Project Title: |
Development of a large-aperture coherent hydrophone array hardware system, and data processing and analysis software system for instantaneous wide-area passive acoustic monitoring of ocean environments |
Project Status: |
Submitted |
Principal Investigator: |
Purnima R. Makris, Nthest U |
Project Institution: |
Nthest U |
Project ID: |
105692 |
Version #: |
1 |
Date Submitted: |
2/11/2017 11:26:00 AM |
Created By: |
Purnima R. Makris |
Date Last Modified: |
9/12/2018 11:04:00 AM |
URI Serial #: |
None |
Funding Agencies: |
NSF/OCE/OTIC - 1736749 - Funded |
Summary of Field Work: |
Two Intermediate and one final testing of coherent hydrophone array hardware.
First test : Prototype array testing for confirming hardware and software parameters
Second test : Intermediate hardware and software testing of a subaperture of the full system. We will complete construction of one subaperture containing 64 hydrophones and the auxillary sensors prior to this sea test.
3rd test: Final hardware and software testing with all four subapertures and functionality of the full system. We will complete construction of all four subapertures containing 160 hydrophones in total and all auxillary sensors prior to this sea test. |
Summary of Facility Requirements: |
CTD/XBT and multibeam/echosounder data will be collected. Will require crane to lift the full array system during mob and demob. |
Summary of other requirements and comments: |
|
|
Type of Request: |
Primary Ship Use |
Request Status: |
Submitted |
Request ID: |
1009215 |
Created By: |
Purnima R. Makris |
Date Last Modified: |
2/11/2017 11:26:00 AM |
Date Submitted: |
2/11/2017 11:26:00 AM |
|
Year: |
2017
|
Ship/Facility: |
Endeavor
|
Optimum Start Date:
|
9/21/2017 |
Dates to Avoid: |
|
|
|
|
|
Earliest Start Date: |
9/15/2017 |
Multi-Ship Op: |
No |
Latest Start Date: |
9/29/2017 |
Other Ship(s): |
|
|
Operating Days Needed: |
Science Days |
Mob Days |
De-Mob Days |
Estimated Transit Days |
Total Days |
13 |
1 |
1 |
2 |
17 |
Repeating Cruise?
(within same year) |
No |
Interval: |
|
# of Cruises: |
|
|
Description of Repeating cruise requirements: |
|
Justification/Explanation for ship choice, dates,
conflicts, number of days & multi-ship operations: |
|
|
Short Description of Op Area
for use in schedules: |
Gulf of Maine |
Description of Op Area: |
Gulf of Maine is in the US East coast and is close to Boston. Marine mammals are abundant in the Gulf of Maine in Sep/Oct. We will test our hydrophone array system by recording the whale vocalizations that span a wide range of frequencies. |
Op Area Size/Dia.: |
50 |
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
|
|
|
Ending
|
42° 30' N
/
68° 30' W
map
|
|
|
|
Show Degrees Minutes |
|
|
|
|
Foreign Clearance Required? |
No |
Coastal States:
|
Important Info on Foreign Research Clearances
|
|
Are you or any member in your science party bringing in any science equipment items which are regulated for export by the International Traffic in Arms Regulations (ITAR) and/or the Export Administration Regulations (EAR)?
|
No |
If yes, have you applied for the necessary permits through your export control office?
|
No |
Questions about ITAR/EAR regulations?
|
Comments about foreign clearance requirements or description of any other special permitting requirements (e.g., MMPA, ESA, IHA, Marine Sanctuaries, etc.) |
|
|
Requested Start Port |
Intermediate Port(s) |
Requested End Port |
Narragansett, RI, USA |
None |
Narragansett, RI, USA |
Explanation/justification for requested ports and dates of intermediate stops or to list additional port stops |
RV Endeavor has Narragansett as its home port. This location is easily accessible for us from Boston. |
Important Info on Working in Foreign Ports
|
|
|
Chief Scientist: |
Purnima R. Makris, Nthest U |
# in Science Party |
14 |
# of different science teams |
1 |
# Marine Technicians to be
provided by ship operator:
(include in science party total)
|
1 |
Explanation of Science Party Requirements and Technician Requirements |
Science party will include PI and graduate and undergraduate students from Northeastern University and MIT.
The prototype array we are bringing on board comprises of a winch and a 100 m tow cable with hydrophone sensors. We will tow the array behind the ship at 4 knots. Help is needed from the crew to assist us in deploying and retrieving the array.
In addition to our towed array data, we will also collect data with shipboard CTD/XBT and echosounders. We will require a ship Science Tech to train us in operating the CTD/XBT and echosounders. |
|
Dynamic Positioning | ADCP | Multibeam | Seismic |
Dredging/Coring/Large Dia. Trawl Wire | Stern A-frame | Fiber Optic (.681) | 0.680 Coax Wire |
SCUBA Diving | Radioisotope use - briefly describe | NO Radioisotope use/Natural level work | Other Operator Provided Inst. - Describe |
0 PI-Provided Vans - briefly describe | MOCNESS | | |
|
Explain Instrumentation or Capability requirements that could affect choice of ship in scheduling. |
N/A
|
|
|
Explain Major Ancillary Facilities Requirements and list description and provider for "other" systems. |
|
|