Colleen Hansel, WHOI   SOLARIS   NSF/OCE/OTIC   Funded   14
Sean Kelley, WHOI   Sentry Engineering   NSF/OCE/IPS   Funded   3
W. Bruce Strickrott, WHOI   2019 Alvin Engineer   NSF/OCE/IPS   Funded   2
W. Bruce Strickrott, WHOI   2019 Alvin Engineer   NAVY/ONR   Funded   0
  Alvin   OTHER   Funded   0
  Start Port: Newport, OR, USA
  End Port: San Diego, CA, USA
Requested Start Port: Manzanillo, Mexico
Intermediate Port(s): None,
Requested End Port: Manzanillo, Mexico
Port Comments: As stated - this OTIC project aims to conduct novel seafloor chemical measurements. The scientific goals of this project are therefore accomplishable across a variety of seafloor environments including cold seeps, hydrothermal vent systems and other biological communities. As such - the requested port of Manzanillo, MX is only to act as a placeholder until more detailed scheduling can be accommodated.
  Lat/Long Marsden Grid Navy Op Area
Beginning
0° N / 0° E map
335 map
SA02 map
Ending
0° N / 0° E map
335 map
SA02 map
  Show Degrees Minutes    
 
Op Area Description: None
  Lat/Long Marsden Grid Navy Op Area
Beginning
9.83° N / 104.29° W map
11 map
NP13 map
Ending
9.83° N / 104.29° W map
11 map
NP13 map
  Show Degrees Minutes    
 
Op Area Description: Seafloor
Coastal States Requiring Clearance: US EEZ(A)
Foreign Clearance Required: No
Foreign Clearance Comments:
Ancil Facilities:
Instrumentation Requested: NO Radioisotope use/Natural level work
Instrumentation Comments: We would request that an operational CTD and rosette be included aboard the Atlantis for potential use for water column work during night ops.
Ancil Facilities Requested: Alvin
Ancil Facility Comments: N/A
External Cruise Webpage:
Cruise Notes: Newport to Monterey- Alvin/ Sentry Engineering cruise 6 days (8-13th).
Launch VIP's to ship in Monterey for 1 dive
Mobe Hansel in Newport and launch science party on in Monterey TBD.
Sentry can stay on board .