  2020 - Neil Armstrong  
Version 9
Secure - ID #14272    Version #2 - 6/1/2020

Scheduling Contact(s)
Kerry Strom kstrom*%*%*whoi^%^%^edu (508) 289-3938

  Notes:   ****2020 US Academic Research Fleet vessel schedules are subject to change as the COVID-19 pandemic evolves.
Scheduled cruise Chief Scientists are urged to keep in close contact with the vessel operators to remain aware of any updates/changes.

5/28: Shifting 2 of the 18 transit days to OSNAP W days for Irminger ops
5/13: -10 days from Spring/Fall Pioneer, -6 days from Irminger.
Added 7 days for Bill Johns OSNAP E.
3/31: May 11th earliest start date for Pioneer as per OOI meeting
3/25: -46 day BLT cruise d/t Covid19. Day count was 229, now 183)
3/16: CA DFO cruise cancelled d/t Corona Virus -28 days (Day count for the year was 257, now 229)
2/25: 1 day delay from yard d/t stern thruster issue.
2/13: Drydock delay, shift Adeon/ Peach off transit
1/29: Adding WHOI Stellwagen Mapping day
1/23: Adding the 4th DFO day at the end of the cruise for a total of 25 days
1/21: Adding 3 days to DFO (Removing WHOI funded day for mapping) and 1 day to Tampa to WHOI transit (was 7, now 8 days) Shift OTZ to the right 1 day.
1/15: Adding 1 charge day to NSF & ONR for home port mobe (PEACH & ADEON)
1/13: Departure DD must be Feb 23rd (39 days)
1/10/20: Swap Spring Pioneer dates as per OOI's request
Add Adeon & Peach to deadhead back to WHOI after DD
Change CA DFO from 33 to 18 days + 1 WHOI day
AND...Add pit stop in Reykjavik for Niskine as per CS & ONR
1/7/20: Oceaneering ROV transformer failure delayed departure by 4 days and cancelled the Adeon & Peach portion of the cruise/ deadhead from WHOI to Tampa.
11/12: Deadheads for CA DFO added & updated voy #'s
10/29: Adding "Rapid" PEACH recovery cruise (9 days)
10/1: Pioneer is 24 days each (STR said 26, so 4 days were removed from the schedule changing the day count from 251 to 247) Last 2 cruises of the year are 2 days earlier.
Thanksgiving is the 26th in 2020
8/28: Exports Cancelled on Armstrong d/t lack of funding (NASA)
7/23: Add possible DoD cruise to start 2020 season
Shift Inst cruise down to October as a TBD
7/1: -2 day from EXPORTS for Dever (NSF) "W"
5/1: Johns Dutch Vsl -27 days
4/15: OSNAP West notified of Barter
1/31: Pickart is looking for a 37 day cruise, same as 2018
Fall Pioneer missing*
NASA: Sampling starting on site on May 1, 2020 (could be May 15)
1/15: Makris 2 ONR cruises are for 2021. He will update the STR (-88 days!)
1/3: Ferrari "BLT" No earlier than 6/20 start
***1 – June 2020, Armstrong
***2 – September 2020, UK vessel
***3 – June 2021, UK vessel
2/15: Send "W" (-22 days)
2020 is a LEAP year 366 days
  View Summary     Set Default Associated Cruises
Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Jan 2020
Dep:01 Jan 2020
Arr:01 Jan 2020
Unload:01 Jan 2020
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Timothy Twomey
General Upkeep and Outfitting
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:02 Jan 2020
Dep:02 Jan 2020
Arr:03 Jan 2020
Unload:03 Jan 2020
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Jennifer Miksis-Olds
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
PEACH Dana K. Savidge/Skidaway 1559476 1/NSF-OCE-PO/F
ADEON Jennifer Miksis-Olds/UNH M16PC00003 1/NAVY-ONR/F
 
Notes: ONR did deploy lander and Oceaneering ROV failed to work

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:04 Jan 2020
Dep:04 Jan 2020
Arr:06 Jan 2020
Unload:06 Jan 2020
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Timothy Twomey
General Upkeep and Outfitting
  3/3

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:07 Jan 2020
Dep:07 Jan 2020
Arr:17 Jan 2020
Unload:17 Jan 2020
 
Woods Hole, MA, USA
Tampa, FL, USA
 
Hatteras/
NA06
NA06
 
 
 
37N/76W
37N/76W
 
  Timothy Twomey
Transit Cruise
  11/11

Clearances: US EEZ(T)
 
Project PI/Institution Project # Days/Agency/Status
11 days Not Specified 0/OTHER/P

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:18 Jan 2020
Dep:18 Jan 2020
Arr:24 Feb 2020
Unload:24 Feb 2020
 
Tampa, FL, USA
Tampa, FL, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Timothy Twomey
Overhaul or Repair
  38/38

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Regulatory 38 days Not Specified 0/OTHER/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:25 Feb 2020
Dep:25 Feb 2020
Arr:04 Mar 2020
Unload:04 Mar 2020
 
Tampa, FL, USA
Woods Hole, MA, USA
 
None/
NA09
NA09
 
 
 
27N/85W
27N/85W
 
  Harvey Seim
Transit Cruise
  9/9

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Non-Op Transit Not Specified 6/OTHER/F
Ledwell Test Not Specified 2/INST-WHOI/F
ARM-MB&USBL cal Laura Stolp/WHOI Not Specified 1/NSF-OCE-IPS/F
 
Notes: EM122: "We only have 24 hrs from this year to move to next year. There is a science cruise @ 26.77 N, 85.07 W. If we can do the EM122 at the same site, we would not have to worry about transit time and there is a chance that science would not need all their time" email dated 12/4/19

