View Schedule

or schedule as:
the schedule as:
  2018 - Atlantis  
Version 13
Final - ID #13726    Version #4 - 1/7/2019

Scheduling Contact(s)
Kerry Strom kstrom*%*%*whoi^%^%^edu (508) 289-3938

  Notes:   11/19: Atlantis arrived 1 day early to San Diego (19th instead of the 20th) will use the extra day for demobe.
11/16: 1 day early departure d/t berth availability
11/8: Departed for Guaymas on the 7th instead of the 8th to make up for transit mistake (7 days were allocated when 8 were needed).
11/1: 1 day later arrival into Puntarenas (Oct 14th), 1 day added to NSF-OCE-BIO" on the transit and 1 day removed from the same on the load.
10/8: Departing San Juan 1 day later d/t thruster issue. ETA Costa Rica holding. (In port charged 1 more day to BIO, removed 1 transit day from BIO (breakeven).
8/8: "Alvin/LARS NAVSEA Survey has been officially
rescheduled from July 2018 to the week of 07 January 2019 (in the
shipyard)."
5/15: Take 1 of Cordes' mobe days & Sentry's eng dive days (to MGG) over to San Juan for 2 additional PREmobe days for PAC cruises.
Added 1 outreach days in San Diego.
Hopefully will get to San Diego in time for the Outreach event.
3/22: Gregg cruise awarded 1 more day for Alvin dives.
1/12: Return from OOI AB Jan 20th (not the 21st)
Made Jan 24th a load day for the deadhead transit until we know what happens in Monte w/ the USCG inspection.
1/8: Departed Monte 2 days early. Hope to catch USCG inspection on the 21st.
12/20: Navy releases AT from search/ demobe on Jan 1st. 3 day shift to the right.
12/14: Additional delay w/ Sub Search
11/30: Koppers deferred OOI AB back on after CURV ops
11/22: Gregg funded 3 additional days and dmobe in San Diego, ADDED 1 more day of transit to get to 9N (Station 2).
10/13: Adams cruise will be planned as 15 days until the 5 remaining days are funded to make it 20.
9/26: Lyle requests 2 mobe days instead of the 1 originally requested on STR.
9/14: Add Sentry 3 Eng Dives to Alvin Cruise, minus 1 day from Kurz, + 1 day to Cordes
9/8: End Hutchins in San Juan 5 days total in port for demobe/ mobe Behrenfeld
8/30: No deadhead to WHOI $
9/5: Shift Koppers 3 days to the left for the OOI AB -3 days.
7/28: Eason "W" (34 days)
7/17: Demobe Lang in PR to save on deadhead transit (3 days overall savings)
6/30: Moved Lang to the left 1 week to get Jason 2 weeks to transit from Bermuda to WA (Tivey on Ride)
5/31: Orcutt w/ Jason on Ride
4/6: Need to add time at WHOI for ABS and in Astoria for Navsea???
4/3: End Hutchins in Barbados
2/21: June NAVSEA Ext. Cert. Survey (5 days) WHOI
2/20: Hutchin's IN/ Saito & Hodgekiss OUT (Armstrong)
1/31: Corrected Johns voyage from 2015-18
-Cordes wants his 2017 cruise 14 months before the 2018 cruise.
12/29: S. Lang Cayman DECLINED, Karson & Wanless "W"
  View Summary     Set Default Associated Cruises
Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:30 Dec 2017
Dep:30 Dec 2017
Arr:03 Jan 2018
Unload:03 Jan 2018
 
Comodoro Rivadavia, Argentina
Montevideo, Uruguay
 
None/ Deadhead/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Tim Schnoor
Transit Cruise
  3/3

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Deadhead Not Specified 3/NAVY-ONR/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:04 Jan 2018
Dep:05 Jan 2018
Arr:20 Jan 2018
Unload:23 Jan 2018
 
Montevideo, Uruguay
Montevideo, Uruguay
 
Argentine Basin/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Sebastien Bigorre
  16/20

