Project Title: |
CalCOFI Survey 1501NH, Fisheries Resources Division |
Project Status: |
Submitted |
Principal Investigator: |
David Griffith, NOAA-NMFS |
Project Institution: |
NOAA-NMFS |
Project ID: |
104675 |
Version #: |
3 |
Date Submitted: |
1/9/2015 3:23:00 PM |
Created By: |
David Griffith |
Date Last Modified: |
1/9/2015 8:54:00 PM |
URI Serial #: |
None |
Funding Agencies: |
NOAA/NMFS - NONE - Funded |
Summary of Field Work: |
1. To continue an ongoing assessment of pelagic fish stocks between La Jolla and San Francisco, California.
2. To monitor environmental conditions within the CalCOFI survey area. 3. To conduct continuous underway sampling of surface waters. Temperature, salinity and chlorophyll will be automatically logged by computer with the output from the GPS navigational unit. 4. To record current profiles throughout the duration of the cruise with the Acoustic Doppler Current Profiler (ADCP).
5. To make continuous observations of sea birds and marine mammals. |
Summary of Facility Requirements: |
Supplied by New Horizon: Starboard hydro winch with ¼” cable for standard Bongo, Pairovet and Manta tows Starboard oceo winch with .322" conductive cable Winch monitoring system Seabird thermosalinometer EK-60 Scientific sounder Knudsen 320B/R 12 kHz depth recorder Acoustic Doppler Current Profiler |
Summary of other requirements and comments: |
|
|
Type of Request: |
Primary Ship Use |
Request Status: |
Submitted |
Request ID: |
1007468 |
Created By: |
David Griffith |
Date Last Modified: |
1/9/2015 8:54:00 PM |
Date Submitted: |
1/9/2015 3:40:00 PM |
|
Year: |
2015
|
Ship/Facility: |
New Horizon
|
Optimum Start Date:
|
1/15/2015 |
Dates to Avoid: |
|
|
|
|
|
Earliest Start Date: |
1/15/2015 |
Multi-Ship Op: |
No |
Latest Start Date: |
1/15/2015 |
Other Ship(s): |
|
|
Operating Days Needed: |
Science Days |
Mob Days |
De-Mob Days |
Estimated Transit Days |
Total Days |
25 |
2 |
1 |
0 |
28 |
Repeating Cruise?
(within same year) |
No |
Interval: |
|
# of Cruises: |
|
|
Description of Repeating cruise requirements: |
|
Justification/Explanation for ship choice, dates,
conflicts, number of days & multi-ship operations: |
|
|
Short Description of Op Area
for use in schedules: |
|
Description of Op Area: |
Del Mar, CA to San Francisco, CA and out 400 nautical miles |
Op Area Size/Dia.: |
|
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
32.956° N
/
117.305° W
map
32° 57.36' N
/
117° 18.3' W
map
|
|
|
Ending
|
36.614° N
/
125.771° W
map
36° 36.84' N
/
125° 46.26' W
map
|
|
|
|
Show Degrees Minutes |
|
|
|
|
Foreign Clearance Required? |
No |
Coastal States:
|
Important Info on Foreign Research Clearances
|
|
Are you or any member in your science party bringing in any science equipment items which are regulated for export by the International Traffic in Arms Regulations (ITAR) and/or the Export Administration Regulations (EAR)?
|
No |
If yes, have you applied for the necessary permits through your export control office?
|
No |
Questions about ITAR/EAR regulations?
|
Comments about foreign clearance requirements or description of any other special permitting requirements (e.g., MMPA, ESA, IHA, Marine Sanctuaries, etc.) |
|
|
Requested Start Port |
Intermediate Port(s) |
Requested End Port |
San Diego, CA, USA |
None |
San Diego, CA, USA |
Explanation/justification for requested ports and dates of intermediate stops or to list additional port stops |
|
Important Info on Working in Foreign Ports
|
|
|
Chief Scientist: |
David Griffith, NOAA-NMFS |
# in Science Party |
17 |
# of different science teams |
1 |
# Marine Technicians to be
provided by ship operator:
(include in science party total)
|
1 |
Explanation of Science Party Requirements and Technician Requirements |
|
|
Dynamic Positioning | ADCP | Multibeam | Seismic |
Dredging/Coring/Large Dia. Trawl Wire | Stern A-frame | Fiber Optic (.681) | 0.680 Coax Wire |
SCUBA Diving | Radioisotope use - briefly describe | NO Radioisotope use/Natural level work | Other Operator Provided Inst. - Describe |
3 PI-Provided Vans - briefly describe | MOCNESS | | |
|
Explain Instrumentation or Capability requirements that could affect choice of ship in scheduling. |
|
|
|
Explain Major Ancillary Facilities Requirements and list description and provider for "other" systems. |
|
|