Project Title: |
Agulhas Current Time-series (ACT): Towards a multi-decadal index of Agulhas Current Transport |
Project Status: |
Submitted |
Principal Investigator: |
Lisa Beal, RSMAS |
Project Institution: |
RSMAS |
Project ID: |
101699 |
Version #: |
4 |
Date Submitted: |
8/12/2008 1:34:00 PM |
Created By: |
Lisa Beal |
Date Last Modified: |
3/1/2012 12:49:00 PM |
URI Serial #: |
None |
Funding Agencies: |
NSF/OCE/PO - 0850891 - Funded |
Summary of Field Work: |
Three cruises, eighteen months apart, to deploy, turn-around, and recover and array of moorings across the Agulhas Current off the east coast of South Africa. |
Summary of Facility Requirements: |
|
Summary of other requirements and comments: |
|
|
Type of Request: |
Primary Ship Use |
Request Status: |
Submitted |
Request ID: |
1002335 |
Created By: |
Lisa Beal |
Date Last Modified: |
3/1/2012 12:49:00 PM |
Date Submitted: |
8/12/2008 1:34:00 PM |
|
Year: |
2011
|
Ship/Facility: |
Knorr
|
Optimum Start Date:
|
11/1/2011 |
Dates to Avoid: |
avoid austral winter due to adverse weather conditions in Agulhas when wind blows against current. Recover moorings before 22 months. |
|
|
|
|
Earliest Start Date: |
10/1/2010 |
Multi-Ship Op: |
No |
Latest Start Date: |
1/1/2011 |
Other Ship(s): |
|
|
Operating Days Needed: |
Science Days |
Mob Days |
De-Mob Days |
Estimated Transit Days |
Total Days |
20 |
2 |
1 |
0 |
23 |
Repeating Cruise?
(within same year) |
No |
Interval: |
|
# of Cruises: |
|
|
Description of Repeating cruise requirements: |
|
Justification/Explanation for ship choice, dates,
conflicts, number of days & multi-ship operations: |
Need to recover, recondition, and redeploy each mooring. Deployment cruise required 7 full days of mooring operations plus CTD and CPIES operations. Here, anticipate 14 days of mooring operations, plus five days of CTDs/CPIES and one weather day. |
|
Short Description of Op Area
for use in schedules: |
|
Description of Op Area: |
300 km long mooring line off East London, South Africa |
Op Area Size/Dia.: |
|
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
|
|
|
Ending
|
|
|
|
|
Show Degrees Minutes |
|
|
|
|
Foreign Clearance Required? |
Yes |
Coastal States:
South Africa |
Important Info on Foreign Research Clearances
|
|
Are you or any member in your science party bringing in any science equipment items which are regulated for export by the International Traffic in Arms Regulations (ITAR) and/or the Export Administration Regulations (EAR)?
|
No |
If yes, have you applied for the necessary permits through your export control office?
|
No |
Questions about ITAR/EAR regulations?
|
Comments about foreign clearance requirements or description of any other special permitting requirements (e.g., MMPA, ESA, IHA, Marine Sanctuaries, etc.) |
|
|
Requested Start Port |
Intermediate Port(s) |
Requested End Port |
Durban, South Africa |
None |
Durban, South Africa |
Explanation/justification for requested ports and dates of intermediate stops or to list additional port stops |
Cape Town is also an excellent port and perhaps logistically easier. However, is 2.5 days steam from work site. |
Important Info on Working in Foreign Ports
|
|
|
Chief Scientist: |
Lisa Beal, RSMAS |
# in Science Party |
10 |
# of different science teams |
1 |
# Marine Technicians to be
provided by ship operator:
(include in science party total)
|
1 |
Explanation of Science Party Requirements and Technician Requirements |
|
|
Dynamic Positioning | ADCP | Multibeam | Seismic |
Dredging/Coring/Large Dia. Trawl Wire | Stern A-frame | Fiber Optic (.681) | 0.680 Coax Wire |
SCUBA Diving | Radioisotope use - briefly describe | NO Radioisotope use/Natural level work | Other Operator Provided Inst. - Describe |
0 PI-Provided Vans - briefly describe | MOCNESS | | |
|
Explain Instrumentation or Capability requirements that could affect choice of ship in scheduling. |
CTD package with Lowered ADCP large winch with secondary drum
|
|
|
Explain Major Ancillary Facilities Requirements and list description and provider for "other" systems. |
|
|