Sentry Mapping EPR
-
2019
-
Atlantis
|
|
|
Project Title: |
Tracking the Run-up to the Next East Pacific Rise (EPR) Volcanic Eruption Near 9° 50’N: 1. Sentry AUV Surveys to Establish the Pre-eruption Surface of the EPR Crest Between 9° 45’-53’N |
Project Status: |
Submitted |
Principal Investigator: |
Daniel J. Fornari, WHOI |
Project Institution: |
WHOI |
Project ID: |
106500 |
Version #: |
2 |
Date Submitted: |
5/21/2019 4:45:00 PM |
Created By: |
Daniel J. Fornari |
Date Last Modified: |
7/23/2019 1:32:00 PM |
URI Serial #: |
None |
Funding Agencies: |
NSF/OCE/BIO - NONE - Funded NSF/OCE/MGG - NONE - Funded |
Summary of Field Work: |
There is an urgent need to more completely map the ‘pre-next’ eruption seafloor in the 9 45’-53’N EPR area, which was subjected to the volcanic eruptions emplaced in 2005-2006. Having the pre-eruption surface will be essential to quantitatively understanding the erupted volume of lava as well as the volcanic emplacement processes associated with a MOR seafloor eruption, and the impacts to the hydrothermal system along this portion of a fast-spreading MOR where so many research experiments have been carried out and which is still a focused area of study for many biologists, chemists and marine geologists. |
Summary of Facility Requirements: |
AUV Sentry with wave glider for 12 days on station. the Wave glider is essential for the Sentry surveys to not negatively impact the conduct of the Alvin diving or RV Atlantis operations at night when Sentry is diving. We would need to use the wave glider from WHOI to ensure good communications and navigation for Sentry. That additional capability is estimated to cost ~$30k and NDSF Sentry group has requested this directly via their facility operations grant.
The Sentry mapping program that would be accomplished during the already funded/planned ~10 days of on-station time that are needed for the Alvin dives to accomplish the Sylvan and Mullineaux field program. That amount of on-station time is sufficient for us to accomplish both the Sylvan off-axis extinct vent mapping and the larger ‘pre-next eruption’ near-bottom multibeam and sidescan mapping with the Sentry AUV. |
Summary of other requirements and comments: |
5 sentry ops team members plus 2 scientists to oversee the Sentry field data acquisition and processing (Fornari and Parnell-Turner). Fornari and Parnell-Turner do not require any additional funding for this data acquisition effort (either travel or salary - we can find internal institution funds to support our work to acquire the data). 2 Sentry operations personnel will be able to berth in Alvin berthing - this has been confirmed by Bruce Strickrott - the Alvin group manager. |
|
Type of Request: |
Collaborative Ship Use |
Request Status: |
Submitted |
Request ID: |
1010485 |
Created By: |
Daniel J. Fornari |
Date Last Modified: |
7/17/2019 3:17:00 PM |
Date Submitted: |
5/21/2019 4:45:00 PM |
|
Year: |
2019
|
Ship/Facility: |
Atlantis
|
Optimum Start Date:
|
12/15/2019 |
Dates to Avoid: |
avoid June through September for EPR 9 50N area due to bad weather |
|
|
|
|
Earliest Start Date: |
12/1/2019 |
Multi-Ship Op: |
No |
Latest Start Date: |
2/1/2020 |
Other Ship(s): |
n/a |
|
Operating Days Needed: |
Science Days |
Mob Days |
De-Mob Days |
Estimated Transit Days |
Total Days |
2 |
0 |
0 |
0 |
2 |
Repeating Cruise?
(within same year) |
No |
Interval: |
|
# of Cruises: |
1 |
|
Description of Repeating cruise requirements: |
n/a |
Justification/Explanation for ship choice, dates,
conflicts, number of days & multi-ship operations: |
We are requesting the Sentry AUV for mapping during an Alvin dive program to the EPR crest at 9 50N for Jason Sylvan and Lauren Mullineaux. A wave glider is needed so that the Sentry ops do not interfere with the Alvin or RV Atlantis operations. |
|
Short Description of Op Area
for use in schedules: |
EPR 9 50N |
Description of Op Area: |
East Pacific Rise axis between 9 45'-53'N |
Op Area Size/Dia.: |
40 sq nm |
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
9.75° N
/
104.266667° W
map
9° 45' N
/
104° 16.00002' W
map
|
|
|
Ending
|
9.883333° N
/
104.333333° W
map
9° 52.99998' N
/
104° 19.99998' W
map
|
|
|
|
Show Degrees Minutes |
|
|
|
|
Foreign Clearance Required? |
No |
Coastal States:
NONE |
Important Info on Foreign Research Clearances
|
|
Are you or any member in your science party bringing in any science equipment items which are regulated for export by the International Traffic in Arms Regulations (ITAR) and/or the Export Administration Regulations (EAR)?
|
No |
If yes, have you applied for the necessary permits through your export control office?
|
No |
Questions about ITAR/EAR regulations?
|
Comments about foreign clearance requirements or description of any other special permitting requirements (e.g., MMPA, ESA, IHA, Marine Sanctuaries, etc.) |
n/a |
|
Requested Start Port |
Intermediate Port(s) |
Requested End Port |
San Diego, CA, USA |
None |
Manzanillo, Mexico |
Explanation/justification for requested ports and dates of intermediate stops or to list additional port stops |
san diego to load sentry |
Important Info on Working in Foreign Ports
|
|
|
Chief Scientist: |
Daniel J. Fornari, WHOI |
# in Science Party |
7 |
# of different science teams |
3 |
# Marine Technicians to be
provided by ship operator:
(include in science party total)
|
1 |
Explanation of Science Party Requirements and Technician Requirements |
Sentry group is 5 people 2 science team members - Fornari and Parnell-Turner |
|
Dynamic Positioning | ADCP | Multibeam | Seismic |
Dredging/Coring/Large Dia. Trawl Wire | Stern A-frame | Fiber Optic (.681) | 0.680 Coax Wire |
SCUBA Diving | Radioisotope use - briefly describe | NO Radioisotope use/Natural level work | Other Operator Provided Inst. - Describe |
0 PI-Provided Vans - briefly describe | MOCNESS | | |
|
Explain Instrumentation or Capability requirements that could affect choice of ship in scheduling. |
Sentry AUV in conjunction with HOV Alvin operations WHOI Wave glider for Sentry operations
|
|
|
Explain Major Ancillary Facilities Requirements and list description and provider for "other" systems. |
The Sentry mapping program that would be accomplished during the already funded/planned ~12 days of on-station time that are needed for the ROV Jason dives to accomplish the Sylvan and Mullineaux field program. That amount of on-station time is sufficient for us to accomplish both the Sylvan off-axis extinct vent mapping and the larger ‘pre-next eruption’ near-bottom multibeam and sidescan mapping with the Sentry AUV. |
|