Lagrangian Study
-
2015
-
Pelican
|
|
|
Project Title: |
A Lagrangian Approach to Study the Gulf of Mexico's Deep Circulation |
Project Status: |
Submitted |
Principal Investigator: |
James J. Singer, leidos |
Project Institution: |
leidos |
Project ID: |
104364 |
Version #: |
1 |
Date Submitted: |
5/1/2014 3:01:00 PM |
Created By: |
James J. Singer |
Date Last Modified: |
5/1/2014 3:01:00 PM |
URI Serial #: |
None |
Funding Agencies: |
BOEM - M10PC00112 - Funded |
Summary of Field Work: |
Three sound source moorings were deployed in US waters and one in Mexican waters in the Gulf of Mexico in July/August 2011. Since then, APEX and RAFOS drifters have been deployed to study ocean circulation at different levels in the water column. The sound source moorings are scheduled for recovery in May/June 2015. |
Summary of Facility Requirements: |
7-8 days of R/V PELICAN with stern A-frame, crane and room on trawl winch drum to handle 5000 m 3/16" jacketed (1/4" diameter) wire rope. |
Summary of other requirements and comments: |
|
|
Type of Request: |
Primary Ship Use |
Request Status: |
Submitted |
Request ID: |
1006970 |
Created By: |
James J. Singer |
Date Last Modified: |
5/1/2014 3:01:00 PM |
Date Submitted: |
5/1/2014 3:01:00 PM |
|
Year: |
2015
|
Ship/Facility: |
Pelican
|
Optimum Start Date:
|
5/12/2015 |
Dates to Avoid: |
Trying to have cruise start date in this window to have sufficient time to get ready for another cruise scheduled for 11-23 June 2015. Also, we are within two months of the manufacturer's stated endurance for the releases on the moorings. |
|
|
|
|
Earliest Start Date: |
5/5/2015 |
Multi-Ship Op: |
No |
Latest Start Date: |
5/12/2015 |
Other Ship(s): |
|
|
Operating Days Needed: |
Science Days |
Mob Days |
De-Mob Days |
Estimated Transit Days |
Total Days |
1 |
0 |
0 |
6 |
7 |
Repeating Cruise?
(within same year) |
No |
Interval: |
|
# of Cruises: |
|
|
Description of Repeating cruise requirements: |
|
Justification/Explanation for ship choice, dates,
conflicts, number of days & multi-ship operations: |
We mobilized and deployed the sound source moorings from the R/V PELICAN in July 2011 and LUMCON is strategically located in the center of the offshore study area where the sound sources were deployed. Ship's crew is very familiar with these type efforts and they and the scientific party have worked together for many years. Total time at sea is expected to be six days, including steaming time and time on station for the three mooring recoveries. Mobilization and demobilization on either end of the cruise should not be more than a few hours. |
|
Short Description of Op Area
for use in schedules: |
N and E GoM |
Description of Op Area: |
93W to 85W 25N to 29N |
Op Area Size/Dia.: |
|
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
29.167° N
/
90.667° W
map
29° 10.02' N
/
90° 40.02' W
map
|
|
|
Ending
|
29.167° N
/
90.667° W
map
29° 10.02' N
/
90° 40.02' W
map
|
|
|
|
Show Degrees Minutes |
|
|
|
|
Foreign Clearance Required? |
No |
Coastal States:
|
Important Info on Foreign Research Clearances
|
|
Are you or any member in your science party bringing in any science equipment items which are regulated for export by the International Traffic in Arms Regulations (ITAR) and/or the Export Administration Regulations (EAR)?
|
No |
If yes, have you applied for the necessary permits through your export control office?
|
No |
Questions about ITAR/EAR regulations?
|
Comments about foreign clearance requirements or description of any other special permitting requirements (e.g., MMPA, ESA, IHA, Marine Sanctuaries, etc.) |
|
|
Requested Start Port |
Intermediate Port(s) |
Requested End Port |
Cocodrie, LA, USA |
None |
Cocodrie, LA, USA |
Explanation/justification for requested ports and dates of intermediate stops or to list additional port stops |
|
Important Info on Working in Foreign Ports
|
|
|
Chief Scientist: |
James J. Singer, leidos |
# in Science Party |
3 |
# of different science teams |
1 |
# Marine Technicians to be
provided by ship operator:
(include in science party total)
|
1 |
Explanation of Science Party Requirements and Technician Requirements |
Support Deck operations: Mooring Recoveries |
|
Dynamic Positioning | ADCP | Multibeam | Seismic |
Dredging/Coring/Large Dia. Trawl Wire | Stern A-frame | Fiber Optic (.681) | 0.680 Coax Wire |
SCUBA Diving | Radioisotope use - briefly describe | NO Radioisotope use/Natural level work | Other Operator Provided Inst. - Describe |
0 PI-Provided Vans - briefly describe | MOCNESS | | |
|
Explain Instrumentation or Capability requirements that could affect choice of ship in scheduling. |
Need A-frame, Crane and Trawl Winch
|
|
|
Explain Major Ancillary Facilities Requirements and list description and provider for "other" systems. |
|
|