Kerry Strom kstrom*%*%*whoi^%^%^edu (508) 289-3938

  Notes:   8/5: Add 4 days to Jason for Kelley OOI make-up work
7/31: Humphris moved to 2018 d/t drydock delay on Thompson (-9 days)
5/22: Kulin/ONC cancelled & removed from schedule.
3/22: 1 day added to Nooner on Revelle, schedule shifts to right 1 day.
2/27: Humphris moved to the left 1 day to accommodate holiday loading.
2/2: Humphris pushed back 2 weeks as per Thompson schedule (email 1/31)
12/20: Ship directly to Auckland as per Doug's email 12/20. Start 1 week earlier.
11/9: 1 day less mobe & transit, 1 day added to demobe for Kelly (save 1 day)
10/17: Saved a day from Kelley to get from Newport to WHOI on time for Wheat.
10/5: Delete 1st Kulin job, put everything on Revelle by combining jobs...
9/01: Wheat has 2 more days on Atlantis d/t wx as per NSF.
8/25: KM & Revelle Pac NW
7/26: Emails...Ship Jason from Barbados to HI onto Thompson for Humphris cruise (not NZ) Thompson departure delayed ~17 days from Honolulu to wait for Jason.

Optimum Start date (earliest-latest)
Cheadle 2/1 (12/6 - 4/1)
McGuire 2/1 (1/1 - 3/1)
Wheat 3/1 (3/1 - 8/1)
Humphris 1/5 (11/1 - 3/31)
Kulin a) 7/1 (6/5 - 7/17)
Kulin b) 8/28 (7/31 - 9/4)
Nooner 7/1 (6/1 - 9/1)
Jackson 7/1 (5/1 - 10/1)
Di lorio a) 5/1 (4/1 - 7/1)
Di lorio b) 7/1 (6/1 - 8/1)
Kelley 7/7 (7/7 - 7/10) ?
Moyer 7/15 (6/15 - 9/1)
Wilcook 8/1 (6/1 - 9/15)
Lang 7/15 (5/1 - 9/15)
  View Summary     Set Default Associated Cruises
Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:12 Jan 2017
Dep:15 Jan 2017
Arr:21 Feb 2017
Unload:23 Feb 2017
 
Isla de Pascua, Chile
Rada de Arica, Chile
 
Pito Deep/
SP03
SP03
 
 
 
23S/112W
23S/112W
 
  Michael J. Cheadle
  38/43

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Pito Deep Gabbros Michael J. Cheadle/UWYO 1459462 42/NSF-OCE-MGG/F
ATL JASON ENG DIVE Not Specified 1/NSF-OCE-IPS/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:24 Feb 2017
Dep:26 Feb 2017
Arr:09 Mar 2017
Unload:11 Mar 2017
 
Rada de Arica, Chile
Rada de Arica, Chile
 
Northern Chile/
SP03A
SP03A
 
 
 
21S/70W
21S/71W
 
  Jeffrey J. McGuire
  12/16

Clearances: Chile(T)
 
Project PI/Institution Project # Days/Agency/Status
Chile Geodesy Jeffrey J. McGuire/WHOI 1459095 16/NSF-OCE-MGG/F
RV ATLANTIS Not Specified 0/OTHER/P

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:12 Mar 2017
Dep:12 Mar 2017
Arr:02 Jun 2017
Unload:02 Jun 2017
 
Rada de Arica, Chile
Woods Hole, MA, USA
 
WHOI/
NA06
NA06
 
 
 
41N/70W
41N/70W
 
  Catherine Offinger
Maintenance
  83/83

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Van Re-Fit (84 days) Not Specified 0/OTHER/P
 
Notes: 30 days shipping Arica to WHOI 7 days shipping WHOI to Seattle Matt needs 44 days minimum for re-fit...They have 47.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:09 Jul 2017
Dep:13 Jul 2017
Arr:23 Jul 2017
Unload:24 Jul 2017
 
Newport, OR, USA
Newport, OR, USA
 
Axial Seamount/
NP09
NP09
 
 
 
46N/130W
46N/130W
 
  Scott L. Nooner
  11/16

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Axial Geodesy 2013 Scott L. Nooner/UNCW 1356216 14/NSF-OCE-MGG/F
Jason Eng Dive Matt Heintz/WHOI Not Specified 1/NSF-OCE-IPS/F
NeMO Time Series David Butterfield/UW Not Specified 1/NOAA/F
RV REVELLE & Sentry William W. Chadwick/OSU_HMSC Not Specified 0/OTHER/P
 
Notes: Chadwick is co-PI with Nooner and wants Sentry onboard as well. Available space on board is still being determined by the vehicle departments.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:25 Jul 2017
Dep:27 Jul 2017
Arr:27 Aug 2017
Unload:29 Aug 2017
 
Newport, OR, USA
Newport, OR, USA
 
Juan de Fuca/
NP09
NP09
 
 
 
45N/127W
44N/125W
 
  Deborah S. Kelley
  32/36

Clearances: NONE(T)

Ancil Facs: Jason
 
Project PI/Institution Project # Days/Agency/Status
OOI-Cabled Array Deborah S. Kelley/UW Not Specified 35/NSF-OOI-OOI/F
Enhance OOI at Axial William W. Chadwick/OSU_HMSC 1634150 1/NSF-OCE-MGG/F
Flipping Tilt William S. Wilcock/UW 1634103 0/NSF-OCE-OTIC/F
RV REVELLE Not Specified 0/OTHER/P
 
Notes: Thompson: Mobe June 29 (4 days) Jason Mob at Pier 90 or 91 then transfer to UW dock for science load out. Two intermediate stops in Newport, OR for 1 or 2 nights weather dependent.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:30 Aug 2017
Dep:01 Sep 2017
Arr:07 Sep 2017
Unload:08 Sep 2017
 
Newport, OR, USA
Newport, OR, USA
 
Oregon Profile/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  William S. Wilcock
  7/10

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Oregon Profile ASCPR William S. Wilcock/UW 1558477 10/NSF-OCE-MGG/F
RV REVELLE Not Specified 0/OTHER/P

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:09 Sep 2017
Dep:09 Sep 2017
Arr:11 Sep 2017
Unload:12 Sep 2017
 
Newport, OR, USA
Newport, OR, USA
 
Juan de Fuca/
NP09
NP09
 
 
 
45N/127W
44N/125W
 
  Dana Manalang
  3/4

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
OOI-Cabled Array Deborah S. Kelley/UW Not Specified 4/NSF-OOI-OOI/F
RV REVELLE Not Specified 0/OTHER/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:28 Sep 2017
Dep:02 Oct 2017
Arr:01 Nov 2017
Unload:03 Nov 2017
 
Woods Hole, MA, USA
Bridgetown, Barbados
 
North Pond MAR/
NA10
NA10
 
 
 
22N/46W
22N/46W
 
  Charles G. Wheat
  31/37

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
North Pond 2016 Charles G. Wheat/UAF_CFOS 1536623 30/NSF-OCE-MGG/F
Viruses in Basement Grieg Steward/UH_SOEST 1636402 3/NSF-OCE-BIO/F
RV ATLANTIS Not Specified 0/OTHER/P
 
Notes: Transits: WHOI to Job Start 1740nm = 6.5 days = 7+1= 8 days Job Finish to Barbados 970nm=3.6 days = 4+1 = 5 days 13 days TOTAL transit
Agency   Funded   Pending   Total
NOAA   1   0   1
NSF   118   0   118
NSF-OOI   39   0   39
OTHER   0   0   0
Total  158 0 158