  2011 - Oceanus  
Final 2011
Final - ID #11317    Version #3 - 1/3/2012

Scheduling Contact(s)
Kaya Johnson kaya^%^%^johnson*%*%*oregonstate^%^%^edu (971) 563-0790
Christine Golden goldenc*%*%*oregonstate^%^%^edu (541) 867-0200
Roberta Mesa roberta^%^%^mesa*%*%*oregonstate^%^%^edu (541) 867-0295

  Notes:   1/3/12: Final schedule published for 2011.

11/14: Updated Conte demob Bermuda port call Oct 16 - Oct 17. Updated final arrival for Oceanus into WHOI Nov 10 for LeBlanc (NOAA). 213 total op days for 2011.
9/28: Updated operation days to 215.
9/21: Edited STANTON cruise. Arrival one day early into Woods Hole (9/16). No change in # op days (216).
9/8/11: Added NOAA NBDC cruise (LeBlanc) 5 days Nov 8 - 12.
8/19: Added CONTE cruise Oct 14 - 16 & added 1 day onto McGillicuddy (Keafer) and shifted cruise 8 days later. new total op days 211.
8/3: ADDED CRUISE - McGillicuddy / Keafer Oct 17 - Oct 27, 2011.
8/2: Toole cruise end 1 day early. 9 op days total. Will add 1 day onto Eglinton cruise Oct 11' (total 13 sci days).
7/20: Changed Kohler arrival date WHOI to July 09 (3 days early).
Added 1 day for Eglington (12 op days total).
3/14: Added Panama City port call to C.Davis cruise
2/28: Reduced # of operating days by 3 to 194 (took away 3 charged port days from Weller).
2/25: added Maintenance period July 12 - July 24
2/4/11: Shifted Weller / OOI cruise from July to Sept 22 - 26.
1/31/11: Added transit to St. Pete / C.Davis GOM cruise / Galveston WHOI transit.
-OOI will have one cruise in July. The second cruise TBD sometime from Sept 2011 to March 2012
-Ledwell cruise is a 3 ship op with Oceanus, Endeavor, Hatteras
  View Summary     Set Default Associated Cruises
Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Jan 2011
Dep:01 Jan 2011
Arr:20 Apr 2011
Unload:20 Apr 2011
 
 
 
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Available for Service
  110/110
 
Project PI/Institution Project # Days/Agency/Status

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Mar 2011
Dep:01 Mar 2011
Arr:07 Mar 2011
Unload:07 Mar 2011
 
Woods Hole, MA, USA
St. Petersburg, FL, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Transit
  7/7
 
Project PI/Institution Project # Days/Agency/Status
VPR Gulf of Mexico Cabell Davis/WHOI Not Specified 7/NOAA/F
 
Notes: Transit 1436 WHOI to St. Pete / Tampa = 5.7 / 6 days + 1 = 7 days

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:08 Mar 2011
Dep:09 Mar 2011
Arr:19 Mar 2011
Unload:19 Mar 2011
 
St. Petersburg, FL, USA
Panama City, FL, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
  Cabell Davis
  11/12
 
Project PI/Institution Project # Days/Agency/Status
VPR Gulf of Mexico Cabell Davis/WHOI Not Specified 12/NOAA/F
 
Notes: NOAA/BP funded. Transit WHOI to Tampa = 1436 nm = 5.7/6day + 1 = 7 days Transit Galveston to WHOI = 1953 nm = 7.8d/8day + 1 = 9 days

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:20 Mar 2011
Dep:20 Mar 2011
Arr:08 Apr 2011
Unload:09 Apr 2011
 
Panama City, FL, USA
Galveston, TX, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
  Cabell Davis
  20/21
 
Project PI/Institution Project # Days/Agency/Status
VPR Gulf of Mexico Cabell Davis/WHOI Not Specified 21/NOAA/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:10 Apr 2011
Dep:10 Apr 2011
Arr:18 Apr 2011
Unload:18 Apr 2011
 
Galveston, TX, USA
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Transit
  9/9
 
