|
C2/nav Test
-
2010
-
Robert Gordon Sproul
|
|
|
Project Title: |
C2/Nav test workup for ASWEET 10-1 |
Project Status: |
Submitted |
Principal Investigator: |
William Schopfel, ONR |
Project Institution: |
ONR |
Project ID: |
102580 |
Version #: |
3 |
Date Submitted: |
7/30/2010 10:03:00 AM |
Created By: |
William Schopfel |
Date Last Modified: |
9/8/2010 5:17:00 PM |
URI Serial #: |
None |
Funding Agencies: |
NAVY/ONR - NONE - Funded |
Summary of Field Work: |
Conduct a C2/Navigation Test on the SCORE range. Testing to include the use of the SCORE hydrophones and a Freewave site established on SCI |
Summary of Facility Requirements: |
|
Summary of other requirements and comments: |
|
|
Type of Request: |
Primary Ship Use |
Request Status: |
Submitted |
Request ID: |
1003947 |
Created By: |
William Schopfel |
Date Last Modified: |
9/8/2010 5:17:00 PM |
Date Submitted: |
7/30/2010 10:03:00 AM |
|
Year: |
2010
|
Ship/Facility: |
Robert Gordon Sproul
|
Optimum Start Date:
|
8/25/2010 |
Dates to Avoid: |
|
|
|
|
|
Earliest Start Date: |
8/25/2010 |
Multi-Ship Op: |
No |
Latest Start Date: |
8/27/2010 |
Other Ship(s): |
|
|
Operating Days Needed: |
Science Days |
Mob Days |
De-Mob Days |
Estimated Transit Days |
Total Days |
2 |
0 |
0 |
1 |
3 |
Repeating Cruise?
(within same year) |
No |
Interval: |
|
# of Cruises: |
|
|
Description of Repeating cruise requirements: |
|
Justification/Explanation for ship choice, dates,
conflicts, number of days & multi-ship operations: |
Dates are dependent on the availability of the SGORE range and can't be adjusted |
|
Short Description of Op Area
for use in schedules: |
North SOAR T1,2 |
Description of Op Area: |
North SOAR ranges T1 and T2 West of San Clemente Island |
Op Area Size/Dia.: |
100 |
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
|
|
|
Ending
|
|
|
|
|
|
Foreign Clearance Required? |
No |
Coastal States:
|
Important Info on Foreign Research Clearances
|
|
Are you or any member in your science party bringing in any science equipment items which are regulated for export by the International Traffic in Arms Regulations (ITAR) and/or the Export Administration Regulations (EAR)?
|
No |
If yes, have you applied for the necessary permits through your export control office?
|
No |
Questions about ITAR/EAR regulations?
|
Comments about foreign clearance requirements or description of any other special permitting requirements (e.g., MMPA, ESA, IHA, Marine Sanctuaries, etc.) |
|
|
Requested Start Port |
Intermediate Port(s) |
Requested End Port |
San Diego, CA, USA |
None |
San Diego, CA, USA |
Explanation/justification for requested ports and dates of intermediate stops or to list additional port stops |
|
Important Info on Working in Foreign Ports
|
|
|
Chief Scientist: |
Lee Freitag, WHOI |
# in Science Party |
3 |
# of different science teams |
1 |
# Marine Technicians to be
provided by ship operator:
(include in science party total)
|
1 |
Explanation of Science Party Requirements and Technician Requirements |
|
|
Dynamic Positioning | ADCP | Multibeam | Seismic |
Dredging/Coring/Large Dia. Trawl Wire | Stern A-frame | Fiber Optic (.681) | 0.680 Coax Wire |
SCUBA Diving | Radioisotope use - briefly describe | NO Radioisotope use/Natural level work | Other Operator Provided Inst. - Describe |
0 PI-Provided Vans - briefly describe | MOCNESS | | |
|
Explain Instrumentation or Capability requirements that could affect choice of ship in scheduling. |
|
|
|
Explain Major Ancillary Facilities Requirements and list description and provider for "other" systems. |
|
|