ADEON
-
2017
-
Neil Armstrong
|
|
|
Project Title: |
Atlantic Deepwater Ecosystem Observatory Network (ADEON) soundscape study |
Project Status: |
Submitted |
Principal Investigator: |
Jennifer Miksis-Olds, UNH |
Project Institution: |
UNH |
Project ID: |
105265 |
Version #: |
3 |
Date Submitted: |
3/21/2016 4:40:00 PM |
Created By: |
Kyle M. Becker |
Date Last Modified: |
2/21/2017 3:00:00 PM |
URI Serial #: |
None |
Funding Agencies: |
NAVY/ONR - NONE - Funded |
Summary of Field Work: |
Deploy 5 long-term moorings with passive acoustics and full complement of oceanographic and met measurement systems. These moorings will be nominally distributed over a 1000 km line along the 1000 m isobath in the Outer Continental Shelf area of the Altantic off the southeast of the US. The moorings will be deployed and tested over 5 weeks. Long-time series data will be collected over multiple years. After initial deployment it is anticipated that each mooring will need to be visited for serving every 3 months. |
Summary of Facility Requirements: |
Sufficient deck space and lifting capacity for mooring deployments. |
Summary of other requirements and comments: |
|
|
Type of Request: |
Primary Ship Use |
Request Status: |
Submitted |
Request ID: |
1008471 |
Created By: |
Kyle M. Becker |
Date Last Modified: |
2/21/2017 3:00:00 PM |
Date Submitted: |
3/21/2016 4:40:00 PM |
|
Year: |
2017
|
Ship/Facility: |
Neil Armstrong
|
Optimum Start Date:
|
9/1/2017 |
Dates to Avoid: |
n/a |
|
|
|
|
Earliest Start Date: |
8/1/2017 |
Multi-Ship Op: |
No |
Latest Start Date: |
12/1/2017 |
Other Ship(s): |
n/a |
|
Operating Days Needed: |
Science Days |
Mob Days |
De-Mob Days |
Estimated Transit Days |
Total Days |
25 |
5 |
2 |
10 |
42 |
Repeating Cruise?
(within same year) |
Yes |
Interval: |
6 months |
# of Cruises: |
4 |
|
Description of Repeating cruise requirements: |
This request is to deploy moorings. It is anticipated they moorings will need to be revisited for servicing every 3 months by a combination of NOAA and/or UNOLS ships. It may not be R/V Armstrong. |
Justification/Explanation for ship choice, dates,
conflicts, number of days & multi-ship operations: |
Need a large ship for initial mooring deployments. |
|
Short Description of Op Area
for use in schedules: |
OCS - Atlantic |
Description of Op Area: |
Outer Continental Shelf southeast United States - ignore given lat/long |
Op Area Size/Dia.: |
500 |
|
|
|
Lat/Long |
Marsden Grid |
Navy Op Area |
Beginning
|
35.517° N
/
74.363° W
map
35° 31.02' N
/
74° 21.78' W
map
|
|
|
Ending
|
32° 55.2' N
/
75° 24.3' W
map
|
|
|
|
Show Degrees Minutes |
|
|
|
|
Foreign Clearance Required? |
No |
Coastal States:
|
Important Info on Foreign Research Clearances
|
|
Are you or any member in your science party bringing in any science equipment items which are regulated for export by the International Traffic in Arms Regulations (ITAR) and/or the Export Administration Regulations (EAR)?
|
No |
If yes, have you applied for the necessary permits through your export control office?
|
No |
Questions about ITAR/EAR regulations?
|
Comments about foreign clearance requirements or description of any other special permitting requirements (e.g., MMPA, ESA, IHA, Marine Sanctuaries, etc.) |
n/a |
|
Requested Start Port |
Intermediate Port(s) |
Requested End Port |
Charleston, SC, USA |
None, |
Charleston, SC, USA |
Explanation/justification for requested ports and dates of intermediate stops or to list additional port stops |
selected as central to experiment site. not a requirement |
Important Info on Working in Foreign Ports
|
|
|
Chief Scientist: |
Jennifer Miksis-Olds, UNH |
# in Science Party |
1 |
# of different science teams |
1 |
# Marine Technicians to be
provided by ship operator:
(include in science party total)
|
1 |
Explanation of Science Party Requirements and Technician Requirements |
TBD |
|
Dynamic Positioning | ADCP | Multibeam | Seismic |
Dredging/Coring/Large Dia. Trawl Wire | Stern A-frame | Fiber Optic (.681) | 0.680 Coax Wire |
SCUBA Diving | Radioisotope use - briefly describe | NO Radioisotope use/Natural level work | Other Operator Provided Inst. - Describe |
0 PI-Provided Vans - briefly describe | MOCNESS | | |
|
Explain Instrumentation or Capability requirements that could affect choice of ship in scheduling. |
TBD
|
|
|
Explain Major Ancillary Facilities Requirements and list description and provider for "other" systems. |
TBD |
|