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:05 Mar 2020
Dep:05 Mar 2020
Arr:09 Mar 2020
Unload:09 Mar 2020
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Timothy Twomey
General Upkeep and Outfitting
  5/5

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
5 Days Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:10 Mar 2020
Dep:11 Mar 2020
Arr:16 Mar 2020
Unload:17 Mar 2020
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
Slope Sea/
NA06
NA06
 
 
 
39N/70W
39N/70W
 
  Joel Llopiz
  6/8

Clearances: US EEZ(T)
 
Project PI/Institution Project # Days/Agency/Status
OTZ WHOI shiptime Joel Llopiz/WHOI Not Specified 8/INST-WHOI/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:18 Mar 2020
Dep:18 Mar 2020
Arr:04 Jun 2020
Unload:04 Jun 2020
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Timothy Twomey
General Upkeep and Outfitting
  79/79

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
79 Days Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:05 Jun 2020
Dep:07 Jun 2020
Arr:17 Jun 2020
Unload:18 Jun 2020
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
NE Shelf/
NA06
NA06
 
 
 
39N/69W
41N/71W
 
  Al Plueddemann
  11/14

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
OOI Pioneer Al Plueddemann/WHOI Not Specified 14/NSF-OOI-OOI/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:19 Jun 2020
Dep:19 Jun 2020
Arr:20 Jun 2020
Unload:20 Jun 2020
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Timothy Twomey
General Upkeep and Outfitting
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
2 Days Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:TBD
Dep:TBD
Arr:TBD
Unload:TBD
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
Irm/Lab Seas/
NA04
NA04
 
 
 
59N/30W
52N/53W
 
  Robert S. Pickart
  40/43

Clearances: Denmark(T)
 
Project PI/Institution Project # Days/Agency/Status
OSNAP West Robert S. Pickart/WHOI 1756361 43/NSF-OCE-PO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:TBD
Dep:TBD
Arr:TBD
Unload:TBD
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Timothy Twomey
General Upkeep and Outfitting
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
2 Days Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:TBD
Dep:TBD
Arr:TBD
Unload:TBD
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
Irminger Sea/
NA01
NA01
 
 
 
60N/39W
60N/39W
 
  Sebastien Bigorre
  35/40

Clearances: Greenland(T)
 
Project PI/Institution Project # Days/Agency/Status
OOI Irminger Sea Weller OOI Project Team/WHOI Not Specified 30/NSF-OOI-OOI/F
OSNAP West Robert S. Pickart/WHOI 1756361 7/NSF-OCE-PO/F
OSNAP-GDWBC Moorings Amy S. Bower/WHOI 1756363 5/NSF-OCE-PO/F
 
Notes: Reduced Irminger from 12 to 7 days Added 7 Bill Johns days 10 day transit up, 1 day to Johns, 10 days back to WHOI

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:TBD
Dep:TBD
Arr:TBD
Unload:TBD
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Timothy Twomey
General Upkeep and Outfitting
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
2 Days Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:TBD
Dep:TBD
Arr:TBD
Unload:TBD
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
N. Atlantic/
NA01
NA01
 
 
 
61N/30W
61N/30W
 
  William E. Johns
  34/38

Clearances: Iceland(T)
 
Project PI/Institution Project # Days/Agency/Status
OSNAP East 2020 William E. Johns/RSMAS 1756231 19/NSF-OCE-PO/F
niskin Jennifer A. MacKinnon/SIO Not Specified 19/NAVY-ONR/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:TBD
Dep:TBD
Arr:TBD
Unload:TBD
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Timothy Twomey
General Upkeep and Outfitting
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
2 Days Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:TBD
Dep:TBD
Arr:TBD
Unload:TBD
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
NE shelf/
NA06
NA06
 
 
 
39N/69W
41N/71W
 
  Al Plueddemann
  11/14

Clearances: US EEZ(T)
 
Project PI/Institution Project # Days/Agency/Status
OOI Pioneer Al Plueddemann/WHOI Not Specified 14/NSF-OOI-OOI/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:TBD
Dep:TBD
Arr:TBD
Unload:TBD
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Timothy Twomey
General Upkeep and Outfitting
  2/2

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
2 Days Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:TBD
Dep:TBD
Arr:TBD
Unload:TBD
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
NE Shelf Break/
NA06
NA06
 
 
 
42N/71W
42N/71W
 
  Ying-Tsong Lin
  9/12

Clearances: US EEZ(T)
 
Project PI/Institution Project # Days/Agency/Status
TFO NESBA Ying-Tsong Lin/WHOI Not Specified 12/NAVY-ONR/F
 
Notes: Confirmed timing is ok July 2019

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:TBD
Dep:TBD
Arr:TBD
Unload:TBD
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Timothy Twomey
General Upkeep and Outfitting
  6/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
6 Days Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:TBD
Dep:TBD
Arr:TBD
Unload:TBD
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
Atlantic OCS/
NA06
NA06
 
 
 
36N/74W
32N/75W
 
  Jennifer Miksis-Olds
  16/20

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
ADEON Jennifer Miksis-Olds/UNH M16PC00003 20/NAVY-ONR/F
 
Notes: Changed from 3 to 2 mobe days as per CS 4/17/2019

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:TBD
Dep:TBD
Arr:TBD
Unload:TBD
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Timothy Twomey
General Upkeep and Outfitting
  13/13

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
13 Days Not Specified 0/OTHER/NonOp
Agency   Funded   Pending   Total
INST   10   0   10
NAVY   52   0   52
NSF   76   0   76
NSF-OOI   58   0   58
OTHER   6   0   6
Total  202 0 202
<
Day Type   Total
Transit Cruise   20
General Upkeep and Outfitting   117
Overhaul or Repair   38
At Sea for Science   164
Total  339
<
Load/Unload Days   Total
ChargeLoad   16
ChargeUnload   11
Total  27