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
OOI Argentine Basin Weller OOI Project Team/WHOI OOI MREFC 20/NSF-OOI-OOI/F
 
Notes: Labor Holiday Schedule: Half Day 12/24, Off 12/25, Half Day 12/31, Off 1/1

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:24 Jan 2018
Dep:24 Jan 2018
Arr:07 Feb 2018
Unload:07 Feb 2018
 
Montevideo, Uruguay
Praia, Sao Tiago, Cape Verde Islands
 
None/ Deadhead/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Rose M. Dufour
Transit Cruise
  15/15

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Deadhead Not Specified 15/NSF-OCE-BIO/F
 
Notes: Funding changed as per email Jan 3rd.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:08 Feb 2018
Dep:11 Feb 2018
Arr:14 Mar 2018
Unload:16 Mar 2018
 
Praia, Sao Tiago, Cape Verde Islands
San Juan, Puerto Rico
 
Atlantic/
NA10
NA09
 
 
 
14N/24W
15N/60W
 
  David Hutchins
  32/37

Clearances: Cape Verde(A)
 
Project PI/Institution Project # Days/Agency/Status
Colimited N-fixers David Hutchins/USC 1657757 37/NSF-OCE-BIO/F
 
Notes: 12/15: Took 1 day out of Hutchins science time to account for Navy Sub Search delays. Let's see if it holds? 5/10: Hutchins stated transit time is wrapped up in his science days.

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:17 Mar 2018
Dep:20 Mar 2018
Arr:13 Apr 2018
Unload:15 Apr 2018
 
San Juan, Puerto Rico
Woods Hole, MA, USA
 
NAMES/
NA06
NA06
 
 
 
41N/70W
41N/70W
 
  Michael J. Behrenfeld
  25/30

Clearances: Canada(A), Greenland(A)
 
Project PI/Institution Project # Days/Agency/Status
NAAMES Michael J. Behrenfeld/OSU_Oregon State Not Specified 28/NASA/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:16 Apr 2018
Dep:16 Apr 2018
Arr:24 Apr 2018
Unload:24 Apr 2018
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Albert Suchy
Standby Days
  9/9

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
9 days Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:25 Apr 2018
Dep:28 Apr 2018
Arr:08 May 2018
Unload:08 May 2018
 
Woods Hole, MA, USA
St. George's, Bermuda
 
>70M dpth/
NA06
NA06
 
 
 
40N/70W
40N/70W
 
  W. Bruce Strickrott
  11/14

Clearances: Bermuda(T), NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
2018 Alvin Engineer Andrew D. Bowen/WHOI Not Specified 4/NSF-OCE-IPS/F
2018 Eng Dives Carl Kaiser/WHOI Not Specified 3/NSF-OCE-IPS/F
Sentry Eng Dive Carl Kaiser/WHOI Not Specified 3/NSF-OCE-IPS/F
Alvin Eng Dive Not Specified 1/NAVY-ONR/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:09 May 2018
Dep:11 May 2018
Arr:10 Jun 2018
Unload:11 Jun 2018
 
St. George's, Bermuda
St. George's, Bermuda
 
Volitales/
NA10
NA10
 
 
 
13N/45W
13N/45W
 
  Mark D. Kurz
  31/34

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Mantle Volatiles Mark D. Kurz/WHOI 1259218 34/NSF-OCE-MGG/F
Alvin/ Sentry/ MISO Not Specified 0/OTHER/F
 
Notes: St George to Start = 1575nm/11/24 = 6 days

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:12 Jun 2018
Dep:14 Jun 2018
Arr:17 Jul 2018
Unload:18 Jul 2018
 
St. George's, Bermuda
Woods Hole, MA, USA
 
NW Atlantic/
NA06
NA04
 
 
 
40N/49W
53N/42W
 
  Mitchell Lyle
  34/37

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Survey for IODP WNAT Mitchell Lyle/CEOAS OSU 1656960 36/NSF-OCE-MGG/F
 
Notes: St. Georges to Job Start- 1610NM/ 11/ 24 = 6 days Job Finish to WHOI - 675NM/ 11/ 24 = 3 days