Project PI/Institution Project # Days/Agency/Status
VPR Gulf of Mexico Cabell Davis/WHOI Not Specified 9/NOAA/F
 
Notes: transit Galveston to WHOI = 1953 = 8.1/ 8 days + 1 = 9 day transit.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:21 Apr 2011
Dep:23 Apr 2011
Arr:13 May 2011
Unload:14 May 2011
 
Woods Hole, MA, USA
Bridgetown, Barbados
 
 /
NA06
NA09
 
 
 
32N/64W
13N/59W
 
  Dennis J. McGillicuddy
  21/24

Clearances: Bermuda(T), Antigua and Barbuda(T), Barbados(T)
 
Project PI/Institution Project # Days/Agency/Status
Trichodesmium 2010 Dennis J. McGillicuddy/WHOI ARRA 0925284 22/NSF-OCE-BIO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:15 May 2011
Dep:17 May 2011
Arr:20 May 2011
Unload:21 May 2011
 
Bridgetown, Barbados
Bridgetown, Barbados
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  4/7
 
Project PI/Institution Project # Days/Agency/Status
Seep Connectivity Cindy L. Van Dover/DUML 1031050 7/NSF-OCE-BIO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:22 May 2011
Dep:22 May 2011
Arr:28 May 2011
Unload:28 May 2011
 
Bridgetown, Barbados
Morehead City, NC, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Transit
  7/7
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 7/NSF-OCE-EDU/F
 
Notes: Bridgetown to Moorehead city Distance = 1603 Nautical Miles Time usage = 6 days 2 hours at 11kts

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:29 May 2011
Dep:01 Jun 2011
Arr:21 Jun 2011
Unload:22 Jun 2011
 
Morehead City, NC, USA
Morehead City, NC, USA
 
Off Outer Banks/
NA06
NA06
 
 
 
34N/74W
34N/74W
 
  Craig M. Lee
  21/25
 
Project PI/Institution Project # Days/Agency/Status
LatMix James R. Ledwell/WHOI OCE-0751653 13/NSF-OCE-EDU/F
LatMix James R. Ledwell/WHOI N00014-09-1-0175 12/NAVY-ONR/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:23 Jun 2011
Dep:25 Jun 2011
Arr:09 Jul 2011
Unload:11 Jul 2011
 
Morehead City, NC, USA
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  15/19
 
Project PI/Institution Project # Days/Agency/Status
DART O&M Craig Kohler/NOAA_NDBC Not Specified 17/NOAA-NWS-NDBC/F
 
Notes: Science completed early = early arrival into WHOI July 10.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:13 Jul 2011
Dep:13 Jul 2011
Arr:24 Jul 2011
Unload:24 Jul 2011
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
Maintenance/
 
 
 
 
 
0N/0E
0N/0E
 
 
Maintenance
  12/12
 
Project PI/Institution Project # Days/Agency/Status
Not Specified 0/OTHER/F
 
Notes: Maintenance (12 days) / Open / TBD

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:23 Jul 2011
Dep:25 Jul 2011
Arr:02 Aug 2011
Unload:03 Aug 2011
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
 /
NA06
NA06
 
 
 
42N/71W
42N/71W
 
  John M. Toole
  9/12

Clearances: Bermuda(T)
 
Project PI/Institution Project # Days/Agency/Status
Line W: A sustained John M. Toole/WHOI 0726720 9/NSF-OCE-PO/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:05 Aug 2011
Dep:07 Aug 2011
Arr:01 Sep 2011
Unload:02 Sep 2011
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  26/29
 
Project PI/Institution Project # Days/Agency/Status
Pteropods & CO2 Gareth Lawson/WHOI 1041068 26/NSF-OCE-BIO/F
 
Notes: Ocean acidification funding. Will not be decided on until Sept.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:02 Sep 2011
Dep:06 Sep 2011
Arr:16 Sep 2011
Unload:17 Sep 2011
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
Georges Bank/
NA06
NA06
 
 
 
39N/58W
39N/58W
 
  Tim Stanton
  11/16
 
Project PI/Institution Project # Days/Agency/Status
Fish Studies Tim Stanton/WHOI N00014-04-1-0440 11/NAVY-ONR/F
 
