Baseline Site Condit
-
2008
-
Melville
|
|
|
Project Title: |
Baseline Site Condition Survey, ODMDS, Offshore of Apra Harbor, Guam, USA |
Project Status: |
Submitted |
Principal Investigator: |
Andrew Martin, Weston |
Project Institution: |
Weston |
Project ID: |
101117 |
Version #: |
2 |
Date Submitted: |
5/8/2007 7:43:00 PM |
Created By: |
Andrew Martin |
Date Last Modified: |
7/30/2007 3:59:00 PM |
URI Serial #: |
20070507132817AL |
Funding Agencies: |
NAVY - NONE - Funded |
Summary of Field Work: |
|
Summary of Facility Requirements: |
Flexible on ship scheduling. Would like to see work completed between November 01, 2007 and January 31, 2008. |
Summary of other requirements and comments: |
Sediment samples to be collected with boxcore, double vanveen or multicore device for sediment chemistry, benthic community assessment (macroinfauna and meiofauna), potential laboratory based bioaccumulation study. CTD and Rosette with Niskin bottles. Fish (beam) trawls (to be provided by principal investigators). Two current meter moorings to be deployed (approximately 7,500 ft of line with 2,000 lbs anchor weight and 5 instruments spaced equally. Current meter moorings to be retrieved at a later date with a vessel of opportunity based in Guam. RV not required for retrieval. Fish traps set and retrieved using acoustic releases. Refrigerated vans not a required component, alternate methods of storage can be used if not vans not available. |
|
Type of Request: |
Primary Ship Use |
Request Status: |
Submitted |
Request ID: |
1001332 |
Created By: |
Andrew Martin |
Date Last Modified: |
5/18/2007 8:09:00 PM |
Date Submitted: |
5/18/2007 8:09:00 PM |
|
Year: |
2008
|
Ship/Facility: |
Melville
|
Optimum Start Date:
|
1/1/2008 |
Dates to Avoid: |
Flexible on ship scheduling. Would like to see work completed between November 01, 2007 and January 31, 2008. However, these dates are optimum dates and we are definitely flexible in our ship scheduling in order to preferrably use the RV Melville and take advantage of "ship dead time" and ONR funding assistance as conveyed to our client (PACDIV Naval Facilities Engineering Command) by ONR. Cruise dates from 1/01/08 to 4/30/08 will be considered. |
|
|
|
|
Earliest Start Date: |
11/15/2007 |
Multi-Ship Op: |
No |
Latest Start Date: |
4/30/2008 |
Other Ship(s): |
|
|
Operating Days Needed: |
Science Days |
Mob Days |
De-Mob Days |
Estimated Transit Days |
Total Days |
20 |
0 |
0 |
0 |
20 |
Repeating Cruise?
(within same year) |
No |
Interval: |
|
# of Cruises: |
|
|
Description of Repeating cruise requirements: |
|
Justification/Explanation for ship choice, dates,
conflicts, number of days & multi-ship operations: |
Optimum date: 1/01/08 - 1/31/08 Alternate dates 2/01/08 - 4/30/08
Melville Request is an alternative to the POINT SUR request, will use one or the other ship. |
|
Short Description of Op Area
for use in schedules: |
|
Description of Op Area: |
|
Op Area Size/Dia.: |
|
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
|
|
|
Ending
|
|
|
|
|
Show Degrees Minutes |
|
|
|
|
Foreign Clearance Required? |
No |
Coastal States:
|
Important Info on Foreign Research Clearances
|
|
Are you or any member in your science party bringing in any science equipment items which are regulated for export by the International Traffic in Arms Regulations (ITAR) and/or the Export Administration Regulations (EAR)?
|
No |
If yes, have you applied for the necessary permits through your export control office?
|
No |
Questions about ITAR/EAR regulations?
|
Comments about foreign clearance requirements or description of any other special permitting requirements (e.g., MMPA, ESA, IHA, Marine Sanctuaries, etc.) |
|
|
Requested Start Port |
Intermediate Port(s) |
Requested End Port |
Apra Harbor, Guam |
None |
Apra Harbor, Guam |
Explanation/justification for requested ports and dates of intermediate stops or to list additional port stops |
|
Important Info on Working in Foreign Ports
|
|
|
Chief Scientist: |
Andrew Martin, Weston |
# in Science Party |
5 |
# of different science teams |
1 |
# Marine Technicians to be
provided by ship operator:
(include in science party total)
|
1 |
Explanation of Science Party Requirements and Technician Requirements |
David Moore, PhD Weston Solutions 760-795-6956 david.moore@westonsolutions.com Brian Riley Weston Solutions |
|
Dynamic Positioning | ADCP | Multibeam | Seismic |
Dredging/Coring/Large Dia. Trawl Wire | Stern A-frame | Fiber Optic (.681) | 0.680 Coax Wire |
SCUBA Diving | Radioisotope use - briefly describe | NO Radioisotope use/Natural level work | Other Operator Provided Inst. - Describe |
0 PI-Provided Vans - briefly describe | MOCNESS | | |
|
Explain Instrumentation or Capability requirements that could affect choice of ship in scheduling. |
|
|
|
Explain Major Ancillary Facilities Requirements and list description and provider for "other" systems. |
|
|