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:19 Jul 2018
Dep:19 Jul 2018
Arr:27 Jul 2018
Unload:27 Jul 2018
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Albert Suchy
Standby Days
  9/9

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
9 days Not Specified 0/OTHER/NonOp

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:28 Jul 2018
Dep:28 Jul 2018
Arr:15 Aug 2018
Unload:15 Aug 2018
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Albert Suchy
Maintenance
  19/19

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
19 days Not Specified 0/OTHER/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:16 Aug 2018
Dep:19 Aug 2018
Arr:02 Sep 2018
Unload:03 Sep 2018
 
Woods Hole, MA, USA
Woods Hole, MA, USA
 
VA, NC, SC, GA/
NA06
NA06
 
 
 
37N/73W
30N/78W
 
  Caitlin Adams
  15/19

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
SAB Deepwater Caitlin Adams/NOAA/OER Not Specified 15/NOAA-OE/F
Alvin Not Specified 0/OTHER/F
 
Notes: 10/13: Adams cruise will be planned as 15 days until the 5 remaining days are funded to make it 20. Caitlin Adams: "So I received a rather definitive answer from Erik over the weekend regarding the potential schedule change to June. Unfortunately, I don't think it would work. This cruise will hinge on data collection by other ships in the area in both April and June, so the team would have the most success if they had time to process that data before an August departure."

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:04 Sep 2018
Dep:08 Sep 2018
Arr:01 Oct 2018
Unload:03 Oct 2018
 
Woods Hole, MA, USA
San Juan, Puerto Rico
 
Lost City 2014/
NA06
NA06
 
 
 
30N/42W
30N/42W
 
  Susan Lang
  24/30

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Lost City 2014 Susan Lang/SC 1536702 26/NSF-OCE-BIO/F
Jason Not Specified 0/OTHER/F
 
Notes: Transits: 11 days total WHOI to Jobsite = 1575nm/11/24 = 6 days Jobsite to St.George's = 1175nm/11/24 = 5 days Jobsite to SanJuan = 1500nm/11/24 = 6 days

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:04 Oct 2018
Dep:04 Oct 2018
Arr:06 Oct 2018
Unload:06 Oct 2018
 
San Juan, Puerto Rico
San Juan, Puerto Rico
 
0/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Sarah Fuller
  3/3

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Pre-Mobe PAC work Not Specified 2/NSF-OCE-BIO/F
Pre-Mobe PAC work Not Specified 1/NSF-OCE-MGG/F
 
Notes: Transits: 11 days total WHOI to Jobsite = 1575nm/11/24 = 6 days Jobsite to St.George's = 1175nm/11/24 = 5 days Jobsite to SanJuan = 1500nm/11/24 = 6 days

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:07 Oct 2018
Dep:07 Oct 2018
Arr:14 Oct 2018
Unload:14 Oct 2018
 
San Juan, Puerto Rico
Puntarenas, Costa Rica
 
Deadhead/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Kerry Strom
Transit Cruise
  8/8

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Deadhead Not Specified 4/NSF-OCE-BIO/F
Deadhead Not Specified 4/NSF-OCE-MGG/F
 
Notes: SanJuan-Colon = 1000nm/11/24 = 4 days Transit = 2 days Panama-Puntarenas = 500nm/11/24 = 2 days Diversion from Bermauda to P.R. to demobe and transit saved 4 days! (was 12 now 8) But added a day to Lang transit Astoria, OR to SCRIPPS = 1000nm/ 11 / 24 = 4 days

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:15 Oct 2018
Dep:16 Oct 2018
Arr:06 Nov 2018
Unload:06 Nov 2018
 
Puntarenas, Costa Rica
Puntarenas, Costa Rica
 
Costa Rica/
NP13
NP13
 
 
 
9N/84W
9N/84W
 
  Erik Cordes
  22/23

Clearances: Costa Rica(A)
 