Notes: Cruise arrived 1 day early into WHOI (9/16). This cruise is a two ship operation with Delaware and needs to start on Sept 6th and requires 4 days for mobilization over the Holiday weekend. 5th is the holiday.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:20 Sep 2011
Dep:22 Sep 2011
Arr:26 Sep 2011
Unload:27 Sep 2011
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
off Woods Hole/
NA06
NA06
 
 
 
45N/65W
45N/65W
 
  Weller OOI Project Team
  5/8
 
Project PI/Institution Project # Days/Agency/Status
OOI CGSN Weller OOI Project Team/WHOI Not Specified 5/NSF-OOI-OOI/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:29 Sep 2011
Dep:01 Oct 2011
Arr:13 Oct 2011
Unload:13 Oct 2011
 
Woods Hole, MA, USA
St. George's, Bermuda
 
NA6/
NA06
NA06
 
 
 
41N/70W
41N/70W
 
  Timothy I. Eglinton
  13/15

Clearances: Canada(T)
 
Project PI/Institution Project # Days/Agency/Status
CARBON EXPORT Timothy I. Eglinton/WHOI arra 0851350 11/NSF-OCE-CO/F
CARBON EXPORT Timothy I. Eglinton/WHOI arra 0851350 1/NSF-OCE-CO/F
Line W: A sustained John M. Toole/WHOI 0726720 1/NSF-OCE-PO/F
 
Notes: 8/16: New end port will be Bermuda (St Georges) to accommodate M. Conte's mooring recovery. WHOI to N station to S station to WHOI 1819nm/6.8D/8D + 3 op days= 11 days 7/20: Added 1 science day for recovery of sediment trap mooring. New arrival date will be July 12.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:14 Oct 2011
Dep:14 Oct 2011
Arr:16 Oct 2011
Unload:16 Oct 2011
 
St. George's, Bermuda
St. George's, Bermuda
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  3/3
 
Project PI/Institution Project # Days/Agency/Status
OFP mooring rcvy Maureen H. Conte/BIOS Not Specified 3/NSF-OCE-EDU/F
 
Notes: 11/14: Cruise finished Oct 16 to use more time at sea dragging for mooring. Demob day same as arrival Oct 16. 8/16: Cruise added 8/16 to recover a unreleased OFP mooring by dragging with Oceanus' trawl wire. Oct 14-16.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:17 Oct 2011
Dep:17 Oct 2011
Arr:20 Oct 2011
Unload:20 Oct 2011
 
St. George's, Bermuda
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
Transit
  4/4
 
Project PI/Institution Project # Days/Agency/Status
Transit Not Specified 4/NSF-OCE-EDU/F
 
Notes: Transit St. Georges to WHOI = 630nm@10= 2.6/ 3 days +1 = 4 days transit.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:22 Oct 2011
Dep:24 Oct 2011
Arr:04 Nov 2011
Unload:05 Nov 2011
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  12/15
 
Project PI/Institution Project # Days/Agency/Status
PCM-HAB GOM predict Dennis J. McGillicuddy/WHOI NA11NOS4780023 11/NOAA/F
GOM Brad Butman/USGS_Woods Hole Not Specified 1/USGS/F
 
Notes: Bruce Keafer is Ch Sci and POC for this cruise bkeafer@whoi.edu May add 1 extra day with USGS.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:07 Nov 2011
Dep:08 Nov 2011
Arr:10 Nov 2011
Unload:11 Nov 2011
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
 /
 
 
 
 
 
0N/0E
0N/0E
 
 
  3/5
 
Project PI/Institution Project # Days/Agency/Status
LeBlanc PI / NOAA Not Specified 3/NOAA-NWS-NDBC/F
 
Notes: 11/14: NOAA completed work early and arrived Nov 10 to finish op year.
Agency   Funded   Pending   Total
NAVY   23   0   23
NOAA   80   0   80
NSF   104   0   104
NSF-OOI   5   0   5
OTHER   0   0   0
USGS   1   0   1
Total  213 0 213
<
<