Final -
ID #10745
Version #11 -
1/6/2014
|
Scheduling Contact(s) |
Kerry Strom |
kstrom*%*%*whoi^%^%^edu |
(508) 289-3938 |
|
|
Notes: |
|
NOAA cruise on Ron Brown in Oct is pending 12/11: Nooner cruise in Dec-Jan canceled, Alvin will be used 3/15: updated dates and ports of NOAA cruise on the Brown 4/12: updated dates and to match Thompson schedule. 7/23: changed end port for Chadwick to Astoria 9/21: changed dates and port of NOAA GOM cruise, ports may change 11/4: took off 1 Delany demob date, and added 1 mob date to Chadwick. |
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 26 Feb 2010 |
Dep: | 26 Feb 2010 |
Arr: | 11 Mar 2010 |
Unload: | 11 Mar 2010 |
|
|
|
|
|
|
|
|
Stan Winslow
Transit
|
|
13/13
|
|
Project
|
PI/Institution
|
Project #
|
Days/Agency/Status
|
Transit
|
Stan Winslow/UH_SOEST
|
Not Specified
|
0/NSF-OCE-EDU/F
|
|
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 12 Mar 2010 |
Dep: | 16 Mar 2010 |
Arr: | 30 Mar 2010 |
Unload: | 01 Apr 2010 |
|
|
|
|
|
|
|
|
William W. Chadwick
|
|
15/21
|
Ancil Facs: Jason |
|
|
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 11 Jun 2010 |
Dep: | 15 Jun 2010 |
Arr: | 01 Jul 2010 |
Unload: | 02 Jul 2010 |
|
|
|
|
|
|
|
|
|
|
17/22
|
|
|
|
Notes: Fisher 3 deferred from 2009 plus 2 lost in 2009, plus one lost in 2008 for total of 6 in 2010 Cowen 6 dives in 2010 plus 2 lost in 2008 for a total of 8 dives, Dives lost in 2008 due to loss of manipulator arm Total dives: 14.
San Fran to ODP sites 678nm/2.6days, 3 days transit to station, 2 back to Astoria. |
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 22 Jul 2010 |
Dep: | 26 Jul 2010 |
Arr: | 23 Aug 2010 |
Unload: | 23 Aug 2010 |
|
|
|
|
|
|
|
|
John R. Delaney
|
|
29/33
|
|
|
|
Notes: Nov. 18, 2009: "On Nov 18, 2009, at 7:47, Liz Caporelli ecaporelli@whoi.edu wrote:
Hi Dan, Can you please add one Jason Eng dive to the Delaney cruises.
The STR is under Offinger. Thanks, Liz" -- email from Liz Caporelli.
Nov. 13, 2009: Chadwick and Delaney have agreed that the latter's cruise will go first. Four days alongside at home port, at no charge in Seattle, to mobe JASON ROV. Cruise ends in Newport to change over to Chadwick. One day added to total for de-mobe. |
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 24 Aug 2010 |
Dep: | 26 Aug 2010 |
Arr: | 07 Sep 2010 |
Unload: | 09 Sep 2010 |
|
|
|
|
|
|
|
|
William W. Chadwick
|
|
13/17
|
Ancil Facs: Jason |
|
|
|
Notes: Nov. 13, 2009: Chadwick and Delaney have agreed upon this sequence of their two cruises. JASON ROV will be de-mobed at the end of this cruise, in Astoria. See notes above.
ROV required. Deferred from CY-2009. (Embley's three NOAA days removed as per guidance from Alan Hilton/Jim Ilg on 25 August 2009.) |
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 10 Oct 2010 |
Dep: | 14 Oct 2010 |
Arr: | 04 Nov 2010 |
Unload: | 06 Nov 2010 |
|
|
|
|
|
|
|
|
|
|
22/28
|
|
|
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 07 Nov 2010 |
Dep: | 09 Nov 2010 |
Arr: | 23 Nov 2010 |
Unload: | 24 Nov 2010 |
|
|
|
|
|
|
|
|
Andy Davis
|
|
15/18
|
|
Project
|
PI/Institution
|
Project #
|
Days/Agency/Status
|
Davis, RON BROWN
|
|
Not Specified
|
18/NOAA-OE/F
|
|
|
Notes: JASON, South Atlantic Byte cruise/Deep Corals, Chief Sci Andy Davis |
|
|
|
|
|
Agency
| |
Funded
| |
Pending
| |
Total
|
INST
| |
16
| |
0
| |
16
|
NOAA
| |
46
| |
0
| |
46
|
NSF
| |
61
| |
0
| |
61
|
NSF-OOI
| |
16
| |
0
| |
16
|
OTHER
| |
0
| |
0
| |
0
|
Total
| | 139 | | 0 | | 139 |
|