  2018 - Alvin  
Version 5
Final - ID #13732    Version #2 - 1/7/2019

Scheduling Contact(s)
Kerry Strom kstrom*%*%*whoi^%^%^edu (508) 289-3938

  Notes:   12/19: Vessel arrives 1 day earlier, added the extra day to the demobe. Day count stays the same.
12/11: Despite the late arrive & early departure on Cordes & Teske, Alvin will still get the days they were funded for as per email 12/11/2018. So 2 days have been re-added to the over all day count.
11/16: Teske 1 day early departure d/t berth availability
11/8: Cordes Departed for Guaymas on the 7th instead of the 8th to make up for transit mistake (7 days were allocated when 8 were needed).
9/6/18: Added 2 non-charge load days & 1 unload day to Adams cruise
5/18: Days shifted on Cordes to Premobe in San Juan & Outreach event in San Diego. -1 day d/t Sentry engineering day removed for Premobe.
+2 days on Gregg
12/28: Corrected the mobe for Teske (was 1 day, supposed to be 2).
11/22: Gregg funded 3 additional days and dmobe in San Diego PLUS 1 transit day to newly added station 2.
7/31: Eason "W" (34 days)
6/16: Olive (6 d) & McDermott (36 d) "W"
6/13: Halanych not funded
4/12: Internal Survey needs to be 30-60 days prior to NAVSEA . 3-5 days port stop ideal.
***NAVSEA 5 days (M-F) ideally in Aug or Sept.
***2 engineering dives...1 before KURZ
1/10/17: Find STR- Kelly UW
  View Summary     Set Default Associated Cruises
Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:25 Apr 2018
Dep:28 Apr 2018
Arr:08 May 2018
Unload:08 May 2018
 
Woods Hole, MA, USA
St. George's, Bermuda
 
>70M dpth/
NA06
NA06
 
 
 
40N/70W
40N/70W
 
  W. Bruce Strickrott
  11/14

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
2018 Alvin Engineer Andrew D. Bowen/WHOI Not Specified 10/NSF-OCE-IPS/F
Alvin Eng Dive Not Specified 1/NAVY-ONR/F
Sentry Eng Dive Not Specified 0/OTHER/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:09 May 2018
Dep:11 May 2018
Arr:10 Jun 2018
Unload:11 Jun 2018
 
St. George's, Bermuda
St. George's, Bermuda
 
Mantle Volatile/
NA10
NA10
 
 
 
13N/45W
14N/45W
 
  Mark D. Kurz
  31/34

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Mantle Volatiles Mark D. Kurz/WHOI 1259218 34/NSF-OCE-MGG/F
 
Notes: 1 day Sentry engineering dive (MGG for Alvin) Preferred start date of March 1st (as of 5/17/2016 meeting w/ Mark & Dan)...They advise that their professors will have to take off from university to attend.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:17 Aug 2018
Dep:19 Aug 2018
Arr:02 Sep 2018
Unload:03 Sep 2018
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
VA, NC, SC, GA/
NA06
NA06
 
 
 
37N/73W
30N/78W
 
  Caitlin Adams
  15/18

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
SAB Deepwater Caitlin Adams/NOAA/OER Not Specified 15/NOAA-OE/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:15 Oct 2018
Dep:16 Oct 2018
Arr:06 Nov 2018
Unload:06 Nov 2018
 
Puntarenas, Costa Rica
Puntarenas, Costa Rica
 
Costa Rica/
NP13
NP13
 
 
 
9N/84W
9N/84W
 
  Erik Cordes
  22/23

Clearances: Costa Rica(T)
 
Project PI/Institution Project # Days/Agency/Status
Costa Rica seeps Erik Cordes/Temple 1635219 24/NSF-OCE-BIO/F
 
Notes: 3 days Sentry engineering dive (MGG for Alvin) 1 day re-added to schedule despite the early departure as per 12/11/2018 email.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:15 Nov 2018
Dep:16 Nov 2018
Arr:29 Nov 2018
Unload:30 Nov 2018
 
Guaymas, Mexico
Manzanillo, Mexico
 
Guaymas Basin/
NP13
NP13
 
 
 
27N/111W
27N/111W
 
  Andreas P. Teske
  14/16

Clearances: Mexico(T)
 
Project PI/Institution Project # Days/Agency/Status
Guaymas Basin Andreas P. Teske/UNC_CH OCE-1357238 17/NSF-OCE-BIO/F
Guaymas Basin Samantha B. Joye/Georgia OCE-1357360; OCE-1357238 0/NSF-OCE-BIO/F
 
Notes: 1 day re-added to schedule despite the early departure as per 12/11/2018 email.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Dec 2018
Dep:03 Dec 2018
Arr:19 Dec 2018
Unload:22 Dec 2018
 
Manzanillo, Mexico
San Diego, CA, USA
 
8°20'N Seamount/
NP13
SA02
 
 
 
8N/107W
0N/0E
 
  Patricia M. Gregg
  17/22

Clearances: France(T)
 
Project PI/Institution Project # Days/Agency/Status
OASIS Patricia Gregg/UIUC 1356610 22/NSF-OCE-MGG/F
Dec22-Outreach Not Specified 0/OTHER/P

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:23 Dec 2018
Dep:23 Dec 2018
Arr:31 Dec 2018
Unload:31 Dec 2018
 
San Diego, CA, USA
San Diego, CA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  None /transit
Maintenance
  9/9

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Agency   Funded   Pending   Total
NAVY   1   0   1
NOAA   15   0   15
NSF   107   0   107
OTHER   0   0   0
Total  123 0 123