Ship Request

STR Management has moved to MFP

The US Academic Research Fleet is moving to Marine Facilities Planning (MFP) for scheduling initially and eventually cruise planning.

For all NEW or RESUBMITTED Projects/Ship Time Requests, go to https://mfp.us and create a new SME. Some STRs for projects starting in 2022 and beyond have already been moved to Marine Facilities Planning (mfp.us). Check your MFP Science Portal for any projects that might already be moved. If you need to make edits to projects that begin in 2022 and beyond, please contact mfp@unols.org for assistance. Be sure to indicate the Project and STR IDs that you would like to edit. For more information on getting into MFP, see the More Information button below.

  SCS traps recovery  -  2009  -  Melville  
  Project Information  
Project Title: Recovery of South China Sea sediment trap mooring.

Co-PIs: Martin Wiesner, University of Hamburg
Alyssa Alampay, University of the Philippines
Project Status: Submitted
Principal Investigator: Pierre Flament, UH_SOEST Project Institution: UH_SOEST
Project ID: 101747 Version #: 6
Date Submitted: 9/5/2008 4:58:00 PM Created By: Pierre Flament
Date Last Modified: 9/18/2008 5:42:00 PM URI Serial #: None
Funding Agencies: NSF/OCE/EDU - NSF-barter - Funded
NAVY/ONR - ONR-PO - Funded
Summary of Field Work: Recover one sediment trap moorings lost in the South China Sea west of Luzon with exhausted release batteries
Summary of Facility Requirements: trawl winch, grapnels for deep operation (3), dynamic positioning, P-code GPS, deck cranes, deck space for 20' container, multibeam, VHF RDF at 156.625 MHz
Summary of other requirements and comments: Use scheduled transit for Melville from Manila to Kaoshiung, March 2009
Ship Request Identification
Type of Request: Primary Ship Use Request Status: Submitted
Request ID: 1002435 Created By: Pierre Flament
Date Last Modified: 9/18/2008 5:42:00 PM Date Submitted: 9/5/2008 4:58:00 PM
Requested Ship, Operating Days and Dates
Year: 2009 Ship/Facility: Melville
Optimum Start Date: 3/29/2009 Dates to Avoid: dates flexible, should follow Gordon cruise, using transit from Manila to Kaohsiung
 
 
Earliest Start Date: 3/29/2009 Multi-Ship Op: No
Latest Start Date:   Other Ship(s):

Operating Days Needed: Science Days Mob Days De-Mob Days Estimated Transit Days Total Days
2 0 0 3 5
Repeating Cruise?
(within same year)
No Interval:   # of Cruises:  

Description of Repeating cruise requirements:
Justification/Explanation for ship choice, dates,
conflicts, number of days & multi-ship operations:
using transit from Manila to Kaohsiung
Work Area for Cruise
Short Description of Op Area
for use in schedules:
South China Sea
Description of Op Area: SCS-NE (to dredge) 119°34.180’ 17°18.590’ 2951 m depth
Op Area Size/Dia.: 20
 
  Lat/Long Marsden Grid Navy Op Area
Beginning
IN02 map
Ending
IN02 map
Foreign Clearance and Permitting Requirements
Foreign Clearance Required? Yes Coastal States:

Philippines
 Important Info on Foreign Research Clearances  

Are you or any member in your science party bringing in any science equipment items which are regulated for export by the International Traffic in Arms Regulations (ITAR) and/or the Export Administration Regulations (EAR)?
No If yes, have you applied for the necessary permits through your export control office? No
 Questions about ITAR/EAR regulations?

Comments about foreign clearance requirements or
description of any other special permitting requirements
(e.g., MMPA, ESA, IHA, Marine Sanctuaries, etc.)
Port Calls
Requested Start Port Intermediate Port(s) Requested End Port
Manila, Philippines None Kao-hsiung, Taiwan
Explanation/justification for requested
ports and dates of intermediate stops
or to list additional port stops
Use existing transit of the Melville to Kaohsiung. Mooring and hydrographic equipment from the Gordon and Lee cruises will remain on board.

 Important Info on Working in Foreign Ports

 
Science Party
Chief Scientist: Pierre Flament, UH_SOEST
# in Science Party 14 # of different science teams 3 # Marine Technicians to be
provided by ship operator:
(include in science party total)
2
Explanation of Science Party Requirements and Technician Requirements mooring specialists and geological oceanographers from University of Hamburg (4), University of the Philippines (4) and University of Hawaii (4)

Observers from Phillipines agencies (2)

Scripps resident technicians (deck only needed) (2)
Instrumentation Requirements That Impact Scheduling Decisions
Selected Dynamic PositioningUnselected ADCPSelected MultibeamUnselected Seismic
Selected Dredging/Coring/Large Dia. Trawl WireUnselected Stern A-frameUnselected Fiber Optic (.681)Unselected 0.680 Coax Wire
Unselected SCUBA DivingUnselected Radioisotope use - briefly describeUnselected NO Radioisotope use/Natural level workSelected Other Operator Provided Inst. - Describe
1 PI-Provided Vans - briefly describe Unselected MOCNESS  
Explain Instrumentation or Capability
requirements that could affect choice
of ship in scheduling.

specialized grapnels for deep water mooring dredging

box corer

VHD RDF at 156.625 MHz

Major Ancillary Facilities (that require coordination of schedules with ship schedule)
Aircraft
Unselected Helicopter Ops (USCG)Unselected Twin OtterUnselected Unmanned Aerial Systems (UAS) 
Autonomous Underwater Vehicle (AUV)
Unselected Other AUVUnselected Sentry  
Coring Facility
Unselected Jumbo Piston CoringUnselected Large Gravity Core Unselected MC800 multicorer w/ MISO camera/telemetryUnselected OSU Coring Facility (MARSSAM)
Unselected Other Large Coring FacilityUnselected WHOI Long Core  
Human Occupied Vehicle (HOV)
Unselected AlvinUnselected Clelia (HBOI)Unselected JSL I & II (HBOI)Unselected Other HOV
Other Facility
Unselected MISO Facility - deep-sea imagingUnselected Other FacilityUnselected Potential Fields Pool Equipment 
Remotely Operated Vehicle (ROV)
Unselected JasonUnselected Other ROV  
Seismic Facility
Unselected Ocean Bottom Seismograph Instrument Center (OBSIC)Unselected Ocean Bottom Seismograph Instrument Pool (OBSIP)Unselected Ocean-Bottom Seismometer Program (UTIG)Unselected Other Seismic/OBS Facility
Unselected PASSCALUnselected Portable MCS groupUnselected Portable MCS/SCS groupUnselected U.S. Geological Survey Ocean Bottom Seismometer Facility (USGS at WHOI)
Towed Underwater Vehicle
Unselected ARGO IIUnselected Hawaii MR1 (HMRG)Unselected IMI12 (HMRG)Unselected IMI120 (HMRG - formerly DSL 120A)
Unselected IMI30 (HMRG)Unselected Other Towed Underwater VehicleUnselected Towfish 
UNOLS Van Pool
Unselected AUV Lab Van #1Unselected Clean Lab VanUnselected Cold Lab VanUnselected General Purpose Lab Van
Unselected Radioisotope Lab VanUnselected Wet Lab Van  
UNOLS Winch Pool
Unselected Mooring SpoolerUnselected Portable WinchUnselected Turn Table 
Explain Major Ancillary Facilities
Requirements and list description
and provider for "other" systems.

Expand request schedules  Associated Schedules

Expand request history Ship Request History