CNP Ratio
-
2013
-
Atlantic Explorer
|
|
|
Project Title: |
Dimensions: Collaborative Research: Biological controls on the Ocean's C:N:P ratio. |
Project Status: |
Submitted |
Principal Investigator: |
Michael W. Lomas, Bigelow |
Project Institution: |
BIOS |
Project ID: |
102529 |
Version #: |
1 |
Date Submitted: |
6/8/2010 6:07:00 AM |
Created By: |
Michael W. Lomas |
Date Last Modified: |
8/6/2010 9:59:00 AM |
URI Serial #: |
None |
Funding Agencies: |
NSF/OCE/BIO - 1045966 - Funded |
Summary of Field Work: |
Field work will involve participation in ocean time-series cruises at BATS and HOT as ancillary users, and our own transect cruises in the North Atlantic and North Pacific as primary users.
Work will be primarily CTD operations, but also perhaps some high volume pump/hydrowire work. |
Summary of Facility Requirements: |
Will require an intermediate class vessel for cruises. We will require, a dedicated radiation van, as well as space for 1 or 2 other 20' research vans. Very clean underway seawater system will be required as well as high volume surface seawater flow for on deck incubators. |
Summary of other requirements and comments: |
|
|
Type of Request: |
Primary Ship Use |
Request Status: |
Submitted |
Request ID: |
1003855 |
Created By: |
Michael W. Lomas |
Date Last Modified: |
6/8/2010 6:07:00 AM |
Date Submitted: |
6/8/2010 6:07:00 AM |
|
Year: |
2013
|
Ship/Facility: |
Atlantic Explorer
|
Optimum Start Date:
|
5/15/2013 |
Dates to Avoid: |
|
|
|
|
|
Earliest Start Date: |
|
Multi-Ship Op: |
No |
Latest Start Date: |
|
Other Ship(s): |
|
|
Operating Days Needed: |
Science Days |
Mob Days |
De-Mob Days |
Estimated Transit Days |
Total Days |
28 |
0 |
0 |
0 |
28 |
Repeating Cruise?
(within same year) |
No |
Interval: |
|
# of Cruises: |
|
|
Description of Repeating cruise requirements: |
|
Justification/Explanation for ship choice, dates,
conflicts, number of days & multi-ship operations: |
We will sample a transect from Bermuda (32N) to roughly ~50N, sampling every degree of latitude both coming and going. Based upon a cruising speed between stations of 9kts, and 4h/station for sampling, we estimate we need 28 days to complete this transect cruise. |
|
Short Description of Op Area
for use in schedules: |
|
Description of Op Area: |
|
Op Area Size/Dia.: |
|
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
|
|
|
Ending
|
|
|
|
|
Show Degrees Minutes |
|
|
|
|
Foreign Clearance Required? |
No |
Coastal States:
|
Important Info on Foreign Research Clearances
|
|
Are you or any member in your science party bringing in any science equipment items which are regulated for export by the International Traffic in Arms Regulations (ITAR) and/or the Export Administration Regulations (EAR)?
|
No |
If yes, have you applied for the necessary permits through your export control office?
|
No |
Questions about ITAR/EAR regulations?
|
Comments about foreign clearance requirements or description of any other special permitting requirements (e.g., MMPA, ESA, IHA, Marine Sanctuaries, etc.) |
|
|
Requested Start Port |
Intermediate Port(s) |
Requested End Port |
St. George's, Bermuda |
None |
St. George's, Bermuda |
Explanation/justification for requested ports and dates of intermediate stops or to list additional port stops |
Based upon the length of the transect, we don't believe we will have to stop at an intermediate port to refuel. |
Important Info on Working in Foreign Ports
|
|
|
Chief Scientist: |
Michael W. Lomas, Bigelow |
# in Science Party |
20 |
# of different science teams |
5 |
# Marine Technicians to be
provided by ship operator:
(include in science party total)
|
2 |
Explanation of Science Party Requirements and Technician Requirements |
Cruise will require around the clock operations, over 28 days so two technicians are required to meet watch standing requirements. |
|
Dynamic Positioning | ADCP | Multibeam | Seismic |
Dredging/Coring/Large Dia. Trawl Wire | Stern A-frame | Fiber Optic (.681) | 0.680 Coax Wire |
SCUBA Diving | Radioisotope use - briefly describe | NO Radioisotope use/Natural level work | Other Operator Provided Inst. - Describe |
1 PI-Provided Vans - briefly describe | MOCNESS | | |
|
Explain Instrumentation or Capability requirements that could affect choice of ship in scheduling. |
We will be doing radioisotope work (phosphorus 33 and carbon 14 for sure, perhaps thymidine 3H as well). The AE has a new radiation van equipped with scintillation counter and is appropriate for our needs.
In addition, if this proposal is funded we will be purchasing a standard 20' UNOLS lab van for our flow cytometry facility. This van can go on the 02deck, bow.
|
|
|
Explain Major Ancillary Facilities Requirements and list description and provider for "other" systems. |
|
|