Project PI/Institution Project # Days/Agency/Status
Costa Rica seeps Erik Cordes/Temple 1635219 23/NSF-OCE-BIO/F
Alvin/ Sentry Not Specified 0/OTHER/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:07 Nov 2018
Dep:07 Nov 2018
Arr:14 Nov 2018
Unload:14 Nov 2018
 
Puntarenas, Costa Rica
Guaymas, Mexico
 
Deadhead/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Daniel J. Fornari
Transit Cruise
  8/8

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Deadhead Not Specified 5/NSF-OCE-BIO/F
Deadhead Not Specified 3/NSF-OCE-MGG/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:15 Nov 2018
Dep:16 Nov 2018
Arr:29 Nov 2018
Unload:30 Nov 2018
 
Guaymas, Mexico
Manzanillo, Mexico
 
Guaymas Basin/
IN02
IN02
 
 
 
27N/111E
27N/111E
 
  Andreas P. Teske
  14/16

Clearances: Mexico(T), NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
Guaymas Basin Andreas P. Teske/UNC_CH OCE-1357238 16/NSF-OCE-BIO/F
Alvin/ Sentry Not Specified 0/OTHER/F
 
Notes: Premobe at WHOI in Sept. (During "Available" Period) Demobe in US Dry Dock Port Only 1 day mobe in Guaymas needed d/t the preloading at WHOI Transit total 8 days Puntarenas, CR to Job = 1930nm/ 11 /24 = 7 days + 1 day to Guaymas, MX

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:01 Dec 2018
Dep:03 Dec 2018
Arr:19 Dec 2018
Unload:21 Dec 2018
 
Manzanillo, Mexico
San Diego, CA, USA
 
8 20N EPR/
NP13
NP13
 
 
 
8N/104W
8N/107W
 
  Patricia Gregg
  17/21

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
OASIS Patricia Gregg/UIUC 1356610 11/NSF-OCE-MGG/F
EPR ECS Cruise Patricia Gregg/UIUC 1834797 10/NSF-OCE-IPS/F
Alvin/ Sentry Not Specified 0/OTHER/F
 
Notes: 11/13 email: 9° 50N for 4 days of work following the Gregg et al. 8° 20'N seamount dives, and then transiting directly to San Diego Manz to 1st station = 3 days Last station to San Diego is 1575nm/ 11/ 24 = 6 days

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:22 Dec 2018
Dep:22 Dec 2018
Arr:22 Dec 2018
Unload:22 Dec 2018
 
San Diego, CA, USA
San Diego, CA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Daniel J. Fornari
Outreach
  1/1

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
EPR ECS Cruise Patricia Gregg/UIUC 1834797 1/NSF-OCE-IPS/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:23 Dec 2018
Dep:23 Dec 2018
Arr:25 Dec 2018
Unload:25 Dec 2018
 
San Diego, CA, USA
Mare Island, CA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Timothy Twomey
Transit Cruise
  3/3

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
3/ Non Op Not Specified 0/OTHER/F

Dates   Ports   Area/Navy Op   Lat/Lon   Chief Scientist   Activity/Total Days
Load:26 Dec 2018
Dep:26 Dec 2018
Arr:31 Dec 2018
Unload:31 Dec 2018
 
Mare Island, CA, USA
Mare Island, CA, USA
 
None/
SA02
SA02
 
 
 
0N/0E
0N/0E
 
  Albert Suchy
Maintenance
  6/6

Clearances: NONE(T)
 
Project PI/Institution Project # Days/Agency/Status
DryDock TBD Not Specified 0/OTHER/F
Agency   Funded   Pending   Total
NASA   28   0   28
NAVY   4   0   4
NOAA   15   0   15
NSF   238   0   238
NSF-OOI   20   0   20
OTHER   0   0   0
Total  305 0 305
<
Day Type   Total
Transit Cruise   37
Standby Days   18
Maintenance   25
At Sea for Science   244
Outreach   1
Total  325
<
Load/Unload Days   Total
ChargeLoad   18
ChargeUnload   12
NonChargeLoad   7
NonChargeUnload   3
Total  40